Home / Browse projects / Dharwad, Karnataka / RUBY TOWERS

Registration approved No litigation declared Mixed Development project

RUBY TOWERS

By M/S MWS TOWERS

RG-KA-22741 · RERA PRM/KA/RERA/1259/479/PR/210725/007938 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Sep 2028Possession promisedno revision filed
6 of 18Construction stages donefurthest along: Masonry Construction, 20%
71 of 94Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 187 documents Report an error

RUBY TOWERS is a Mixed Development project by M/S MWS TOWERS in Dharwad, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1259/479/PR/210725/007938 on 21 Jul 2025. Possession is promised by 30 Sep 2028. 23 of the 94 units on this registration are recorded sold or booked, and 6 of 18 construction stages are filed complete.

At a glance

Project

  • NameRUBY TOWERS
  • TypeMixed Development
  • Location
    • Hubballi
    • Dharwad
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1259/479/PR/210725/007938
  • ReraGenie IDRG-KA-22741

Builder

  • NameM/S MWS TOWERS
  • Entity typePartnership Firm
  • GSTIN29ABKFM2789DIZU
  • Authorized SignatoryYogesh A Habib
  • Other registrations1 more →

Key dates

this monthRegisteredJul 2025PromisedSep 2028

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on21 Jul 2025
  • Promised completion30 Sep 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed187 files

Current status

24%23 of 94 units booked
21.2%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
rubi tower---94094

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 18 construction stages are filed complete. The stage furthest along is Masonry Construction, at 20%.

Building: 41% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure100%
Masonry Construction20%
Plastering inside , outside & Ceiling20%
Joinery: Doors, Windows, Ventilators etc10%
Basic work of Water supply, Sanitary and Electrification10%
Dadoing, Skirting, Flooring, Tiles work (All types)10%
Railing and Grill fixing10%
Electrification, Water supply and Sanitary Finishing20%
Painting10%
Fire prevention and fire fighting fitting and fixture with network10%
Weather Proof work(tile,concrete)10%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes50%
Sewage and Drainage SystemYes100%
Water conservation/rain water harvesting/recharge of ground waterYes20%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes20%
Solid waste management and disposalYes10%
Emergency Evacuation servicesYes20%
Internal Roads & FootpathsYes50%
Electricity supply transformer and substationYes10%
Storm water drainsYes10%
Use of renewable energyYes10%
Sewage Treatment Plant (STP)Yes10%
Parks & Tree plantingYes10%
Street LightingYes10%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes0%
Community HallYes0%
Outdoor Sports facilityYes0%
Indoor Sports facilityNoNot applicable
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes15%
LiftsYes15%
Corridor/LobbiesNoNot applicable
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementYes100%
TerraceNoNot applicable
Outer WallNoNot applicable
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership6

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners6
LandownerVillageDistrict
Yogesh A Habib--
Prakash P Habib--
Kiran P Habib--
Deepak M Sharma--
Divyank P Bhandari--
Chirag Bhandari--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 15.67 cr
Cost incurredRs 3.32 cr
Spent of the estimate21.21%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 15.67 crRs 3.32 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectShreekant N Kabadi
EngineerShreekant N Kabadi
Chartered AccountantHiteskumar Modi

