MAHATMA GANDHI FRUIT MARKET

By SAKSHI ENTERPRISE

RG-GJ-79954 · RERA PR/GJ/SURAT/SURAT CITY/Surat Urban Development Authority/CN22AA09922/EX1/090925/300326 · Last updated on GujRERA portal: 3 Sep 2025

Source: official GujRERA filing

Red flags

  • Completion date moved by 28 months
  • 2 extensions taken

Clear

  • Nothing verified clear yet
Jul 2027Possession promisedmoved 28 months from the original
36 of 72Construction stages doneacross 8 buildings; furthest along: Sanitary fittings within the flats, 95%
245 of 375Units unsoldnot recorded sold or booked
Jump to the 44 documents Report an error

MAHATMA GANDHI FRUIT MARKET is a Commercial project by SAKSHI ENTERPRISE in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/SURAT CITY/Surat Urban Development Authority/CN22AA09922/EX1/090925/300326 on 7 May 2022. Possession is promised by 30 Jul 2027. The completion date has moved by 28 months from the original filing. 130 of the 375 units on this registration are recorded sold or booked, and 36 of 72 construction stages are filed complete.

At a glance

Project

  • NameMAHATMA GANDHI FRUIT MARKET
  • TypeCommercial
  • Location
    • BLOCK NO-43
    • 44
    • 45
    • 47 & 48/B
    • SUB PLOT NO-1
    • 2 MOJE- ANTROLI TAL-PALSANA
    • ANTROLI
    • Palsana
    • Surat
    • 394325
  • Pincode394325
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/SURAT/SURAT CITY/Surat Urban Development Authority/CN22AA09922/EX1/090925/300326
  • ReraGenie IDRG-GJ-79954

Builder

  • NameSAKSHI ENTERPRISE
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredMay 2022First promiseMar 2025Revised toJul 2027

Key facts

Registration and timeline

  • StatusValid until 30 Jul 2027
  • Registered on7 May 2022
  • Promised completion30 Jul 2027
  • Revised completionRevised to 30 Jul 2027 (originally 31 Mar 2025)
  • Buildings8 building records
  • Documents filed44 files

Current status

35%130 of 375 units booked
83.8%Of the estimated cost spent so far

Figures as on 3 Sep 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
B2---02424
B3---02626
B4---01313
A1---0110110
A2---02828
A3---03232
A4---01616
B1---0126126

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building8

As on 3 Sep 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

36 of 72 construction stages are filed complete across 8 buildings. The stage furthest along is Sanitary fittings within the flats, at 95%.

B284%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats90%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing80%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing90%
B387%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats95%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing95%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%
B487%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats95%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing95%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%
A160%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats50%
Sanitary fittings within the flats40%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing40%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing40%
A286%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats90%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing90%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%
A386%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats90%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing90%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%
A487%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats95%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing95%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%
B160%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats50%
Sanitary fittings within the flats40%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing40%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing40%

Progress on shared amenities19

As on 3 Sep 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes70%
Water supplyYes75%
Sewerage (chamber, lines, septic tank, STP)Yes70%
Storm water drainsYes70%
Landscaping and tree plantingYes50%
Street lightingYes60%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes50%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesYes30%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes30%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area25,503 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 39.25 cr
Cost incurredRs 32.90 cr
Spent of the estimate83.82%
BuildingWingEstimatedIncurred
A1NARs 12.50 crRs 9.00 cr
B1NARs 12.50 crRs 10.50 cr
A3NARs 3.25 crRs 3.10 cr
A2NARs 2.75 crRs 2.60 cr
B3NARs 2.50 crRs 2.30 cr
B2NARs 2.25 crRs 2.10 cr
B4NARs 2.00 crRs 1.90 cr
A4NARs 1.50 crRs 1.40 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNirav Asit Khandwala
EngineerSMIT JAWAHARBHAI THAKKAR

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/SURAT/SURAT CITY/Surat Urban Development Authority/CN22AA09922/EX1/090925/300326Applied Mar 2025; approved Sep 2025
ExtensionApplied Apr 2026; no approval date filed

Documents filed44

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/SURAT CITY/Surat Urban Development Authority/CN22AA09922/EX1/090925/300326 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)3 Sep 2025
Engineer's certificate (Form 2)3 Sep 2025
Engineer's certificate annexure3 Sep 2025
Accountant's certificate (Form 3)3 Sep 2025
Site photograph, B23 Sep 2025
Site photograph, B33 Sep 2025
Site photograph, B43 Sep 2025
Site photograph, A13 Sep 2025
Site photograph, A23 Sep 2025
Site photograph, A33 Sep 2025
Site photograph, A43 Sep 2025
Site photograph, B13 Sep 2025
RERA registration certificate7 May 2022
Proforma agreement for sale-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Drainage affidavit-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Proforma sale deed-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Surat

35%of this project is bookeddistrict median 39%
15%of Surat projects moved their completion datethis one moved by 28 months

Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.

Keep MAHATMA GANDHI FRUIT MARKET on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near ANTROLI2,600+ in Surat

2 kmMAHATMA GANDHI FRUIT MAROther 3Dot size: filed unitsN

Filed coordinates, straight-line distance. 3 registered projects within 2 km.

Builder: SAKSHI ENTERPRISE

SAKSHI ENTERPRISE has 1 registration on GujRERA, including MAHATMA GANDHI FRUIT MARKET. Read the full track record. See more projects on the Surat district page.

Frequently asked questions

What are my rights if MAHATMA GANDHI FRUIT MARKET is delayed beyond 30 Jul 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of MAHATMA GANDHI FRUIT MARKET?

The registered promoter entity is SAKSHI ENTERPRISE, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in MAHATMA GANDHI FRUIT MARKET?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at MAHATMA GANDHI FRUIT MARKET?

The professionals named in the filing: Architect: Nirav Asit Khandwala; Engineer: SMIT JAWAHARBHAI THAKKAR. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MAHATMA GANDHI FRUIT MARKET?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MAHATMA GANDHI FRUIT MARKET. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MAHATMA GANDHI FRUIT MARKET to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.