Home / Browse projects / Kutch, Gujarat / RAJVI GARDEN
RAJVI GARDEN
By YARMOUTH REALTY PRIVATE LIMITED
RG-GJ-10715 · RERA PR/GJ/KUTCH/GANDHIDHAM/Gandhidham Development Authority/RAA10613/A1R/060724/310327 · Last updated on GujRERA portal: 21 May 2026
Source: official GujRERA filing
Red flags
- No red flags in this filing
Clear
- Completion date never moved
Saved.
RAJVI GARDEN is a Residential/Group Housing project by YARMOUTH REALTY PRIVATE LIMITED in Kutch, Gujarat, registered with GujRERA as PR/GJ/KUTCH/GANDHIDHAM/Gandhidham Development Authority/RAA10613/A1R/060724/310327 on 2 Sep 2022. Possession is promised by 31 Jul 2027. 91 of the 125 units on this registration are recorded sold or booked, and 44 of 54 construction stages are filed complete.
At a glance
Project
- NameRAJVI GARDEN
- TypeResidential/Group Housing
- Location
- R. S. NO. 129/35 Paiky 4
- Opp. Galpadar Lake
- Gandhidham
- Kutch
- PincodeNot stated
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR/GJ/KUTCH/GANDHIDHAM/Gandhidham Development Authority/RAA10613/A1R/060724/310327
- ReraGenie IDRG-GJ-10715
Builder
- NameYARMOUTH REALTY PRIVATE LIMITED
- Entity typeCOMPANY
Key dates
Key facts
Registration and timeline
- StatusValid until 31 Jul 2027
- Registered on2 Sep 2022
- Promised completion31 Jul 2027
- Revised completionNone
- Buildings6 building records
- Documents filed48 files
Current status
Figures as on 21 May 2026, this project's latest GujRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| RESI 87 TO 107 | - | - | - | 21 | 0 | 21 |
| RESI 64 TO 86 | - | - | - | 23 | 0 | 23 |
| RESI 108 TO 125 | - | - | - | 18 | 0 | 18 |
| RESI 1 TO 16 | - | - | - | 16 | 0 | 16 |
| RESI 41 TO 63 | - | - | - | 23 | 0 | 23 |
| RESI 17 TO 40 | - | - | - | 24 | 0 | 24 |
The full filing
Everything below is from the project's own GujRERA filing, free to read.
Construction progress by building6
As on 21 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
44 of 54 construction stages are filed complete across 6 buildings. The stage furthest along is External plumbing and external plaster, at 40%.
RESI 87 TO 10791%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 20% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
RESI 64 TO 8693%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 40% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
RESI 108 TO 125100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
RESI 1 TO 1667%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
RESI 41 TO 6380%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 20% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
RESI 17 TO 4071%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 40% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Progress on shared amenities19
As on 21 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal roads and footpaths | Yes | 50% |
| Water supply | Yes | 45% |
| Sewerage (chamber, lines, septic tank, STP) | Yes | 55% |
| Storm water drains | Yes | 0% |
| Landscaping and tree planting | Yes | 100% |
| Street lighting | Yes | 0% |
| Community buildings | No | Not applicable |
| Treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Water conservation, rain water harvesting | No | Not applicable |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Fire fighting | No | Not applicable |
| Drinking water facilities | Yes | 20% |
| Emergency evacuation | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Security | Yes | 50% |
| Letter box | No | Not applicable |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| RESI 108 TO 125 | NA | Rs 4.76 cr | Rs 4.76 cr |
| RESI 17 TO 40 | NA | Rs 3.76 cr | Rs 3.56 cr |
| RESI 41 TO 63 | NA | Rs 3.64 cr | Rs 3.64 cr |
