Home / Browse projects / Anand, Gujarat / RADHA BUNGALOWS

Valid until 17 Oct 2019 Residential/Group Housing project

RADHA BUNGALOWS

By ASHIRWAD PROCON PRIVATE LIMITED

RG-GJ-98350 · RERA PR/GJ/ANAND/ANAND/Others/RAA03272/270718 · Last updated on GujRERA portal: 17 Oct 2019

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
  • Separate project account declared
Oct 2019Possession promisedno revision filed
40 of 40Construction stages doneacross 5 buildings; every applicable stage filed complete
21 of 55Units unsoldnot recorded sold or booked
Jump to the 40 documents Report an error

RADHA BUNGALOWS is a Residential/Group Housing project by ASHIRWAD PROCON PRIVATE LIMITED in Anand, Gujarat, registered with GujRERA as PR/GJ/ANAND/ANAND/Others/RAA03272/270718 on 27 Jul 2018. Possession is promised by 17 Oct 2019. 34 of the 55 units on this registration are recorded sold or booked, and 40 of 40 construction stages are filed complete.

At a glance

Project

  • NameRADHA BUNGALOWS
  • TypeResidential/Group Housing
  • Location
    • B/H. SHASHWAT LANDMARK
    • OPP. GREEN VIEW APARTMENT KARAMSAD VIDHYANAGAR ROAD
    • Karamsad
    • Anand
    • 388325
  • Pincode388325
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/ANAND/ANAND/Others/RAA03272/270718
  • ReraGenie IDRG-GJ-98350

Builder

  • NameASHIRWAD PROCON PRIVATE LIMITED
  • Entity typeCOMPANY
  • Other registrations5 more →

Key dates

this monthRegisteredJul 2018PromisedOct 2019

Key facts

Registration and timeline

  • StatusValid until 17 Oct 2019
  • Registered on27 Jul 2018
  • Promised completion17 Oct 2019
  • Revised completionNone
  • Buildings5 building records
  • Documents filed40 files

Current status

62%34 of 55 units booked
100.0%Of the estimated cost spent so far

Figures as on 17 Oct 2019, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TYPE A---12012
TYPE B---13013
TYPE C---18018
TYPE D---11011
TYPE E---101

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building5

As on 17 Oct 2019, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

40 of 40 construction stages are filed complete across 5 buildings.

TYPE A100%
ActivityProgress
Excavation100%
Podiums (if any)100%
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
TYPE B100%
ActivityProgress
Excavation100%
Podiums (if any)100%
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
TYPE C100%
ActivityProgress
Excavation100%
Podiums (if any)100%
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
TYPE D100%
ActivityProgress
Excavation100%
Podiums (if any)100%
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
TYPE E100%
ActivityProgress
Excavation100%
Podiums (if any)100%
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable

Progress on shared amenities19

As on 17 Oct 2019, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingNoNot applicable
Drinking water facilitiesYes100%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area9,559 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 3.88 cr
Cost incurredRs 3.88 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
TYPE ANARs 77.61 lakhRs 77.61 lakh
TYPE BNARs 77.61 lakhRs 77.61 lakh
TYPE CNARs 77.61 lakhRs 77.61 lakh
TYPE DNARs 77.61 lakhRs 77.61 lakh
TYPE ENARs 77.61 lakhRs 77.61 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPRATYUSH ARCHITECTS
EngineerAKSHAR CONSULTANT

Documents filed40

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/ANAND/ANAND/Others/RAA03272/270718 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)17 Oct 2019
Architect's certificate (Form 1)15 Oct 2019
Engineer's certificate (Form 2)15 Oct 2019
Engineer's certificate annexure15 Oct 2019
Site photograph, TYPE A15 Oct 2019
Site photograph, TYPE B15 Oct 2019
Site photograph, TYPE C15 Oct 2019
Site photograph, TYPE D15 Oct 2019
Site photograph, TYPE E15 Oct 2019
RERA registration certificate27 Jul 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Anand

62%of this project is bookeddistrict median 57%
17%of Anand projects moved their completion datethis one has not

Computed across the 310+ Anand projects on ReraGenie, from their own filings.

Keep RADHA BUNGALOWS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Karamsad310+ in Anand

2 kmRADHA BUNGALOWSOther 119Dot size: filed unitsN

Filed coordinates, straight-line distance. 119 registered projects within 2 km.

Builder: ASHIRWAD PROCON PRIVATE LIMITED

ASHIRWAD PROCON PRIVATE LIMITED has 6 registrations on GujRERA, including RADHA BUNGALOWS and RADHA VRUND. Read the full track record. See more projects on the Anand district page.

Frequently asked questions

What are my rights if RADHA BUNGALOWS is delayed beyond 17 Oct 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of RADHA BUNGALOWS?

The registered promoter entity is ASHIRWAD PROCON PRIVATE LIMITED, a company as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in RADHA BUNGALOWS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at RADHA BUNGALOWS?

The professionals named in the filing: Architect: PRATYUSH ARCHITECTS; Engineer: AKSHAR CONSULTANT. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in RADHA BUNGALOWS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About RADHA BUNGALOWS. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save RADHA BUNGALOWS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.