Red flags

  • Completion date moved by 23 months
  • 2 extensions taken

Clear

  • Nothing verified clear yet
Apr 2026Possession promisedmoved 23 months from the original
41 of 45Construction stages doneacross 5 buildings; furthest along: External plumbing and external plaster, 97%
70 of 192Units unsoldnot recorded sold or booked
Jump to the 38 documents Report an error

RAJVI EXOTICA is a Residential/Group Housing project by RAJVI INFRASTRUCTURE in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA06799/EX1/EX2/300625/300426 on 25 Feb 2020. Possession is promised by 30 Apr 2026. The completion date has moved by 23 months from the original filing. 122 of the 192 units on this registration are recorded sold or booked, and 41 of 45 construction stages are filed complete.

At a glance

Project

  • NameRAJVI EXOTICA
  • TypeResidential/Group Housing
  • Location
    • RAJVI EXOTICA
    • NR. SOMNATH PARTY PLOT
    • B/H. DEVSHYA INTERNATIONAL SCHOOL
    • NIKOL
    • Nikol
    • Ahmedabad City
    • Ahmedabad
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA06799/EX1/EX2/300625/300426
  • ReraGenie IDRG-GJ-20582

Builder

  • NameRAJVI INFRASTRUCTURE
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredFeb 2020First promiseMay 2024Revised toApr 2026

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2026
  • Registered on25 Feb 2020
  • Promised completion30 Apr 2026
  • Revised completionRevised to 30 Apr 2026 (originally 1 May 2024)
  • Buildings5 building records
  • Documents filed38 files

Current status

64%122 of 192 units booked
99.6%Of the estimated cost spent so far

Figures as on 21 Mar 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A + B---56056
C---28028
D---26026
E + F---56056
G---26026

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building5

As on 21 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

41 of 45 construction stages are filed complete across 5 buildings. The stage furthest along is External plumbing and external plaster, at 97%.

A + B98%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor95%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats95%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%
C100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
D100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
E + F100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
G100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing97%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities23

As on 21 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterYes90%
Solid waste management and disposalYes50%
Water conservation, rain water harvestingYes60%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes60%
Electrical meter room, sub-station, receiving stationYes60%
Fire fightingYes60%
Drinking water facilitiesYes60%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes60%
Letter boxYes60%
Compound wallYes100%
Plinth protectionYes100%
Water tankYes100%
Other requirementsYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area8,316 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 43.00 cr
Cost incurredRs 42.82 cr
Spent of the estimate99.57%
BuildingWingEstimatedIncurred
A + BNARs 12.63 crRs 12.50 cr
E + FNARs 12.63 crRs 12.63 cr
CNARs 6.20 crRs 6.20 cr
GNARs 5.78 crRs 5.73 cr
DNARs 5.76 crRs 5.76 cr

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA06799/EX1/240524/300425Applied Mar 2024; approved May 2024
PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA06799/EX1/EX2/300625/300426Applied Mar 2025; approved Jun 2025

Documents filed38

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA06799/EX1/EX2/300625/300426 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)21 Mar 2025
Engineer's certificate annexure21 Mar 2025
RERA registration certificate25 Feb 2020
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Proforma sale deed-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

64%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one moved by 23 months

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep RAJVI EXOTICA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Nikol5,400+ in Ahmedabad

2 kmRAJVI EXOTICAOther 304Dot size: filed unitsN

Filed coordinates, straight-line distance. 304 registered projects within 2 km.

Builder: RAJVI INFRASTRUCTURE

RAJVI INFRASTRUCTURE has 1 registration on GujRERA, including RAJVI EXOTICA. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if RAJVI EXOTICA is delayed beyond 30 Apr 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of RAJVI EXOTICA?

The registered promoter entity is RAJVI INFRASTRUCTURE, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in RAJVI EXOTICA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in RAJVI EXOTICA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About RAJVI EXOTICA. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save RAJVI EXOTICA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.