ReraGenieLog inGet a buyer report

Home / Browse projects / Anand, Gujarat / SHIVALIK SKY LINE

Valid until 30 Jan 2029 Mixed Development project

SHIVALIK SKY LINE

By SHIVALIK BUILDCON

RG-GJ-92285 · RERA PR/GJ/ANAND/ANAND/Anand VallabhVidhyanagar Karmsad Urban Development Authority/MAA15492/100725/300928 · Last updated on GujRERA portal: 2 Oct 2025

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Jan 2029Possession promisedno revision filed
3 of 9Construction stages donefurthest along: Internal walls, 67%
44 of 51Units unsoldnot recorded sold or booked
Jump to the 37 documents Report an error

SHIVALIK SKY LINE is a Mixed Development project by SHIVALIK BUILDCON in Anand, Gujarat, registered with GujRERA as PR/GJ/ANAND/ANAND/Anand VallabhVidhyanagar Karmsad Urban Development Authority/MAA15492/100725/300928 on 10 Jul 2025. Possession is promised by 30 Jan 2029. 7 of the 51 units on this registration are recorded sold or booked, and 3 of 9 construction stages are filed complete.

At a glance

Project

  • NameSHIVALIK SKY LINE
  • TypeMixed Development
  • Location
    • OPP. MAPEL OASIS
    • KARAMSAD
    • KARAMSAD
    • Anand
    • 388325
  • Pincode388325
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/ANAND/ANAND/Anand VallabhVidhyanagar Karmsad Urban Development Authority/MAA15492/100725/300928
  • ReraGenie IDRG-GJ-92285

Builder

  • NameSHIVALIK BUILDCON
  • Entity typePARTNERSHIP FIRM
  • Other registrations1 more →

Key dates

this monthRegisteredJul 2025PromisedJan 2029

Key facts

Registration and timeline

  • StatusValid until 30 Jan 2029
  • Registered on10 Jul 2025
  • Promised completion30 Jan 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed37 files

Current status

14%7 of 51 units booked
45.0%Of the estimated cost spent so far

Figures as on 2 Oct 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---312051

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 2 Oct 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 9 construction stages are filed complete. The stage furthest along is Internal walls, at 67%.

A: 46% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats67%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks28%
External plumbing and external plaster, elevation, completion of terraces with waterproofing17%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities19

As on 2 Oct 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesYes0%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes0%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,737 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 8.10 cr
Cost incurredRs 3.65 cr
Spent of the estimate45.0%
BuildingWingEstimatedIncurred
ANARs 8.10 crRs 3.65 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPriyanka Bhadreshkumar Gajjar
EngineerINDRAJIT PATEL

Documents filed37

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/ANAND/ANAND/Anand VallabhVidhyanagar Karmsad Urban Development Authority/MAA15492/100725/300928 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)2 Oct 2025
Engineer's certificate (Form 2)1 Oct 2025
Engineer's certificate annexure1 Oct 2025
Architect's certificate (Form 1)30 Sep 2025
Site photograph, A30 Sep 2025
RERA registration certificate10 Jul 2025
Proforma agreement for sale-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Drainage affidavit-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Statutory document-
Project photograph-
Proforma sale deed-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Anand

14%of this project is bookeddistrict median 57%
17%of Anand projects moved their completion datethis one has not

Computed across the 310+ Anand projects on ReraGenie, from their own filings.

Keep SHIVALIK SKY LINE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near KARAMSAD310+ in Anand

2 kmSHIVALIK SKY LINEOther 128Dot size: filed unitsN

Filed coordinates, straight-line distance. 128 registered projects within 2 km.

Builder: SHIVALIK BUILDCON

SHIVALIK BUILDCON has 2 registrations on GujRERA, including SHIVALIK -2 and SHIVALIK SKY LINE. Read the full track record. See more projects on the Anand district page.

Frequently asked questions

What are my rights if SHIVALIK SKY LINE is delayed beyond 30 Jan 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SHIVALIK SKY LINE?

The registered promoter entity is SHIVALIK BUILDCON, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SHIVALIK SKY LINE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SHIVALIK SKY LINE?

The professionals named in the filing: Architect: Priyanka Bhadreshkumar Gajjar; Engineer: INDRAJIT PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHIVALIK SKY LINE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHIVALIK SKY LINE. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHIVALIK SKY LINE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.