Home / Browse projects / Surat, Gujarat / SHANTA GODAVARI LUXURY VILLAS
SHANTA GODAVARI LUXURY VILLAS
RG-GJ-53823 · RERA PR/GJ/SURAT/CHORASI/SUDA/RAA00811/EX2/210223 · Last updated on GujRERA portal: 28 Jun 2023
Source: official GujRERA filing
Red flags
- Completion date moved by 24 months
- 2 extensions taken
Clear
- Separate project account declared
Saved.
SHANTA GODAVARI LUXURY VILLAS is a Residential/Group Housing project by SHANTA GODAVARI INFRA in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/CHORASI/SUDA/RAA00811/EX2/210223 on 24 Nov 2017. Possession is promised by 30 Jun 2023. The completion date has moved by 24 months from the original filing. 34 of the 44 units on this registration are recorded sold or booked, and 176 of 176 construction stages are filed complete.
At a glance
Project
- NameSHANTA GODAVARI LUXURY VILLAS
- TypeResidential/Group Housing
- Location
- RS. No 299/2
- tps no. 6
- FP NO 41/1
- VIP ROAD
- VESU
- Vesu
- Chorasi
- Surat
- 394518
- Pincode394518
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR/GJ/SURAT/CHORASI/SUDA/RAA00811/EX2/210223
- ReraGenie IDRG-GJ-53823
Builder
- NameSHANTA GODAVARI INFRA
- Entity typePARTNERSHIP FIRM
Key dates
Key facts
Registration and timeline
- StatusValid until 30 Jun 2023
- Registered on24 Nov 2017
- Promised completion30 Jun 2023
- Revised completionRevised to 30 Jun 2023 (originally 30 Jun 2021)
- Buildings22 building records
- Documents filed58 files
Current status
Figures as on 28 Jun 2023, this project's latest GujRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Unit 1 | - | - | - | 2 | 0 | 2 |
| Unit 2 | - | - | - | 2 | 0 | 2 |
| Unit 3 | - | - | - | 2 | 0 | 2 |
| Unit 4 | - | - | - | 2 | 0 | 2 |
| Unit 5 | - | - | - | 2 | 0 | 2 |
| Unit 6 | - | - | - | 2 | 0 | 2 |
| Unit 7 | - | - | - | 2 | 0 | 2 |
| Unit 8 | - | - | - | 2 | 0 | 2 |
| Unit 9 | - | - | - | 2 | 0 | 2 |
| Unit 10 | - | - | - | 2 | 0 | 2 |
| Unit 11 | - | - | - | 2 | 0 | 2 |
| Unit 12 | - | - | - | 2 | 0 | 2 |
| Unit 13 | - | - | - | 2 | 0 | 2 |
| Unit 14 | - | - | - | 2 | 0 | 2 |
| Unit 15 | - | - | - | 2 | 0 | 2 |
| Unit 16 | - | - | - | 2 | 0 | 2 |
| Unit 17 | - | - | - | 2 | 0 | 2 |
| Unit 18 | - | - | - | 2 | 0 | 2 |
| Unit 19 | - | - | - | 2 | 0 | 2 |
| Unit 20 | - | - | - | 2 | 0 | 2 |
| Unit 21 | - | - | - | 2 | 0 | 2 |
| Unit 22 | - | - | - | 2 | 0 | 2 |
The full filing
Everything below is from the project's own GujRERA filing, free to read.
Construction progress by building20
As on 28 Jun 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 22 buildings; the table lists the first 20.
176 of 176 construction stages are filed complete across 22 buildings.
