Home / Browse projects / Ahmedabad, Gujarat / SAHDEV CAPITOL

Valid until 31 Jul 2027 Commercial project

SAHDEV CAPITOL

By SAHDEV DEVELOPERS

RG-GJ-73073 · RERA PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/CAA11769/160523 · Last updated on GujRERA portal: 2 Oct 2024

Source: official GujRERA filing

Red flags

  • Completion date moved by 16 months
  • 1 extension taken

Clear

  • Nothing verified clear yet
Jul 2027Possession promisedmoved 16 months from the original
3 of 9Construction stages donefurthest along: Staircases, 77%
62 of 145Units unsoldnot recorded sold or booked
Jump to the 38 documents Report an error

SAHDEV CAPITOL is a Commercial project by SAHDEV DEVELOPERS in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/CAA11769/160523 on 16 May 2023. Possession is promised by 31 Jul 2027. The completion date has moved by 16 months from the original filing. 83 of the 145 units on this registration are recorded sold or booked, and 3 of 9 construction stages are filed complete.

At a glance

Project

  • NameSAHDEV CAPITOL
  • TypeCommercial
  • Location
    • SURVER NO. 203(1+2+4)
    • FP NO
    • 106/1
    • DRAFT TPS 31
    • OPP. MANAV MANDIR
    • MEMNAGAR
    • AHEMDABAD
    • Ahmedabad City
    • Ahmedabad
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/CAA11769/160523
  • ReraGenie IDRG-GJ-73073

Builder

  • NameSAHDEV DEVELOPERS
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredMay 2023First promiseMar 2026Revised toJul 2027

Key facts

Registration and timeline

  • StatusValid until 31 Jul 2027
  • Registered on16 May 2023
  • Promised completion31 Jul 2027
  • Revised completionRevised to 31 Jul 2027 (originally 31 Mar 2026)
  • Buildings1 building record
  • Documents filed38 files

Current status

57%83 of 145 units booked
65.0%Of the estimated cost spent so far

Figures as on 2 Oct 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BULIDING 1---0145145

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 2 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 9 construction stages are filed complete. The stage furthest along is Staircases, at 77%.

BULIDING 1: 54% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor21%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats46%
Sanitary fittings within the flats15%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks77%
External plumbing and external plaster, elevation, completion of terraces with waterproofing15%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing15%

Progress on shared amenities23

As on 2 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes20%
Water supplyYes15%
Sewerage (chamber, lines, septic tank, STP)Yes22%
Storm water drainsYes25%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes0%
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes0%
Letter boxYes0%
Compound wallYes70%
Plinth protectionYes25%
Water tankYes80%
Other requirementsYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,540 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 32.00 cr
Cost incurredRs 20.80 cr
Spent of the estimate65.0%
BuildingWingEstimatedIncurred
BULIDING 1NARs 32.00 crRs 20.80 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRUDRA ARCHITECTS
EngineerUmang J Patel

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionApplied Mar 2026; no approval date filed

Documents filed38

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/CAA11769/160523 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)2 Oct 2024
Engineer's certificate annexure2 Oct 2024
RERA registration certificate16 May 2023
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

57%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one moved by 16 months

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep SAHDEV CAPITOL on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Ahmedabad5,400+ in Ahmedabad

2 kmSAHDEV CAPITOLOther 171Dot size: filed unitsN

Filed coordinates, straight-line distance. 171 registered projects within 2 km.

Builder: SAHDEV DEVELOPERS

SAHDEV DEVELOPERS has 1 registration on GujRERA, including SAHDEV CAPITOL. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if SAHDEV CAPITOL is delayed beyond 31 Jul 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SAHDEV CAPITOL?

The registered promoter entity is SAHDEV DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SAHDEV CAPITOL?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SAHDEV CAPITOL?

The professionals named in the filing: Architect: RUDRA ARCHITECTS; Engineer: Umang J Patel. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAHDEV CAPITOL?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAHDEV CAPITOL. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAHDEV CAPITOL to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.