Home / Browse projects / Surat, Gujarat / SAHJANAND HARMONY

Valid until 29 Jan 2026 Residential/Group Housing project

SAHJANAND HARMONY

By STARLINERS DEVELOPER

RG-GJ-32557 · RERA PR/GJ/SURAT/KAMREJ/SUDA/RAA01579/EX2/041221 · Last updated on GujRERA portal: 5 Sep 2022

Source: official GujRERA filing

Red flags

  • Completion date moved by 64 months
  • 3 extensions taken

Clear

  • Nothing verified clear yet
Jan 2026Possession promisedmoved 64 months from the original
12 of 27Construction stages doneacross 4 buildings; furthest along: External plumbing and external plaster, 95%
97 of 160Units unsoldnot recorded sold or booked
Jump to the 41 documents Report an error

SAHJANAND HARMONY is a Residential/Group Housing project by STARLINERS DEVELOPER in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/KAMREJ/SUDA/RAA01579/EX2/041221 on 9 Feb 2018. Possession is promised by 29 Jan 2026. The completion date has moved by 64 months from the original filing. 63 of the 160 units on this registration are recorded sold or booked, and 12 of 27 construction stages are filed complete.

At a glance

Project

  • NameSAHJANAND HARMONY
  • TypeResidential/Group Housing
  • Location
    • Block no.151New Block No 158
    • Sahajanand Harmony
    • Kosmada
    • Block no.151New Block No 158
    • Sahajanand Harmony
    • Kosmada
    • Kosmada
    • Kamrej
    • Surat
    • 394325
  • Pincode394325
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/SURAT/KAMREJ/SUDA/RAA01579/EX2/041221
  • ReraGenie IDRG-GJ-32557

Builder

  • NameSTARLINERS DEVELOPER
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredFeb 2018First promiseSep 2020Revised toJan 2026

Key facts

Registration and timeline

  • StatusValid until 29 Jan 2026
  • Registered on9 Feb 2018
  • Promised completion29 Jan 2026
  • Revised completionRevised to 29 Jan 2026 (originally 30 Sep 2020)
  • Buildings4 building records
  • Documents filed41 files

Current status

39%63 of 160 units booked
55.3%Of the estimated cost spent so far

Figures as on 5 Sep 2022, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---40040
B---40040
C---40040
D---40040

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building4

As on 5 Sep 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

12 of 27 construction stages are filed complete across 4 buildings. The stage furthest along is External plumbing and external plaster, at 95%.

A94%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing95%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing60%
B94%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing60%
C56%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure90%
Internal walls, internal plaster, floorings, doors and windows within flats65%
Sanitary fittings within the flats5%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks55%
External plumbing and external plaster, elevation, completion of terraces with waterproofing20%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
D20%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure25%
Internal walls, internal plaster, floorings, doors and windows within flats5%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks9%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities19

As on 5 Sep 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes5%
Sewerage (chamber, lines, septic tank, STP)Yes5%
Storm water drainsYes5%
Landscaping and tree plantingYes0%
Street lightingYes10%
Community buildingsYes0%
Treatment and disposal of sewage and sullage waterYes0%
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes5%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingNoNot applicable
Drinking water facilitiesYes5%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area10,346 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 43.06 cr
Cost incurredRs 23.80 cr
Spent of the estimate55.27%
BuildingWingEstimatedIncurred
ANARs 10.77 crRs 5.95 cr
BNARs 10.77 crRs 5.95 cr
CNARs 10.77 crRs 5.95 cr
DNARs 10.77 crRs 5.95 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKCL ARCHITECTS & ENGINEERS
EngineerB'N'K Asssociates

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/SURAT/KAMREJ/SUDA/RAA01579/EX1/261120Applied Sep 2020; approved Nov 2020
PR/GJ/SURAT/KAMREJ/SUDA/RAA01579/EX2/041221Applied Sep 2021; approved Dec 2021
ExtensionApplied Nov 2024; no approval date filed

Documents filed41

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/KAMREJ/SUDA/RAA01579/EX2/041221 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)5 Sep 2022
Engineer's certificate (Form 2)5 Sep 2022
Engineer's certificate annexure5 Sep 2022
Accountant's certificate (Form 3)5 Sep 2022
Site photograph, A5 Sep 2022
Site photograph, B5 Sep 2022
Site photograph, C5 Sep 2022
Site photograph, D5 Sep 2022
RERA registration certificate9 Feb 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Surat

39%of this project is bookeddistrict median 39%
15%of Surat projects moved their completion datethis one moved by 64 months

Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.

Keep SAHJANAND HARMONY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Kosmada2,600+ in Surat

2 kmSAHJANAND HARMONYOther 11Dot size: filed unitsN

Filed coordinates, straight-line distance. 11 registered projects within 2 km.

Builder: STARLINERS DEVELOPER

STARLINERS DEVELOPER has 1 registration on GujRERA, including SAHJANAND HARMONY. Read the full track record. See more projects on the Surat district page.

Frequently asked questions

What are my rights if SAHJANAND HARMONY is delayed beyond 29 Jan 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SAHJANAND HARMONY?

The registered promoter entity is STARLINERS DEVELOPER, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SAHJANAND HARMONY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SAHJANAND HARMONY?

The professionals named in the filing: Architect: KCL ARCHITECTS & ENGINEERS; Engineer: B'N'K Asssociates. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAHJANAND HARMONY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAHJANAND HARMONY. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAHJANAND HARMONY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.