Unit 1100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Unit 2100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Unit 3100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Unit 4100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Unit 5100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Unit 6100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Unit 7100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Unit 8100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Unit 9100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Unit 10100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Unit 11100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Unit 12100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Unit 13100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Unit 14100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Unit 15100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Unit 16100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Unit 17100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Unit 18100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Unit 19100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Unit 20100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Progress on shared amenities19
As on 28 Jun 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal roads and footpaths | Yes | 100% |
| Water supply | Yes | 100% |
| Sewerage (chamber, lines, septic tank, STP) | Yes | 100% |
| Storm water drains | Yes | 100% |
| Landscaping and tree planting | Yes | 100% |
| Street lighting | Yes | 100% |
| Community buildings | Yes | 100% |
| Treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Water conservation, rain water harvesting | No | Not applicable |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Fire fighting | No | Not applicable |
| Drinking water facilities | No | Not applicable |
| Emergency evacuation | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Security | No | Not applicable |
| Letter box | No | Not applicable |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Unit 1 | NA | Rs 47.19 lakh | Rs 49.27 lakh |
| Unit 2 | NA | Rs 47.19 lakh | Rs 49.27 lakh |
| Unit 3 | NA | Rs 47.19 lakh | Rs 49.27 lakh |
| Unit 4 | NA | Rs 47.19 lakh | Rs 49.27 lakh |
| Unit 5 | NA | Rs 47.19 lakh | Rs 49.27 lakh |
| Unit 6 | NA | Rs 47.19 lakh | Rs 49.27 lakh |
| Unit 7 | NA | Rs 47.19 lakh | Rs 49.27 lakh |
| Unit 8 | NA | Rs 47.19 lakh | Rs 49.27 lakh |
| Unit 9 | NA | Rs 47.19 lakh | Rs 49.27 lakh |
| Unit 10 | NA | Rs 47.19 lakh | Rs 49.27 lakh |
| Unit 11 | NA | Rs 47.19 lakh | Rs 49.27 lakh |
| Unit 12 | NA | Rs 47.19 lakh | Rs 49.27 lakh |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Documents filed58
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/CHORASI/SUDA/RAA00811/EX2/210223 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect's certificate (Form 1) | 28 Jun 2023 |
| Engineer's certificate (Form 2) | 28 Jun 2023 |
| Engineer's certificate annexure | 28 Jun 2023 |
| Accountant's certificate (Form 3) | 28 Jun 2023 |
| Site photograph, Unit 1 | 28 Jun 2023 |
| Site photograph, Unit 2 | 28 Jun 2023 |
| Site photograph, Unit 3 | 28 Jun 2023 |
| Site photograph, Unit 4 | 28 Jun 2023 |
| Site photograph, Unit 5 | 28 Jun 2023 |
| Site photograph, Unit 6 | 28 Jun 2023 |
| Site photograph, Unit 7 | 28 Jun 2023 |
| Site photograph, Unit 8 | 28 Jun 2023 |
| Site photograph, Unit 9 | 28 Jun 2023 |
| Site photograph, Unit 10 | 28 Jun 2023 |
| Site photograph, Unit 11 | 28 Jun 2023 |
| Site photograph, Unit 12 | 28 Jun 2023 |
| Site photograph, Unit 13 | 28 Jun 2023 |
| Site photograph, Unit 14 | 28 Jun 2023 |
| Site photograph, Unit 15 | 28 Jun 2023 |
| Site photograph, Unit 16 | 28 Jun 2023 |
| Site photograph, Unit 17 | 28 Jun 2023 |
| Site photograph, Unit 18 | 28 Jun 2023 |
| Site photograph, Unit 19 | 28 Jun 2023 |
| Site photograph, Unit 20 | 28 Jun 2023 |
| Site photograph, Unit 21 | 28 Jun 2023 |
| Site photograph, Unit 22 | 28 Jun 2023 |
| RERA registration certificate | 24 Nov 2017 |
| Proforma agreement for sale | - |
| Auditor's report (1 of 3) | - |
| Auditor's report (2 of 3) | - |
| Auditor's report (3 of 3) | - |
| Income tax return (1 of 3) | - |
| Income tax return (2 of 3) | - |
| Income tax return (3 of 3) | - |
| Project specific document | - |
| Directors' report (1 of 3) | - |
| Directors' report (2 of 3) | - |
| Directors' report (3 of 3) | - |
| Commencement certificate | - |
| Approved sanctioned plan | - |
| Approved layout plan | - |
| Agreement | - |
| Land location | - |
| Encumbrance certificate | - |
| Area development document | - |
| Proforma allotment letter | - |
| Brochure | - |
| Project related document | - |
| Declaration in Form B | - |
| Audited balance sheet (1 of 3) | - |
| Audited balance sheet (2 of 3) | - |
| Audited balance sheet (3 of 3) | - |
| Audited profit and loss statement (1 of 3) | - |
| Audited profit and loss statement (2 of 3) | - |
| Audited profit and loss statement (3 of 3) | - |
| Cash flow statement (1 of 3) | - |
| Cash flow statement (2 of 3) | - |
| Cash flow statement (3 of 3) | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Surat
Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.
Keep SHANTA GODAVARI LUXURY VILLAS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Vesu2,600+ in Surat
Filed coordinates, straight-line distance. 165 registered projects within 2 km.
HAPPY GOLDMINES SHOPPERS
HAPPY HOME CORPORATION
AVADH ARKELIA
PIONEER CONSTRUCTION COMPANY
HAPPY ELEGANCE
HAPPY HOME CORPORATION
GREEN SIGNATURE SHOPPERS
HAPPY HOME REALTY
EXULT SHOPPERS
EXULT DEVELOPER
Raghuvir Silverstone
RAGHUVIR BUILDERS
See every Surat project, with the district possession charts
Builder: SHANTA GODAVARI INFRA
SHANTA GODAVARI INFRA has 1 registration on GujRERA, including SHANTA GODAVARI LUXURY VILLAS. Read the full track record. See more projects on the Surat district page.
Frequently asked questions
What are my rights if SHANTA GODAVARI LUXURY VILLAS is delayed beyond 30 Jun 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.
How do I verify and contact the developer of SHANTA GODAVARI LUXURY VILLAS?
The registered promoter entity is SHANTA GODAVARI INFRA, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.
Is my payment protected in SHANTA GODAVARI LUXURY VILLAS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
What should I check before booking in SHANTA GODAVARI LUXURY VILLAS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.