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed187

As listed on the registration, under the names the promoter filed them with; the newest 80 of 187 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1259/479/PR/210725/007938 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Q2 2026-2027 Form 4 CA.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Q2 2026-2027 Form 5 ARCH.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Q2 2026-2027 Form 6 ENG.pdf15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Certificate.pdf4 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 Architect Certificate.pdf4 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate.pdf4 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: FORM 4 CA CERTIFICATE_compressed (7).pdf14 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect Certificate.pdf14 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate.pdf14 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Certificate.pdf10 Mar 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: form 5 Architect Certificate.pdf10 Mar 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: form 6 Engineer Certificate.pdf10 Mar 2026
MEMORANDUM OF JDAFile: Memorandum of JDA.pdf24 Apr 2025
JDA CLARIFICATIONFile: JD clarification affidavit.pdf19 Mar 2025
BALANCE SHEETFile: Balance sheet.pdf5 Mar 2025
CA CERTIFICATE FORM 1File: CA Certificate form 1.pdf5 Mar 2025
FINANCIAL STATEMENT 2024File: Financial statement 2024.pdf5 Mar 2025
PROFIT AND LOSS ACCOUNTFile: Profit and loss account.pdf5 Mar 2025
EC FROM 01/04/2008 TO TILL DATEFile: EC 2008 to till date.pdf5 Mar 2025
JD CUM DECLARATION AFFIDAVITFile: JD clarification affidavit.pdf5 Mar 2025
LATEST RTCFile: Latest RTC.pdf5 Mar 2025
BUILDING LICENSEFile: Building license.pdf5 Mar 2025
KSPCB NOCFile: KSPCB NOC.pdf5 Mar 2025
SINGLE LAYOUT APPROVALFile: Single layout approval.pdf5 Mar 2025
ADLR SURVEY SKETCHFile: ADLR Survey sketch.pdf5 Mar 2025
BASEMENT FLOOR PLANFile: Basement floor plan.pdf5 Mar 2025
BRIEF ESTIMATED PROJECT COSTFile: Brief estiamted project cost.pdf5 Mar 2025
DECLARATION OF LAND VALUE CALCULATIONFile: Declaration of land value calculations.pdf5 Mar 2025
DECLARATION OF WATER SOURCESFile: Declaration of water source.pdf5 Mar 2025
ENGINEER LICENSEFile: Engineer license.pdf5 Mar 2025
FORM 6 ENGINEER CERTIFICATEFile: Form 6.pdf5 Mar 2025
ORIGINAL PLANFile: Original plan.pdf5 Mar 2025
PLANFile: Plan.pdf5 Mar 2025
PROJECT SPECIFICATION AND AMENITIESFile: Project specification and amenities.pdf5 Mar 2025
STABILITY STRUTURAL CERTIFICATEFile: Stability structural certificate.pdf5 Mar 2025
TYPICAL FLOOR PLANFile: Typical floor plan.pdf5 Mar 2025
TYPICAL PLAN ALL FLOORFile: Typical plan all flor.pdf5 Mar 2025
HESCOM NOCFile: hescom permission.pdf5 Mar 2025
ADDITIONAL FEE PAYMENT CLARIFICATIONFile: Project Area Clarification for RERA Fees Payment.pdf5 Mar 2025
MASTER PLANFile: master plan.pdf5 Mar 2025
MOTHER DEEDFile: Mother Deed.pdf5 Mar 2025
SALE DEEDFile: SALE DEED OF LAND.pdf5 Mar 2025
STP DRAWINGFile: STP Drawing.pdf5 Mar 2025
SALE DEED CHIRAGFile: Chirag sale deed.pdf5 Mar 2025
SALE DEED DIVYANKFile: Divyank sale deed.pdf5 Mar 2025
SALE DEED PRAKASH AND KIRANFile: Prakash and kiran sale deed.pdf5 Mar 2025
SALE DEED YOGESHFile: Yogesh sale deed.pdf5 Mar 2025
LATEST RTCFile: RTC upto tiil date.pdf15 Jan 2025
EC FROM 01/01/2009 TIIL DATEFile: EC up to till Date merged.pdf15 Jan 2025
BALANCE SHEETFile: BALANCE SHEET FY 22-23.pdf15 Jan 2025
PROFIT AND LOSS ACCOUNTFile: Profit and loss account 2022 23.pdf15 Jan 2025
INCOME TAX RETURNSFile: ITR MWS TOWERS FY 22-23.pdf15 Jan 2025
APPROVAL LAYOUT PLAN ( SANCTIONED TYPICAL PLAN )File: Aprovel Layout Plan.pdf15 Jan 2025
BASEMENT FLOOR PLAN ( PARKING )File: Aprovel Layout PLan 2.pdf15 Jan 2025
SINGLE PLOT LAYOUT PLANFile: Single plot layout plan.pdf15 Jan 2025
Agreement For SaleFile: Agreement of Sale Proforma Ruby.pdf11 Dec 2024
Balancesheet 2021-22File: Balance sheet 2021-22.pdf11 Dec 2024
Balancesheet 2022-23File: BALANCE SHEET FY 22-23.pdf11 Dec 2024
Curent Year RTCFile: Cureent Year RTC.pdf11 Dec 2024
EC Up tp till dateFile: EC_up_to_till_Date.pdf11 Dec 2024
Hescom permissionFile: hescom permission.pdf11 Dec 2024
ITR 2021-22File: ITR 2021-22.pdf11 Dec 2024
Profit & Loss 2021-22File: Profit and loss account 2021-22.pdf11 Dec 2024
ITR 2022-23File: ITR FY 22-23.pdf11 Dec 2024
P&L 2022-23File: Profit & Loss 2023-24.pdf11 Dec 2024
MutationFile: Mutation.pdf11 Dec 2024
MOU AgreementFile: MOU Agreement.pdf11 Dec 2024
Area Statment for RERA Fees PaymentFile: Project Area Clarification for RERA Fees Payment.pdf11 Dec 2024
land sale deedsFile: LAND SALE DEED-compressed.pdf11 Dec 2024
land sale deedsFile: SALE DEED OF LAND.pdf11 Dec 2024
land sale deedsFile: sale deed.pdf11 Dec 2024
building permissionFile: ApprovalCertificate.pdf11 Dec 2024
Balancesheet 2022-23 With CA UDINFile: BALANCE_SHEET_FY_22-23[1].pdf9 Oct 2024
Profit & Loss Account 2022-23 With CA UDINFile: P&L_FY_22-23[1].pdf9 Oct 2024
Relevent Title DeedFile: LAND_SALE_DEED[1].pdf9 Oct 2024
MOU AgreementFile: MOU Agreement.pdf9 Oct 2024
RTC Full Exetent The ProjectFile: RTC_upto_tiil_date[1].pdf9 Oct 2024
Approvel Building PlanFile: Aprovel Building Plan.pdf9 Oct 2024
Aproved Parking PlanFile: Aprovel Parking Plan.pdf9 Oct 2024
HESCOM PermissionFile: HESCOM permission.pdf9 Oct 2024

How this compares with Dharwad

24%of this project is bookeddistrict median 38%
29%of Dharwad projects moved their completion datethis one has not
0%of Dharwad registrations are shown as withdrawn or revokedthis one is not

Computed across the 250+ Dharwad projects on ReraGenie, from their own filings.

Keep RUBY TOWERS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dharwad250+ in Dharwad

Builder: M/S MWS TOWERS

M/S MWS TOWERS has 2 registrations on RERA Karnataka, including WORLD SQUARE TOWERS and RUBY TOWERS. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Dharwad district page.

Frequently asked questions

What are my rights if RUBY TOWERS is delayed beyond 30 Sep 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of RUBY TOWERS?

The registered promoter entity is M/S MWS TOWERS, a partnership firm as per the filing. Its GSTIN 29ABKFM2789DIZU can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in RUBY TOWERS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at RUBY TOWERS?

The professionals named in the filing: Architect: Shreekant N Kabadi; Engineer: Shreekant N Kabadi; Chartered Accountant: Hiteskumar Modi. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in RUBY TOWERS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About RUBY TOWERS. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save RUBY TOWERS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.