REDWOOD CELEST is a Group Housing project by REDWOOD BUILD DEVELOPERS in Jaipur, Rajasthan, registered with RERA Rajasthan as RAJ/P/2023/2778 on 23 Oct 2023. Possession is promised by 9 Jan 2027.
At a glance
Project
- TypeGroup Housing
- Location
- Khasra No./ Plot No.Plot No. A-90
- A-91
- A-92
- A-111 and A-112
- Village- Badh Chela
- Lotus Villa
- Jagatpura
- Jaipur - 302017 (Rajasthan)
- Jaipur
- PincodeNot stated
- RERA no.RAJ/P/2023/2778
- ReraGenie IDRG-RJ-71892
Builder
- NameREDWOOD BUILD DEVELOPERS
- Entity typePartnership Firm
- Other registrations2 more →
- Completed2 of 3
- No longer live1 lapsed or revoked
Registration and timeline
- StatusRegistration revoked
- Registered on23 Oct 2023
- Promised completion9 Jan 2027
- Revised completionNone
- Documents filed6 on the register's page, not listed here
Key dates
The full filing
Everything below is from the project's own RERA Rajasthan filing, free to read.
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Jaipur
Computed across the 2,400+ Jaipur projects on ReraGenie, from their own filings.
Keep REDWOOD CELEST on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects in Jaipur2,400+ in Jaipur
"GOVERDHAN VATIKA"
Bordiya Balaji Builders And Developers Pri
"LANDMARK"
BADRINATH INFRAPROJECTS PVT LTD
"ROYAL AANGAN BLOCK-A EXT."
GOKUL KRIPA COLONIZERS AND DEVELOPERS PVT.
"THE ELEGANCE"
NEW PATH DEVELOPERS LLP
''PLATINUM GREENS''
RIYASAT INFRA DEVELOPERS PRIVATE LIMITED
14 WOODLAND PARK
WOODLAND PARK BUILDCON LLP
See every Jaipur project, with the district possession charts
Builder: REDWOOD BUILD DEVELOPERS
REDWOOD BUILD DEVELOPERS has 3 registrations on RERA Rajasthan, including REDWOOD ORION and REDWOOD KOSMOS. Read the full track record. See more projects on the Jaipur district page.
Frequently asked questions
What does it mean that REDWOOD CELEST shows as registration revoked on RERA Rajasthan?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the RERA Rajasthan portal, and take legal advice before paying any further instalment.
What are my rights if REDWOOD CELEST is delayed beyond 9 Jan 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Rajasthan.
How do I verify and contact the developer of REDWOOD CELEST?
The registered promoter entity is REDWOOD BUILD DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Rajasthan listing and in its filed documents.
Is my payment protected in REDWOOD CELEST?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
What should I check before booking in REDWOOD CELEST?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Rajasthan, and we read every report.
Report an error Share feedback