Home / Browse projects / Anand, Gujarat / SAHAJANAND SWAROOP
SAHAJANAND SWAROOP
By SAHAJANAND SARJAN DEVELOPERS
RG-GJ-38119 · RERA PR/GJ/ANAND/ANAND/Anand VallabhVidhyanagar Karmsad Urban Development Authority/RAA13889/290724/300926 · Last updated on GujRERA portal: 5 Jun 2026
Source: official GujRERA filing
Red flags
- Completion date moved by 12 months
- 1 extension taken
Clear
- Nothing verified clear yet
Saved.
SAHAJANAND SWAROOP is a Residential/Group Housing project by SAHAJANAND SARJAN DEVELOPERS in Anand, Gujarat, registered with GujRERA as PR/GJ/ANAND/ANAND/Anand VallabhVidhyanagar Karmsad Urban Development Authority/RAA13889/290724/300926 on 29 Jul 2024. Possession is promised by 30 Sep 2027. The completion date has moved by 12 months from the original filing. 42 of the 59 units on this registration are recorded sold or booked, and 49 of 144 construction stages are filed complete.
At a glance
Project
- NameSAHAJANAND SWAROOP
- TypeResidential/Group Housing
- Location
- C.T.S.NO: NA625/1+626/1+626/3
- NEAR SHYAM RESIDENCY
- OPP. MARUTI SANKALP SOCIETY
- KARAMSAD-GANA ROAD
- KARAMSAD
- Anand
- 388325
- Pincode388325
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR/GJ/ANAND/ANAND/Anand VallabhVidhyanagar Karmsad Urban Development Authority/RAA13889/290724/300926
- ReraGenie IDRG-GJ-38119
Builder
- NameSAHAJANAND SARJAN DEVELOPERS
- Entity typePARTNERSHIP FIRM
- Other registrations1 more →
Key dates
Key facts
Registration and timeline
- StatusValid until 30 Sep 2027
- Registered on29 Jul 2024
- Promised completion30 Sep 2027
- Revised completionRevised to 30 Sep 2027 (originally 30 Sep 2026)
- Buildings16 building records
- Documents filed102 files
Current status
Figures as on 5 Jun 2026, this project's latest GujRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| N | - | - | - | 2 | 0 | 2 |
| M | - | - | - | 6 | 0 | 6 |
| P | - | - | - | 1 | 0 | 1 |
| O | - | - | - | 2 | 0 | 2 |
| B | - | - | - | 5 | 0 | 5 |
| A | - | - | - | 3 | 0 | 3 |
| D | - | - | - | 1 | 0 | 1 |
| C | - | - | - | 2 | 0 | 2 |
| F | - | - | - | 10 | 0 | 10 |
| E | - | - | - | 1 | 0 | 1 |
| H | - | - | - | 1 | 0 | 1 |
| G | - | - | - | 3 | 0 | 3 |
| J | - | - | - | 3 | 0 | 3 |
| I | - | - | - | 2 | 0 | 2 |
| L | - | - | - | 12 | 0 | 12 |
| K | - | - | - | 5 | 0 | 5 |
The full filing
Everything below is from the project's own GujRERA filing, free to read.
Construction progress by building16
As on 5 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
49 of 144 construction stages are filed complete across 16 buildings. The stage furthest along is Sanitary fittings within the flats, at 90%.
