Registration approved Residential/Group Housing project

SAI SUBHOD APARTMENT

By VANISHREE BUILDERS

RG-KA-93417 · RERA PRM/KA/RERA/1259/410/PR/180504/001578

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Jun 2020Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 40 documents Report an error

SAI SUBHOD APARTMENT is a Residential/Group Housing project by VANISHREE BUILDERS in Dharwad, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1259/410/PR/180504/001578 on 4 May 2018. Possession is promised by 30 Jun 2020.

At a glance

Project

  • NameSAI SUBHOD APARTMENT
  • TypeResidential/Group Housing
  • Location
    • Dharwad
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1259/410/PR/180504/001578
  • ReraGenie IDRG-KA-93417

Builder

  • NameVANISHREE BUILDERS
  • Entity typePartnership Firm
  • Authorized SignatoryCHANDRAKANT V MEGHARAJ
  • Other registrations18 more →
  • Declared earlier projects5 →

Key dates

this monthRegisteredMay 2018PromisedJun 2020

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on4 May 2018
  • Promised completion30 Jun 2020
  • Revised completionNone
  • Buildings1 building record
  • Documents filed40 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SAI SUBODH---16016

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)-
PaintingNot applicable
Elevation work-
Internal and External work including landscapes as per santioned drawingsNot applicable

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsYes-
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
GasNoNot applicable
Water and SanitationNoNot applicable
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementNoNot applicable
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area850 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 3.40 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSHRIEESH MADALAGI
EngineerVENKETESH M.MISKIN

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed40

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1259/410/PR/180504/001578 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: CERTIFICATE 001.jpg-
COMMENCEMENT CERTIFICATE-
CTS EXPLANATION LETTER -
Plan for Subbod-
SALE DEED FORMATE-
AGREEMENT FOR SALE (1)-
RIGHTS-
SECTION DRAWING-Model-
allotment letter-
BROUCHER SAI SUBHOD-
specification 001-
EC-
MOTATION ENTRY-
AGREEMENT-
SALE DEEDS-
CTS -
Unnamed document-
V M SAI SUBHOD 001-
LEGAL OPINION-
Balance Sheet 2016 - 2017File: BALANCE SHEET.jpg-
Balance Sheet 2015 - 2016File: BALANCE SHEET.JPG-
Balance Sheet 2014 - 2015File: BALANCE SHEET 2014 001.jpg-
Audited Profit and Loss Statement 2016 - 2017File: PROFIT AND LOSS 2015.pdf-
Audited Profit and Loss Statement 2015 - 2016File: PROFIT AND LOSS 2015.pdf-
Audited Profit and Loss Statement 2014 - 2015File: PROFIT AND LOSS.pdf-
Cash Flow Statement 2016 - 2017File: CASH FLOW 2016.pdf-
Cash Flow Statement 2015 - 2016File: CASH FLOW 2016.pdf-
Auditor's Report 2016 - 2017File: AUDITOR REPORT 2016.pdf-
Auditor's Report 2015 - 2016File: AUDITOR REPORT 2015.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: ITR 2016.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: ITR 2015 001.jpg-
Income Tax Return Acknowledgement 2014 - 2015File: ITR 2014 001.jpg-
DECLARATION-
Prospectus/BrochureFile: SAI SUBODH 002.jpg-
Advertisement Copy 1File: SAI SUBODH 001.jpg-
Tower Excel SheetFile: SAI SUBODH.xlsx-
Occupancy CertificateFile: Completion Certificate Applied Copy .jpg-
Completion certificateFile: Completion Certificate Applied Copy .jpg-
Registered Agreement of SaleFile: Sale agreement Prakesh Tadas Sai subodh.pdf-
Registered conveyance deed for an individual unitFile: the sale deed Prakesh Tadas Sai Subodh.pdf-

How this compares with Dharwad

29%of Dharwad projects moved their completion datethis one has not
0%of Dharwad registrations are shown as withdrawn or revokedthis one is not

Computed across the 250+ Dharwad projects on ReraGenie, from their own filings.

Keep SAI SUBHOD APARTMENT on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dharwad250+ in Dharwad

Builder: VANISHREE BUILDERS

VANISHREE BUILDERS has 19 registrations on RERA Karnataka, including SAI GOPAL APARTMENT and SAI NANDAN APARTMENT. Its filings declare 5 earlier projects, 2 of them declared completed. Read the full track record. See more projects on the Dharwad district page.

Frequently asked questions

What are my rights if SAI SUBHOD APARTMENT is delayed beyond 30 Jun 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SAI SUBHOD APARTMENT?

The registered promoter entity is VANISHREE BUILDERS, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SAI SUBHOD APARTMENT?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SAI SUBHOD APARTMENT?

The professionals named in the filing: Architect: SHRIEESH MADALAGI; Engineer: VENKETESH M.MISKIN. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAI SUBHOD APARTMENT?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAI SUBHOD APARTMENT. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAI SUBHOD APARTMENT to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.