Home / Browse projects / Bharuch, Gujarat / RANG CITY

Valid until 31 Mar 2020 Residential/Group Housing project

RANG CITY

By AVDHOOT BUILDERS

RG-GJ-86465 · RERA PR/GJ/BHARUCH/BHARUCH/Others/RAA01310/EX1/020519 · Last updated on GujRERA portal: 12 Feb 2020

Source: official GujRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Separate project account declared
Mar 2020Possession promisedmoved 12 months from the original
18 of 18Construction stages doneacross 3 buildings; every applicable stage filed complete
18 of 107Units unsoldnot recorded sold or booked
Jump to the 40 documents Report an error

RANG CITY is a Residential/Group Housing project by AVDHOOT BUILDERS in Bharuch, Gujarat, registered with GujRERA as PR/GJ/BHARUCH/BHARUCH/Others/RAA01310/EX1/020519 on 16 Jan 2018. Possession is promised by 31 Mar 2020. The completion date has moved by 12 months from the original filing. 89 of the 107 units on this registration are recorded sold or booked, and 18 of 18 construction stages are filed complete.

At a glance

Project

  • NameRANG CITY
  • TypeResidential/Group Housing
  • Location
    • RS 188/189 OPP SNPS PUBLIC SCHOOL
    • CHAVAJ ROAD
    • Chavaj
    • Bharuch
    • 392001
  • Pincode392001
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/BHARUCH/BHARUCH/Others/RAA01310/EX1/020519
  • ReraGenie IDRG-GJ-86465

Builder

  • NameAVDHOOT BUILDERS
  • Entity typePARTNERSHIP FIRM
  • Other registrations2 more →

Key dates

this monthRegisteredJan 2018First promiseMar 2019Revised toMar 2020

Key facts

Registration and timeline

  • StatusValid until 31 Mar 2020
  • Registered on16 Jan 2018
  • Promised completion31 Mar 2020
  • Revised completionRevised to 31 Mar 2020 (originally 31 Mar 2019)
  • Buildings3 building records
  • Documents filed40 files

Current status

83%89 of 107 units booked
101.0%Of the estimated cost spent so far

Figures as on 12 Feb 2020, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TYPE A---81081
TYPE B---11011
TYPE C---15015

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building3

As on 12 Feb 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 18 construction stages are filed complete across 3 buildings.

TYPE A100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
TYPE B100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
TYPE C100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable

Progress on shared amenities19

As on 12 Feb 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area14,592 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 6.95 cr
Cost incurredRs 7.01 cr
Spent of the estimate100.97%
BuildingWingEstimatedIncurred
TYPE ANARs 2.32 crRs 2.34 cr
TYPE BNARs 2.32 crRs 2.34 cr
TYPE CNARs 2.32 crRs 2.34 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNISARG RACHNA
EngineerSVN CONSULTING ENGINEER

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/BHARUCH/BHARUCH/Others/RAA01310/EX1/020519Applied Mar 2019; approved May 2019

Documents filed40

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/BHARUCH/BHARUCH/Others/RAA01310/EX1/020519 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)12 Feb 2020
Engineer's certificate (Form 2)12 Feb 2020
Engineer's certificate annexure12 Feb 2020
Accountant's certificate (Form 3)12 Feb 2020
Site photograph, TYPE A12 Feb 2020
Site photograph, TYPE B12 Feb 2020
Site photograph, TYPE C12 Feb 2020
RERA registration certificate16 Jan 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Bharuch

83%of this project is bookeddistrict median 52%
20%of Bharuch projects moved their completion datethis one moved by 12 months

Computed across the 200+ Bharuch projects on ReraGenie, from their own filings.

Keep RANG CITY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Chavaj200+ in Bharuch

2 kmRANG CITYOther 25Dot size: filed unitsN

Filed coordinates, straight-line distance. 25 registered projects within 2 km.

Builder: AVDHOOT BUILDERS

AVDHOOT BUILDERS has 3 registrations on GujRERA, including RANG CITY and RANG CITY COMPLEX. Read the full track record. See more projects on the Bharuch district page.

Frequently asked questions

What are my rights if RANG CITY is delayed beyond 31 Mar 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of RANG CITY?

The registered promoter entity is AVDHOOT BUILDERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in RANG CITY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at RANG CITY?

The professionals named in the filing: Architect: NISARG RACHNA; Engineer: SVN CONSULTING ENGINEER. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in RANG CITY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About RANG CITY. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save RANG CITY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.