N39%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 75% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 25% |
| Sanitary fittings within the flats | 25% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 25% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
M55%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 75% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 75% |
| Sanitary fittings within the flats | 50% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 35% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 10% |
P22%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 0% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
O34%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 60% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 25% |
| Sanitary fittings within the flats | 25% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
B57%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 75% |
| Sanitary fittings within the flats | 50% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 35% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 35% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 20% |
A36%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 75% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 50% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
D44%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
C33%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 50% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 50% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
F83%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 90% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 85% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 85% |
E44%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
H22%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 0% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
G56%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 75% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 25% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
J82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 90% |
| Sanitary fittings within the flats | 90% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 90% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 75% |
I86%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 75% |
L81%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 90% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 85% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 75% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 75% |
K45%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 50% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 50% |
| Sanitary fittings within the flats | 35% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 35% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 35% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
Progress on shared amenities19
As on 5 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal roads and footpaths | Yes | 85% |
| Water supply | Yes | 50% |
| Sewerage (chamber, lines, septic tank, STP) | Yes | 50% |
| Storm water drains | No | Not applicable |
| Landscaping and tree planting | Yes | 75% |
| Street lighting | Yes | 0% |
| Community buildings | No | Not applicable |
| Treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | Yes | 0% |
| Water conservation, rain water harvesting | No | Not applicable |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Fire fighting | No | Not applicable |
| Drinking water facilities | Yes | 0% |
| Emergency evacuation | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Security | Yes | 0% |
| Letter box | No | Not applicable |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| L | NA | Rs 1.11 cr | Rs 1.07 cr |
| F | NA | Rs 92.76 lakh | Rs 90.00 lakh |
| K | NA | Rs 52.15 lakh | Rs 36.50 lakh |
| M | NA | Rs 51.54 lakh | Rs 37.00 lakh |
| B | NA | Rs 42.95 lakh | Rs 33.38 lakh |
| A | NA | Rs 31.29 lakh | Rs 25.50 lakh |
| G | NA | Rs 25.02 lakh | Rs 21.25 lakh |
| J | NA | Rs 23.25 lakh | Rs 21.50 lakh |
| C | NA | Rs 18.04 lakh | Rs 10.15 lakh |
| I | NA | Rs 15.50 lakh | Rs 15.25 lakh |
| N | NA | Rs 14.38 lakh | Rs 8.98 lakh |
| O | NA | Rs 14.37 lakh | Rs 7.32 lakh |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | NAYANKUMAR JAGDISHBHAI PANCHAL |
| Engineer | INDRAJIT PATEL |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Documents filed102
