SAANVI HEIGHTS

By JYOT CORPORATION

RG-GJ-48749 · RERA PR/GJ/SURAT/SURAT CITY/SUDA/RAA01970/A1R/EX1/140322 · Last updated on GujRERA portal: 26 May 2023

Source: official GujRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Separate project account declared
Feb 2023Possession promisedmoved 12 months from the original
33 of 35Construction stages doneacross 4 buildings; furthest along: Stilt Floor, 50%
118 of 200Units unsoldnot recorded sold or booked
Jump to the 45 documents Report an error

SAANVI HEIGHTS is a Residential/Group Housing project by JYOT CORPORATION in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/SURAT CITY/SUDA/RAA01970/A1R/EX1/140322 on 12 Mar 2018. Possession is promised by 28 Feb 2023. The completion date has moved by 12 months from the original filing. 82 of the 200 units on this registration are recorded sold or booked, and 33 of 35 construction stages are filed complete.

At a glance

Project

  • NameSAANVI HEIGHTS
  • TypeResidential/Group Housing
  • Location
    • RS NO.23/1 BLOCK NO.52
    • TP 21
    • FP 29
    • MOJE SIMADA
    • Simada
    • Surat City
    • Surat
    • 395006
  • Pincode395006
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/SURAT/SURAT CITY/SUDA/RAA01970/A1R/EX1/140322
  • ReraGenie IDRG-GJ-48749

Builder

  • NameJYOT CORPORATION
  • Entity typePARTNERSHIP FIRM
  • Other registrations1 more →

Key dates

this monthRegisteredMar 2018First promiseFeb 2022Revised toFeb 2023

Key facts

Registration and timeline

  • StatusValid until 28 Feb 2023
  • Registered on12 Mar 2018
  • Promised completion28 Feb 2023
  • Revised completionRevised to 28 Feb 2023 (originally 28 Feb 2022)
  • Buildings4 building records
  • Documents filed45 files

Current status

41%82 of 200 units booked
99.5%Of the estimated cost spent so far

Figures as on 26 May 2023, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---52052
B---52052
C---48048
D---48048

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building4

As on 26 May 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

33 of 35 construction stages are filed complete across 4 buildings. The stage furthest along is Stilt Floor, at 50%.

A94%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor50%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B94%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor50%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flatsNot applicable
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
C100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
D100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 26 May 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes90%
Water supplyYes90%
Sewerage (chamber, lines, septic tank, STP)NoNot applicable
Storm water drainsYes0%
Landscaping and tree plantingYes90%
Street lightingYes90%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes90%
Water conservation, rain water harvestingYes90%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes90%
Fire fightingYes90%
Drinking water facilitiesYes90%
Emergency evacuationYes90%
Use of renewable energyNoNot applicable
SecurityYes90%
Letter boxYes90%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,892 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 33.00 cr
Cost incurredRs 32.85 cr
Spent of the estimate99.55%
BuildingWingEstimatedIncurred
ANARs 8.25 crRs 8.21 cr
BNARs 8.25 crRs 8.21 cr
CNARs 8.25 crRs 8.21 cr
DNARs 8.25 crRs 8.21 cr

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/SURAT/SURAT CITY/SUDA/RAA01970/A1R/EX1/140322Applied Jan 2022; approved Mar 2022

Documents filed45

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/SURAT CITY/SUDA/RAA01970/A1R/EX1/140322 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)26 May 2023
Engineer's certificate (Form 2)26 May 2023
Engineer's certificate annexure26 May 2023
Accountant's certificate (Form 3)26 May 2023
Site photograph, A26 May 2023
Site photograph, A26 May 2023
Site photograph, A26 May 2023
Site photograph, B26 May 2023
Site photograph, B26 May 2023
Site photograph, C26 May 2023
Site photograph, C26 May 2023
Site photograph, D26 May 2023
RERA registration certificate12 Mar 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Surat

41%of this project is bookeddistrict median 39%
15%of Surat projects moved their completion datethis one moved by 12 months

Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.

Keep SAANVI HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Simada2,600+ in Surat

2 kmSAANVI HEIGHTSOther 145Dot size: filed unitsN

Filed coordinates, straight-line distance. 145 registered projects within 2 km.

Builder: JYOT CORPORATION

JYOT CORPORATION has 2 registrations on GujRERA, including SAANVI HEIGHTS and SANCTUM HOMES. Read the full track record. See more projects on the Surat district page.

Frequently asked questions

What are my rights if SAANVI HEIGHTS is delayed beyond 28 Feb 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SAANVI HEIGHTS?

The registered promoter entity is JYOT CORPORATION, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SAANVI HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in SAANVI HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAANVI HEIGHTS. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAANVI HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.