Home / Browse projects / Vadodara, Gujarat / RAJESHWAR GALAXY

Valid until 31 Dec 2025 Residential/Group Housing project

RAJESHWAR GALAXY

By Propritorship of Shri Raj Associates

RG-GJ-42977 · RERA PR/GJ/VADODARA/VADODARA/Vadodara Municipal Corporation/RAA04275/A1R/EX3/281125/311225 · Last updated on GujRERA portal: 17 Nov 2025

Source: official GujRERA filing

Red flags

  • Completion date moved by 59 months
  • 3 extensions taken

Clear

  • Nothing verified clear yet
Dec 2025Possession promisedmoved 59 months from the original
59 of 81Construction stages doneacross 9 buildings; furthest along: Sanitary fittings within the flats, 90%
14 of 184Units unsoldnot recorded sold or booked
Jump to the 52 documents Report an error

RAJESHWAR GALAXY is a Residential/Group Housing project by Propritorship of Shri Raj Associates in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Vadodara Municipal Corporation/RAA04275/A1R/EX3/281125/311225 on 6 Dec 2018. Possession is promised by 31 Dec 2025. The completion date has moved by 59 months from the original filing. 170 of the 184 units on this registration are recorded sold or booked, and 59 of 81 construction stages are filed complete.

At a glance

Project

  • NameRAJESHWAR GALAXY
  • TypeResidential/Group Housing
  • Location
    • B/h. Rajeshwar Gold
    • Nr. Vallam Hall
    • Harni-Golden Chowkdi Road
    • Harni
    • Harni
    • Vadodara
    • 390022
  • Pincode390022
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Vadodara Municipal Corporation/RAA04275/A1R/EX3/281125/311225
  • ReraGenie IDRG-GJ-42977

Builder

  • NamePropritorship of Shri Raj Associates
  • Entity typeIndividual/Propritorship

Key dates

this monthRegisteredDec 2018First promiseJan 2021Revised toDec 2025

Key facts

Registration and timeline

  • StatusValid until 31 Dec 2025
  • Registered on6 Dec 2018
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 31 Jan 2021)
  • Buildings9 building records
  • Documents filed52 files

Current status

92%170 of 184 units booked
88.9%Of the estimated cost spent so far

Figures as on 17 Nov 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A3---22022
A4---22022
A5---20020
B6---20020
B7---20020
B8---20020
B9---20020
B10---20020
B11---20020

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building9

As on 17 Nov 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

59 of 81 construction stages are filed complete across 9 buildings. The stage furthest along is Sanitary fittings within the flats, at 90%.

A373%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats90%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing90%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing90%
A478%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
A578%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B678%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B778%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B878%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B978%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B1078%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B1178%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 17 Nov 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes90%
Sewerage (chamber, lines, septic tank, STP)Yes90%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalYes100%
Water conservation, rain water harvestingYes100%
Energy managementYes100%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes90%
Fire fightingNoNot applicable
Drinking water facilitiesYes90%
Emergency evacuationNoNot applicable
Use of renewable energyYes100%
SecurityYes90%
Letter boxYes90%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area11,083 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 23.05 cr
Cost incurredRs 20.49 cr
Spent of the estimate88.89%
BuildingWingEstimatedIncurred
A3NARs 2.56 crRs 2.05 cr
A4NARs 2.56 crRs 2.31 cr
A5NARs 2.56 crRs 2.31 cr
B6NARs 2.56 crRs 2.31 cr
B7NARs 2.56 crRs 2.31 cr
B8NARs 2.56 crRs 2.31 cr
B9NARs 2.56 crRs 2.31 cr
B10NARs 2.56 crRs 2.31 cr
B11NARs 2.56 crRs 2.31 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHARESH BALMUKUND GANDHI
EngineerKISHORBHAI LALJIBHAI PATEL

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/VADODARA/VADODARA/Others/RAA04275/EX1/300621Applied Mar 2021; approved Jun 2021
PR/GJ/VADODARA/VADODARA/Others/RAA04275/EX2/100522Applied Mar 2022; approved May 2022
PR/GJ/VADODARA/VADODARA/Others/RAA04275/EX3/140525/311225Applied Jan 2025; approved May 2025

Documents filed52

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Vadodara Municipal Corporation/RAA04275/A1R/EX3/281125/311225 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)17 Nov 2025
Architect's certificate (Form 1)11 Jul 2025
Engineer's certificate (Form 2)11 Jul 2025
Engineer's certificate annexure11 Jul 2025
Site photograph, A310 Jul 2025
Site photograph, A410 Jul 2025
Site photograph, A510 Jul 2025
Site photograph, B610 Jul 2025
Site photograph, B710 Jul 2025
Site photograph, B810 Jul 2025
Site photograph, B910 Jul 2025
Site photograph, B1010 Jul 2025
Site photograph, B1110 Jul 2025
RERA registration certificate6 Dec 2018
Extension certificate-
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Drainage affidavit-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Approved building or plotting plan-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Proforma sale deed-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

92%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one moved by 59 months

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep RAJESHWAR GALAXY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Harni2,900+ in Vadodara

2 kmRAJESHWAR GALAXYOther 120Dot size: filed unitsN

Filed coordinates, straight-line distance. 120 registered projects within 2 km.

Builder: Propritorship of Shri Raj Associates

Propritorship of Shri Raj Associates has 1 registration on GujRERA, including RAJESHWAR GALAXY. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if RAJESHWAR GALAXY is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of RAJESHWAR GALAXY?

The registered promoter entity is Propritorship of Shri Raj Associates, an individual/propritorship as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in RAJESHWAR GALAXY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at RAJESHWAR GALAXY?

The professionals named in the filing: Architect: HARESH BALMUKUND GANDHI; Engineer: KISHORBHAI LALJIBHAI PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in RAJESHWAR GALAXY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About RAJESHWAR GALAXY. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save RAJESHWAR GALAXY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.