ReraGenieLog inGet a buyer report

Home / Browse projects / Surat, Gujarat / SAHJANAND GREEN CITY

Valid until 30 Sep 2023 Mixed Development project

SAHJANAND GREEN CITY

By BHUMINBHAI RAMESHBHAI BUTANI

RG-GJ-43802 · RERA PR/GJ/SURAT/KAMREJ/Others/MAA02121/220318 · Last updated on GujRERA portal: 27 Sep 2023

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
  • Separate project account declared
Sep 2023Possession promisedno revision filed
50 of 54Construction stages doneacross 6 buildings; furthest along: Sanitary fittings within the flats, 75%
407 of 571Units unsoldnot recorded sold or booked
Jump to the 43 documents Report an error

SAHJANAND GREEN CITY is a Mixed Development project by BHUMINBHAI RAMESHBHAI BUTANI in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/KAMREJ/Others/MAA02121/220318 on 22 Mar 2018. Possession is promised by 30 Sep 2023. 164 of the 571 units on this registration are recorded sold or booked, and 50 of 54 construction stages are filed complete.

At a glance

Project

  • NameSAHJANAND GREEN CITY
  • TypeMixed Development
  • Location
    • BLOCK NO-166
    • R.S. NO-171/1 Village: KAMREJ
    • Tehsil : KAMREJ District : Surat
    • State : Gujarat
    • BLOCK NO-166
    • R.S. NO-171/1 Village: KAMREJ
    • Tehsil : KAMREJ...
  • Pincode394180
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/SURAT/KAMREJ/Others/MAA02121/220318
  • ReraGenie IDRG-GJ-43802

Builder

  • NameBHUMINBHAI RAMESHBHAI BUTANI
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredMar 2018PromisedSep 2023

Key facts

Registration and timeline

  • StatusValid until 30 Sep 2023
  • Registered on22 Mar 2018
  • Promised completion30 Sep 2023
  • Revised completionNone
  • Buildings6 building records
  • Documents filed43 files

Current status

29%164 of 571 units booked
38.1%Of the estimated cost spent so far

Figures as on 27 Sep 2023, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A1A2---401252
A3A4---401353
B1B2---40040
B3---20020
D1D2---401252
D3D4---401454

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building6

As on 27 Sep 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

50 of 54 construction stages are filed complete across 6 buildings. The stage furthest along is Sanitary fittings within the flats, at 75%.

A1A2100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
A3A4100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B1B268%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats75%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
B3100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
D1D2100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
D3D4100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 27 Sep 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes5%
Water supplyYes5%
Sewerage (chamber, lines, septic tank, STP)Yes10%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes7%
Street lightingYes7%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes3%
Fire fightingYes0%
Drinking water facilitiesYes0%
Emergency evacuationYes0%
Use of renewable energyYes0%
SecurityYes0%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area21,643 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 45.13 cr
Cost incurredRs 17.19 cr
Spent of the estimate38.08%
BuildingWingEstimatedIncurred
A1A2NARs 3.22 crRs 1.23 cr
A3A4NARs 3.22 crRs 1.23 cr
B1B2NARs 3.22 crRs 1.23 cr
B3NARs 3.22 crRs 1.23 cr
C1C2NARs 3.22 crRs 1.23 cr
C3C4NARs 3.22 crRs 1.23 cr
D1D2NARs 3.22 crRs 1.23 cr
D3D4NARs 3.22 crRs 1.23 cr
E1E2NARs 3.22 crRs 1.23 cr
E3E4NARs 3.22 crRs 1.23 cr
F1F2NARs 3.22 crRs 1.23 cr
F3F4NARs 3.22 crRs 1.23 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectABHIJIT MADBHAVI (PYGMALION DESIGN STUDIO)
EngineerARPITKUMAR N DUDHAT
EngineerSURESH V BARVALIYA

Documents filed43

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/KAMREJ/Others/MAA02121/220318 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Site photograph, A1A227 Sep 2023
Site photograph, A3A427 Sep 2023
Site photograph, B1B227 Sep 2023
Site photograph, B327 Sep 2023
Site photograph, D1D227 Sep 2023
Site photograph, D3D427 Sep 2023
Engineer's certificate (Form 2)1 Jul 2023
Engineer's certificate annexure1 Jul 2023
Accountant's certificate (Form 3)1 Jul 2023
RERA registration certificate22 Mar 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-
Architect's certificate (Form 1)-

How this compares with Surat

29%of this project is bookeddistrict median 39%
15%of Surat projects moved their completion datethis one has not

Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.

Keep SAHJANAND GREEN CITY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Kamrej2,600+ in Surat

2 kmSAHJANAND GREEN CITYOther 6Dot size: filed unitsN

Filed coordinates, straight-line distance. 6 registered projects within 2 km.

Builder: BHUMINBHAI RAMESHBHAI BUTANI

BHUMINBHAI RAMESHBHAI BUTANI has 1 registration on GujRERA, including SAHJANAND GREEN CITY. Read the full track record. See more projects on the Surat district page.

Frequently asked questions

What are my rights if SAHJANAND GREEN CITY is delayed beyond 30 Sep 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SAHJANAND GREEN CITY?

The registered promoter entity is BHUMINBHAI RAMESHBHAI BUTANI, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SAHJANAND GREEN CITY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SAHJANAND GREEN CITY?

The professionals named in the filing: Architect: ABHIJIT MADBHAVI (PYGMALION DESIGN STUDIO); Engineer: ARPITKUMAR N DUDHAT; Engineer: SURESH V BARVALIYA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAHJANAND GREEN CITY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAHJANAND GREEN CITY. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAHJANAND GREEN CITY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.