Home / Browse projects / Dharwad, Karnataka / SAILAND PARK

Registration approved Residential/Group Housing project

SAILAND PARK

By NEW HOMES REALITY

RG-KA-34394 · RERA PRM/KA/RERA/1259/410/PR/180516/001709

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • No complaints on record
  • Separate project account declared
Dec 2021Possession promisedmoved 9 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 37 documents Report an error

SAILAND PARK is a Residential/Group Housing project by NEW HOMES REALITY in Dharwad, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1259/410/PR/180516/001709 on 16 May 2018. Possession is promised by 31 Dec 2021. The completion date has moved by 9 months from the original filing.

At a glance

Project

  • NameSAILAND PARK
  • TypeResidential/Group Housing
  • Location
    • Dharwad
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1259/410/PR/180516/001709
  • ReraGenie IDRG-KA-34394

Builder

  • NameNEW HOMES REALITY
  • Entity typePartnership Firm
  • Authorized SignatoryS.M.SHIVYOGIMATH
  • OthersS. M. SHIVYOGIMATH
  • Other registrations1 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredMay 2018First promiseMar 2021Revised toDec 2021

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on16 May 2018
  • Promised completion31 Dec 2021
  • Revised completionRevised to 31 Dec 2021 (originally 31 Mar 2021)
  • Buildings1 building record
  • Documents filed37 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SAILAND PARK---40040

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)Not applicable
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawingsNot applicable

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes-
Water conservationYes-
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes-
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
GasNoNot applicable
Water and SanitationNoNot applicable
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,584 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 6.59 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKIRAN UPPAR
EngineerD.L.KULKARNI & ASSOCIATES

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionMar 2021 → Dec 2021

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed37

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1259/410/PR/180516/001709 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: FIRM REGISTRATION.pdf-
RERA 001-
APPROVED PLAN SAILAND-
SITE MAP 001-
NHR-SALE AGREEMENT SAILAND PARK (1)-
NHR-SALE AGREEMENT SAILAND PARK-
saledeed latest-
plan-
ALLOTMENT LETTER-
New homes brochure-
List of Amenities-
sailand park ec-
UTARA 001-
2018-04-13_NA_all-
fire NOC small-
HESCOM NOC 001-
KARNATAKA WATER BOARD NOC 001-
HDMC LICENCE-
sailand plan-
Balance Sheet 2015 - 2016File: 2.jpg-
Audited Profit and Loss Statement 2015 - 2016File: 3.jpg-
Income Tax Return Acknowledgement 2015 - 2016File: 1.jpg-
forn b-
Tower Excel SheetFile: PRM_KA_RERA_1259_410_PR_180516_001709.xlsx-
Stability CertificateFile: Sailand stability Certificate.pdf-
Road cutting permission letter issued by the planning Authority for laying Water supply line, sanitary line, UFile: Road cutting Permission.pdf-
NOC issued by the Fire Force department after completion of workFile: FIRE NOC 25 2 21.pdf-
Occupancy CertificateFile: SAILAND PARK CC.pdf-
Certificate of operation for lifts issued by the Chief of Department of Electrical inspectorate Government of File: Electl inspection for Lift.pdf-
Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: Electl inspection for Tranformer.pdf-
Sanctioned letter issued by concerned water supply and sanitary board for the projectFile: Drinking water connection.pdf-
Architect certificate for having completed the work(in format no 5)File: F5 Architect for completion.pdf-
Chartered Accountant certificate for having completed the work(in format no 4)File: 4 FORM CA SAILAND PARK.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Affidavit cum Declaration.pdf-
Electl inspection for DGFile: Electl inspection for DG.pdf-
HESCOM Sanction letterFile: HESCOM Sanction letter.pdf-
F6 Engineer for completionFile: F6 Engineer for completion.pdf-

How this compares with Dharwad

29%of Dharwad projects moved their completion datethis one moved by 9 months
0%of Dharwad registrations are shown as withdrawn or revokedthis one is not

Computed across the 250+ Dharwad projects on ReraGenie, from their own filings.

Keep SAILAND PARK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dharwad250+ in Dharwad

2 kmSAILAND PARKOther 25Dot size: filed unitsN

Filed coordinates, straight-line distance. 25 registered projects within 2 km.

Builder: NEW HOMES REALITY

NEW HOMES REALITY has 2 registrations on RERA Karnataka, including SAILAND PARK and S F TOWERS. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Dharwad district page.

Frequently asked questions

What are my rights if SAILAND PARK is delayed beyond 31 Dec 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SAILAND PARK?

The registered promoter entity is NEW HOMES REALITY, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SAILAND PARK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SAILAND PARK?

The professionals named in the filing: Architect: KIRAN UPPAR; Engineer: D.L.KULKARNI & ASSOCIATES. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAILAND PARK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAILAND PARK. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAILAND PARK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.