| RESI 64 TO 86 | NA | Rs 3.64 cr | Rs 3.60 cr |
| RESI 87 TO 107 | NA | Rs 3.60 cr | Rs 3.25 cr |
| RESI 1 TO 16 | NA | Rs 3.10 cr | Rs 3.10 cr |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | DIVYESH DESAI |
| Engineer | KALPEN SOMPURA |
Documents filed48
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/KUTCH/GANDHIDHAM/Gandhidham Development Authority/RAA10613/A1R/060724/310327 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Engineer's certificate (Form 2) | 21 May 2026 |
| Engineer's certificate annexure | 21 May 2026 |
| Accountant's certificate (Form 3) | 21 May 2026 |
| Architect's certificate (Form 1) | 20 May 2026 |
| Site photograph, RESI 87 TO 107 | 20 May 2026 |
| Site photograph, RESI 64 TO 86 | 20 May 2026 |
| Site photograph, RESI 108 TO 125 | 20 May 2026 |
| Site photograph, RESI 1 TO 16 | 20 May 2026 |
| Site photograph, RESI 41 TO 63 | 20 May 2026 |
| Site photograph, RESI 17 TO 40 | 20 May 2026 |
| RERA registration certificate | 2 Sep 2022 |
| Alteration certificate | - |
| Proforma agreement for sale | - |
| Auditor's report (1 of 3) | - |
| Auditor's report (2 of 3) | - |
| Auditor's report (3 of 3) | - |
| Income tax return (1 of 3) | - |
| Income tax return (2 of 3) | - |
| Income tax return (3 of 3) | - |
| Project specific document | - |
| Directors' report (1 of 3) | - |
| Directors' report (2 of 3) | - |
| Directors' report (3 of 3) | - |
| Approved sanctioned plan | - |
| Approved layout plan | - |
| Agreement | - |
| Land location | - |
| Encumbrance certificate | - |
| Area development document | - |
| Proforma allotment letter | - |
| Brochure | - |
| Project related document | - |
| Declaration in Form B | - |
| Approved building or plotting plan | - |
| Title clearance certificate | - |
| Title report | - |
| Property card | - |
| Proforma sale deed | - |
| Project photograph | - |
| Audited balance sheet (1 of 3) | - |
| Audited balance sheet (2 of 3) | - |
| Audited balance sheet (3 of 3) | - |
| Audited profit and loss statement (1 of 3) | - |
| Audited profit and loss statement (2 of 3) | - |
| Audited profit and loss statement (3 of 3) | - |
| Cash flow statement (1 of 3) | - |
| Cash flow statement (2 of 3) | - |
| Cash flow statement (3 of 3) | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Kutch
Computed across the 80 Kutch projects on ReraGenie, from their own filings.
Keep RAJVI GARDEN on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Gandhidham80 in Kutch
Filed coordinates, straight-line distance. 13 registered projects within 2 km.
SANGHVI HOMES
SUMANRAVISANGHVI AND OTHERS
522 LIG KAILASHNAGAR
GUJARAT HOUSING BOARD
Rajvi Park - Plot
Arti Dhaval Acharya
ARAVALI
HEMAL VINODBHAI THACKER & ARTI VASANTKUMAR
SURAMYA 158
ASHOKKUMAR AMARCHAND SINGHVI
BAGESHREE TOWNSHIP - 9
OM INFRA
See every Kutch project, with the district possession charts
Builder: YARMOUTH REALTY PRIVATE LIMITED
YARMOUTH REALTY PRIVATE LIMITED has 1 registration on GujRERA, including RAJVI GARDEN. Read the full track record. See more projects on the Kutch district page.
Frequently asked questions
What are my rights if RAJVI GARDEN is delayed beyond 31 Jul 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.
How do I verify and contact the developer of RAJVI GARDEN?
The registered promoter entity is YARMOUTH REALTY PRIVATE LIMITED, a company as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.
Is my payment protected in RAJVI GARDEN?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at RAJVI GARDEN?
The professionals named in the filing: Architect: DIVYESH DESAI; Engineer: KALPEN SOMPURA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in RAJVI GARDEN?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.