Valid until 31 Mar 2027 Commercial project

RIZE

By TRIVEDAA

RG-GJ-00352 · RERA PR/GJ/SURAT/SURAT CITY/Surat Municipal Corporation/CAA14566/EX1/170426/310327 · Last updated on GujRERA portal: 25 Feb 2026

Source: official GujRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Nothing verified clear yet
Mar 2027Possession promisedmoved 12 months from the original
3 of 9Construction stages donefurthest along: Internal walls, 88%
82 of 93Units unsoldnot recorded sold or booked
Jump to the 31 documents Report an error

RIZE is a Commercial project by TRIVEDAA in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/SURAT CITY/Surat Municipal Corporation/CAA14566/EX1/170426/310327 on 23 Dec 2024. Possession is promised by 31 Mar 2027. The completion date has moved by 12 months from the original filing. 11 of the 93 units on this registration are recorded sold or booked, and 3 of 9 construction stages are filed complete.

At a glance

Project

  • NameRIZE
  • TypeCommercial
  • Location
    • OLD REVENUE SURVEY NO. 4 HISSA 3/1/B
    • AFTER CONSOLIDATION BLOCK NO 11
    • T.P. NO. 13 (BHARTHANA-VESU)
    • F.P. NO. 17
    • OP NO 11
    • VESU
    • Surat City
    • Surat
    • 395007
  • Pincode395007
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/SURAT/SURAT CITY/Surat Municipal Corporation/CAA14566/EX1/170426/310327
  • ReraGenie IDRG-GJ-00352

Builder

  • NameTRIVEDAA
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredDec 2024First promiseMar 2026Revised toMar 2027

Key facts

Registration and timeline

  • StatusValid until 31 Mar 2027
  • Registered on23 Dec 2024
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 31 Mar 2026)
  • Buildings1 building record
  • Documents filed31 files

Current status

12%11 of 93 units booked
84.2%Of the estimated cost spent so far

Figures as on 25 Feb 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---09393

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 25 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 9 construction stages are filed complete. The stage furthest along is Internal walls, at 88%.

A: 63% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats88%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing80%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing20%

Progress on shared amenities19

As on 25 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsNoNot applicable
Water supplyYes50%
Sewerage (chamber, lines, septic tank, STP)Yes80%
Storm water drainsYes80%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes40%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesYes0%
Emergency evacuationYes0%
Use of renewable energyNoNot applicable
SecurityYes0%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,200 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 9.50 cr
Cost incurredRs 8.00 cr
Spent of the estimate84.21%
BuildingWingEstimatedIncurred
ANARs 9.50 crRs 8.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAPURVA ASHOKKUMAR DESAI
EngineerJAY BHAGVANBHAI LAKHANAKIYA

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/SURAT/SURAT CITY/Surat Municipal Corporation/CAA14566/EX1/170426/310327Applied Feb 2026; approved Apr 2026

Documents filed31

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/SURAT CITY/Surat Municipal Corporation/CAA14566/EX1/170426/310327 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)25 Feb 2026
Engineer's certificate (Form 2)25 Feb 2026
Engineer's certificate annexure25 Feb 2026
Accountant's certificate (Form 3)25 Feb 2026
Site photograph, A25 Feb 2026
RERA registration certificate23 Dec 2024
Extension certificate-
Proforma agreement for sale-
Auditor's report (3 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Statutory document-
Project photograph-
Proforma sale deed-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (3 of 3)-

How this compares with Surat

12%of this project is bookeddistrict median 39%
15%of Surat projects moved their completion datethis one moved by 12 months

Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.

Keep RIZE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near VESU2,600+ in Surat

2 kmRIZEOther 198Dot size: filed unitsN

Filed coordinates, straight-line distance. 198 registered projects within 2 km.

Builder: TRIVEDAA

TRIVEDAA has 1 registration on GujRERA, including RIZE. Read the full track record. See more projects on the Surat district page.

Frequently asked questions

What are my rights if RIZE is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of RIZE?

The registered promoter entity is TRIVEDAA, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in RIZE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at RIZE?

The professionals named in the filing: Architect: APURVA ASHOKKUMAR DESAI; Engineer: JAY BHAGVANBHAI LAKHANAKIYA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in RIZE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About RIZE. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save RIZE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.