As listed on the registration, under the names the promoter filed them with; the newest 80 of 102 are shown. The files themselves are available at source: search the registration number PR/GJ/ANAND/ANAND/Anand VallabhVidhyanagar Karmsad Urban Development Authority/RAA13889/290724/300926 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect's certificate (Form 1) | 5 Jun 2026 |
| Engineer's certificate (Form 2) | 5 Jun 2026 |
| Engineer's certificate annexure | 5 Jun 2026 |
| Accountant's certificate (Form 3) | 5 Jun 2026 |
| Site photograph, N | 3 Jun 2026 |
| Site photograph, M | 3 Jun 2026 |
| Site photograph, M | 3 Jun 2026 |
| Site photograph, M | 3 Jun 2026 |
| Site photograph, M | 3 Jun 2026 |
| Site photograph, M | 3 Jun 2026 |
| Site photograph, M | 3 Jun 2026 |
| Site photograph, P | 3 Jun 2026 |
| Site photograph, O | 3 Jun 2026 |
| Site photograph, O | 3 Jun 2026 |
| Site photograph, B | 3 Jun 2026 |
| Site photograph, B | 3 Jun 2026 |
| Site photograph, B | 3 Jun 2026 |
| Site photograph, B | 3 Jun 2026 |
| Site photograph, B | 3 Jun 2026 |
| Site photograph, A | 3 Jun 2026 |
| Site photograph, A | 3 Jun 2026 |
| Site photograph, A | 3 Jun 2026 |
| Site photograph, D | 3 Jun 2026 |
| Site photograph, C | 3 Jun 2026 |
| Site photograph, C | 3 Jun 2026 |
| Site photograph, F | 3 Jun 2026 |
| Site photograph, F | 3 Jun 2026 |
| Site photograph, F | 3 Jun 2026 |
| Site photograph, F | 3 Jun 2026 |
| Site photograph, F | 3 Jun 2026 |
| Site photograph, F | 3 Jun 2026 |
| Site photograph, F | 3 Jun 2026 |
| Site photograph, F | 3 Jun 2026 |
| Site photograph, F | 3 Jun 2026 |
| Site photograph, F | 3 Jun 2026 |
| Site photograph, E | 3 Jun 2026 |
| Site photograph, H | 3 Jun 2026 |
| Site photograph, G | 3 Jun 2026 |
| Site photograph, G | 3 Jun 2026 |
| Site photograph, G | 3 Jun 2026 |
| Site photograph, J | 3 Jun 2026 |
| Site photograph, J | 3 Jun 2026 |
| Site photograph, J | 3 Jun 2026 |
| Site photograph, I | 3 Jun 2026 |
| Site photograph, I | 3 Jun 2026 |
| Site photograph, L | 3 Jun 2026 |
| Site photograph, L | 3 Jun 2026 |
| Site photograph, L | 3 Jun 2026 |
| Site photograph, L | 3 Jun 2026 |
| Site photograph, L | 3 Jun 2026 |
| Site photograph, L | 3 Jun 2026 |
| Site photograph, L | 3 Jun 2026 |
| Site photograph, L | 3 Jun 2026 |
| Site photograph, L | 3 Jun 2026 |
| Site photograph, L | 3 Jun 2026 |
| Site photograph, L | 3 Jun 2026 |
| Site photograph, L | 3 Jun 2026 |
| Site photograph, K | 3 Jun 2026 |
| Site photograph, K | 3 Jun 2026 |
| Site photograph, K | 3 Jun 2026 |
| Site photograph, K | 3 Jun 2026 |
| Site photograph, K | 3 Jun 2026 |
| RERA registration certificate | 29 Jul 2024 |
| Proforma agreement for sale | - |
| Auditor's report (1 of 3) | - |
| Auditor's report (2 of 3) | - |
| Auditor's report (3 of 3) | - |
| Income tax return (1 of 3) | - |
| Income tax return (2 of 3) | - |
| Income tax return (3 of 3) | - |
| Project specific document | - |
| Drainage affidavit | - |
| Directors' report (1 of 3) | - |
| Directors' report (2 of 3) | - |
| Directors' report (3 of 3) | - |
| Approved sanctioned plan | - |
| Approved layout plan | - |
| Land location | - |
| Encumbrance certificate | - |
| Area development document | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Anand
Computed across the 310+ Anand projects on ReraGenie, from their own filings.
Keep SAHAJANAND SWAROOP on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near KARAMSAD310+ in Anand
Filed coordinates, straight-line distance. 72 registered projects within 2 km.
SUKIRTAN REGALIA
SHAKTI BUILDERS
RAGHUKUL PARISAR - 3
PURANSINGH RAMSINGH RATHORE (PROP. OF RAGH
Veer Elegance
KUSHAL VINODKUMAR BHATT AND OTHERS
ATMIYA SKY
ATMIYA FIELDCON PRIVATE LIMITED
Sahajanad Elegance-3
Sahajanand Developers
SHASHWAT BLISS
SHAKTI ASSOCIATES
See every Anand project, with the district possession charts
Builder: SAHAJANAND SARJAN DEVELOPERS
SAHAJANAND SARJAN DEVELOPERS has 2 registrations on GujRERA, including SAHAJANAND-21 and SAHAJANAND SWAROOP. Read the full track record. See more projects on the Anand district page.
Frequently asked questions
What are my rights if SAHAJANAND SWAROOP is delayed beyond 30 Sep 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.
How do I verify and contact the developer of SAHAJANAND SWAROOP?
The registered promoter entity is SAHAJANAND SARJAN DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.
Is my payment protected in SAHAJANAND SWAROOP?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at SAHAJANAND SWAROOP?
The professionals named in the filing: Architect: NAYANKUMAR JAGDISHBHAI PANCHAL; Engineer: INDRAJIT PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SAHAJANAND SWAROOP?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.