Valid until 30 Sep 2026 Mixed Development project

PUSHKAR VALLEY

By SAI SHRADDHA BUILDCON

RG-GJ-45503 · RERA PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA09952/EX1/261125/300926 · Last updated on GujRERA portal: 20 Nov 2025

Source: official GujRERA filing

Red flags

  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • Nothing verified clear yet
Sep 2026Possession promisedmoved 9 months from the original
48 of 63Construction stages doneacross 7 buildings; furthest along: External plumbing and external plaster, 90%
208 of 394Units unsoldnot recorded sold or booked
Jump to the 48 documents Report an error

PUSHKAR VALLEY is a Mixed Development project by SAI SHRADDHA BUILDCON in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA09952/EX1/261125/300926 on 22 Mar 2022. Possession is promised by 30 Sep 2026. The completion date has moved by 9 months from the original filing. 186 of the 394 units on this registration are recorded sold or booked, and 48 of 63 construction stages are filed complete.

At a glance

Project

  • NamePUSHKAR VALLEY
  • TypeMixed Development
  • Location
    • PUSHKAR VALLEY
    • BESIDES. FORTUNE SKY
    • 100 FT BHAKTI CIRCLE ROAD
    • NIKOL
    • Ahmedabad City
    • Ahmedabad
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA09952/EX1/261125/300926
  • ReraGenie IDRG-GJ-45503

Builder

  • NameSAI SHRADDHA BUILDCON
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredMar 2022First promiseDec 2025Revised toSep 2026

Key facts

Registration and timeline

  • StatusValid until 30 Sep 2026
  • Registered on22 Mar 2022
  • Promised completion30 Sep 2026
  • Revised completionRevised to 30 Sep 2026 (originally 1 Dec 2025)
  • Buildings7 building records
  • Documents filed48 files

Current status

47%186 of 394 units booked
88.4%Of the estimated cost spent so far

Figures as on 20 Nov 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BLOCK G---40040
BLOCK H---40040
BLOCK I---40040
BLOCK A+B+C---11440154
BLOCK D---40040
BLOCK E---40040
BLOCK F---40040

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building7

As on 20 Nov 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

48 of 63 construction stages are filed complete across 7 buildings. The stage furthest along is External plumbing and external plaster, at 90%.

BLOCK G64%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats65%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks30%
External plumbing and external plaster, elevation, completion of terraces with waterproofing85%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
BLOCK H60%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats50%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks25%
External plumbing and external plaster, elevation, completion of terraces with waterproofing65%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
BLOCK I73%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats75%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks30%
External plumbing and external plaster, elevation, completion of terraces with waterproofing90%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing65%
BLOCK A+B+C100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK D100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK E100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK F100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 20 Nov 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes70%
Water supplyYes75%
Sewerage (chamber, lines, septic tank, STP)Yes90%
Storm water drainsYes60%
Landscaping and tree plantingYes50%
Street lightingYes75%
Community buildingsYes80%
Treatment and disposal of sewage and sullage waterYes90%
Solid waste management and disposalYes90%
Water conservation, rain water harvestingYes90%
Energy managementYes70%
Fire protection and fire safety requirementsYes75%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingYes75%
Drinking water facilitiesYes20%
Emergency evacuationYes85%
Use of renewable energyYes70%
SecurityYes70%
Letter boxYes75%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area11,836 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 84.11 cr
Cost incurredRs 74.34 cr
Spent of the estimate88.39%
BuildingWingEstimatedIncurred
BLOCK A+B+CNARs 41.28 crRs 41.28 cr
BLOCK INARs 8.97 crRs 5.83 cr
BLOCK HNARs 8.43 crRs 4.39 cr
BLOCK GNARs 6.44 crRs 3.87 cr
BLOCK DNARs 6.43 crRs 6.43 cr
BLOCK ENARs 6.43 crRs 6.43 cr
BLOCK FNARs 6.11 crRs 6.11 cr

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA09952/EX1/261125/300926Applied Oct 2025; approved Nov 2025

Documents filed48

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA09952/EX1/261125/300926 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)20 Nov 2025
Architect's certificate (Form 1)19 Nov 2025
Engineer's certificate (Form 2)19 Nov 2025
Engineer's certificate annexure19 Nov 2025
Site photograph, BLOCK G19 Nov 2025
Site photograph, BLOCK H19 Nov 2025
Site photograph, BLOCK I19 Nov 2025
Site photograph, BLOCK A+B+C19 Nov 2025
Site photograph, BLOCK D19 Nov 2025
Site photograph, BLOCK E19 Nov 2025
Site photograph, BLOCK F19 Nov 2025
RERA registration certificate22 Mar 2022
Extension certificate-
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

47%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one moved by 9 months

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep PUSHKAR VALLEY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Ahmedabad5,400+ in Ahmedabad

2 kmPUSHKAR VALLEYOther 317Dot size: filed unitsN

Filed coordinates, straight-line distance. 317 registered projects within 2 km.

Builder: SAI SHRADDHA BUILDCON

SAI SHRADDHA BUILDCON has 1 registration on GujRERA, including PUSHKAR VALLEY. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if PUSHKAR VALLEY is delayed beyond 30 Sep 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of PUSHKAR VALLEY?

The registered promoter entity is SAI SHRADDHA BUILDCON, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in PUSHKAR VALLEY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in PUSHKAR VALLEY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PUSHKAR VALLEY. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PUSHKAR VALLEY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.