Home / Browse projects / Ahmedabad, Gujarat / SHIVANTA ONE

Valid until 28 Jun 2029 Mixed Development project

SHIVANTA ONE

By SHIV DEVELOPERS

RG-GJ-28487 · RERA PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Urban Development Authority/MAA14131/180924/280229 · Last updated on GujRERA portal: 18 Sep 2024

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Jun 2029Possession promisedno revision filed
2 of 18Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 71%
165 of 165Units unsoldnot recorded sold or booked
Jump to the 40 documents Report an error

SHIVANTA ONE is a Mixed Development project by SHIV DEVELOPERS in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Urban Development Authority/MAA14131/180924/280229 on 18 Sep 2024. Possession is promised by 28 Jun 2029. 0 of the 165 units on this registration are recorded sold or booked, and 2 of 18 construction stages are filed complete.

At a glance

Project

  • NameSHIVANTA ONE
  • TypeMixed Development
  • Location
    • SR NO 101/2 MUTHIYA
    • TP NO 75 HANSPURA
    • FP NO 33/2
    • 2206 SQM
    • Hanspura
    • Naroda I E S.O
    • AHMEDABAD
    • Gujarat
    • INDIA
    • 382330
    • MUTHIYA
    • Ahmedabad City
    • ...
  • Pincode382330
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Urban Development Authority/MAA14131/180924/280229
  • ReraGenie IDRG-GJ-28487

Builder

  • NameSHIV DEVELOPERS
  • Entity typePARTNERSHIP FIRM
  • Other registrations48 more →

Key dates

this monthRegisteredSep 2024PromisedJun 2029

Key facts

Registration and timeline

  • StatusValid until 28 Jun 2029
  • Registered on18 Sep 2024
  • Promised completion28 Jun 2029
  • Revised completionNone
  • Buildings2 building records
  • Documents filed40 files

Current status

0%0 of 165 units booked
0.1%Of the estimated cost spent so far

Figures as on 18 Sep 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---841195
B---70070

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building2

As on 18 Sep 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 18 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 71%.

A20%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth5%
Stilt Floor0%
Slabs of Super Structure71%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
B19%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth2%
Stilt Floor0%
Slabs of Super Structure71%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities23

As on 18 Sep 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesNoNot applicable
Emergency evacuationYes0%
Use of renewable energyYes0%
SecurityNoNot applicable
Letter boxYes0%
Compound wallYes0%
Plinth protectionYes0%
Water tankYes0%
Other requirementsYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,206 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 13.25 cr
Cost incurredRs 1.15 lakh
Spent of the estimate0.09%
BuildingWingEstimatedIncurred
ANARs 6.62 crRs 62,190
BNARs 6.62 crRs 53,030

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSiddharth Vitthalbhai Patel
EngineerKIRANKUMAR NARSHIBHAI PATEL

Documents filed40

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Urban Development Authority/MAA14131/180924/280229 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
RERA registration certificate18 Sep 2024
Engineer's certificate (Form 2)4 Sep 2024
Engineer's certificate annexure4 Sep 2024
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Statutory document-
Project photograph-
Proforma sale deed-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

0%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one has not

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep SHIVANTA ONE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near MUTHIYA5,400+ in Ahmedabad

2 kmSHIVANTA ONEOther 242Dot size: filed unitsN

Filed coordinates, straight-line distance. 242 registered projects within 2 km.

Builder: SHIV DEVELOPERS

SHIV DEVELOPERS has 49 registrations on GujRERA, including PRATHAM LUXURIA and SHIV HABITAT. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if SHIVANTA ONE is delayed beyond 28 Jun 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SHIVANTA ONE?

The registered promoter entity is SHIV DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SHIVANTA ONE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SHIVANTA ONE?

The professionals named in the filing: Architect: Siddharth Vitthalbhai Patel; Engineer: KIRANKUMAR NARSHIBHAI PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHIVANTA ONE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHIVANTA ONE. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHIVANTA ONE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.