Home / Browse projects / Vadodara, Gujarat / Royalisa

Valid until 28 Mar 2022 Mixed Development project

Royalisa

By Om Associates

RG-GJ-93937 · RERA PR/GJ/VADODARA/VADODARA/Others/MAA04696/EX1/090621 · Last updated on GujRERA portal: 26 Mar 2022

Source: official GujRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Separate project account declared
Mar 2022Possession promisedmoved 12 months from the original
23 of 24Construction stages doneacross 3 buildings; furthest along: Stilt Floor, 0%
25 of 66Units unsoldnot recorded sold or booked
Jump to the 40 documents Report an error

Royalisa is a Mixed Development project by Om Associates in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/MAA04696/EX1/090621 on 18 Jan 2019. Possession is promised by 28 Mar 2022. The completion date has moved by 12 months from the original filing. 41 of the 66 units on this registration are recorded sold or booked, and 23 of 24 construction stages are filed complete.

At a glance

Project

  • NameRoyalisa
  • TypeMixed Development
  • Location
    • Royalisa
    • Near Krishna Party Plot
    • Harni Sama Link Road
    • Harni
    • Vadodara
    • 390022
  • Pincode390022
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/MAA04696/EX1/090621
  • ReraGenie IDRG-GJ-93937

Builder

  • NameOm Associates
  • Entity typePARTNERSHIP FIRM
  • Other registrations1 more →

Key dates

this monthRegisteredJan 2019First promiseMar 2021Revised toMar 2022

Key facts

Registration and timeline

  • StatusValid until 28 Mar 2022
  • Registered on18 Jan 2019
  • Promised completion28 Mar 2022
  • Revised completionRevised to 28 Mar 2022 (originally 30 Mar 2021)
  • Buildings3 building records
  • Documents filed40 files

Current status

62%41 of 66 units booked
99.0%Of the estimated cost spent so far

Figures as on 26 Mar 2022, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOWER - A---18422
TOWER - B---20020
TOWER - C---20424

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building3

As on 26 Mar 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

23 of 24 construction stages are filed complete across 3 buildings. The stage furthest along is Stilt Floor, at 0%.

TOWER - A88%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TOWER - B100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TOWER - C100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 26 Mar 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,054 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 5.30 cr
Cost incurredRs 5.25 cr
Spent of the estimate99.01%
BuildingWingEstimatedIncurred
TOWER - ANARs 1.77 crRs 1.75 cr
TOWER - BNARs 1.77 crRs 1.75 cr
TOWER - CNARs 1.77 crRs 1.75 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRUCHIR SHETH
EngineerNitin Siddhpura

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/VADODARA/VADODARA/Others/MAA04696/EX1/090621Applied Mar 2021; approved Jun 2021

Documents filed40

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/MAA04696/EX1/090621 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)26 Mar 2022
Engineer's certificate (Form 2)26 Mar 2022
Engineer's certificate annexure26 Mar 2022
Accountant's certificate (Form 3)26 Mar 2022
Site photograph, TOWER - A26 Mar 2022
Site photograph, TOWER - B26 Mar 2022
Site photograph, TOWER - C26 Mar 2022
RERA registration certificate18 Jan 2019
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

62%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one moved by 12 months

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep Royalisa on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Harni2,900+ in Vadodara

2 kmRoyalisaOther 195Dot size: filed unitsN

Filed coordinates, straight-line distance. 195 registered projects within 2 km.

Builder: Om Associates

Om Associates has 2 registrations on GujRERA, including Royalisa and OM AASHRAY. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if Royalisa is delayed beyond 28 Mar 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Royalisa?

The registered promoter entity is Om Associates, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Royalisa?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Royalisa?

The professionals named in the filing: Architect: RUCHIR SHETH; Engineer: Nitin Siddhpura. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Royalisa?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Royalisa. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Royalisa to a free account