Valid until 30 Apr 2031 Residential/Group Housing project

RAJHANS SILVANA

By RAJHANS INFRACON (INDIA) PRIVATE LIMITED

RG-GJ-16228 · RERA PR/GJ/SURAT/SURAT CITY/Surat Municipal Corporation/RAA14345/281024/311230 · Last updated on GujRERA portal: 28 Oct 2024

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Apr 2031Possession promisedno revision filed
12 of 54Construction stages doneacross 6 buildings; furthest along: Slabs of Super Structure, 82%
101 of 108Units unsoldnot recorded sold or booked
Jump to the 39 documents Report an error

RAJHANS SILVANA is a Residential/Group Housing project by RAJHANS INFRACON (INDIA) PRIVATE LIMITED in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/SURAT CITY/Surat Municipal Corporation/RAA14345/281024/311230 on 28 Oct 2024. Possession is promised by 30 Apr 2031. 7 of the 108 units on this registration are recorded sold or booked, and 12 of 54 construction stages are filed complete.

At a glance

Project

  • NameRAJHANS SILVANA
  • TypeResidential/Group Housing
  • Location
    • BLOCK NO:- 223
    • O.P. NO: - 112
    • F.P NO:-145
    • AT PRELIMINARY T.P.S. NO: - 13 (BHARTHANA-VESU)
    • MOJE: BHARTHANA
    • TA: SURAT CITY
    • DIST: - SURAT
    • BHARTHANA -...
  • Pincode395007
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/SURAT/SURAT CITY/Surat Municipal Corporation/RAA14345/281024/311230
  • ReraGenie IDRG-GJ-16228

Builder

  • NameRAJHANS INFRACON (INDIA) PRIVATE LIMITED
  • Entity typeCOMPANY
  • Other registrations18 more →

Key dates

this monthRegisteredOct 2024PromisedApr 2031

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2031
  • Registered on28 Oct 2024
  • Promised completion30 Apr 2031
  • Revised completionNone
  • Buildings6 building records
  • Documents filed39 files

Current status

6%7 of 108 units booked
13.7%Of the estimated cost spent so far

Figures as on 28 Oct 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
B---18018
A---18018
D---18018
C---18018
F---18018
E---18018

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building6

As on 28 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

12 of 54 construction stages are filed complete across 6 buildings. The stage furthest along is Slabs of Super Structure, at 82%.

B43%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure82%
Internal walls, internal plaster, floorings, doors and windows within flats55%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks55%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
A39%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure82%
Internal walls, internal plaster, floorings, doors and windows within flats36%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks36%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
D45%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure82%
Internal walls, internal plaster, floorings, doors and windows within flats64%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks64%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
C43%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure82%
Internal walls, internal plaster, floorings, doors and windows within flats55%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks55%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
F39%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure82%
Internal walls, internal plaster, floorings, doors and windows within flats36%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks36%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
E43%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure82%
Internal walls, internal plaster, floorings, doors and windows within flats55%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks55%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities23

As on 28 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsYes0%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesYes0%
Emergency evacuationYes0%
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxYes0%
Compound wallYes0%
Plinth protectionYes0%
Water tankYes0%
Other requirementsNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area13,243 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 102.00 cr
Cost incurredRs 14.00 cr
Spent of the estimate13.73%
BuildingWingEstimatedIncurred
ANARs 17.00 crRs 2.50 cr
BNARs 17.00 crRs 2.50 cr
CNARs 17.00 crRs 2.50 cr
DNARs 17.00 crRs 2.50 cr
ENARs 17.00 crRs 2.50 cr
FNARs 17.00 crRs 1.50 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKrishnapalsinh Bhupendrasinh Gohel
EngineerLALITKUMAR MOHANLAL KHENI

Documents filed39

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/SURAT CITY/Surat Municipal Corporation/RAA14345/281024/311230 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
RERA registration certificate28 Oct 2024
Engineer's certificate (Form 2)14 Oct 2024
Engineer's certificate annexure14 Oct 2024
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Statutory document-
Project photograph-
Proforma sale deed-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Surat

6%of this project is bookeddistrict median 39%
15%of Surat projects moved their completion datethis one has not

Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.

Keep RAJHANS SILVANA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near BHARTHANA - VESU2,600+ in Surat

2 kmRAJHANS SILVANAOther 202Dot size: filed unitsN

Filed coordinates, straight-line distance. 202 registered projects within 2 km.

Builder: RAJHANS INFRACON (INDIA) PRIVATE LIMITED

RAJHANS INFRACON (INDIA) PRIVATE LIMITED has 19 registrations on GujRERA, including RAJHANS GRANDEZZA and RAJHANS ROYALTON. Read the full track record. See more projects on the Surat district page.

Frequently asked questions

What are my rights if RAJHANS SILVANA is delayed beyond 30 Apr 2031?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of RAJHANS SILVANA?

The registered promoter entity is RAJHANS INFRACON (INDIA) PRIVATE LIMITED, a company as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in RAJHANS SILVANA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at RAJHANS SILVANA?

The professionals named in the filing: Architect: Krishnapalsinh Bhupendrasinh Gohel; Engineer: LALITKUMAR MOHANLAL KHENI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in RAJHANS SILVANA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About RAJHANS SILVANA. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save RAJHANS SILVANA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.