ReraGenieLog inGet a buyer report

Home / Browse projects / Vadodara, Gujarat / PRIME PEARL

Valid until 31 Mar 2031 Residential/Group Housing project

PRIME PEARL

By PRIME CREATORS

RG-GJ-68062 · RERA PR/GJ/VADODARA/VADODARA/Vadodara Urban Development Authority/RAA17565/041126/310331 · Last updated on GujRERA portal: 4 Nov 2026

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Mar 2031Possession promisedno revision filed
40 of 360Construction stages doneacross 40 buildings; furthest along: Plinth, 50%
40 of 40Units unsoldnot recorded sold or booked
Jump to the 82 documents Report an error

PRIME PEARL is a Residential/Group Housing project by PRIME CREATORS in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Vadodara Urban Development Authority/RAA17565/041126/310331 on 4 Nov 2026. Possession is promised by 31 Mar 2031. 0 of the 40 units on this registration are recorded sold or booked, and 40 of 360 construction stages are filed complete.

At a glance

Project

  • NamePRIME PEARL
  • TypeResidential/Group Housing
  • Location
    • NR.GAYATRI MANDIR
    • AMODAR
    • WAGHODIA ROAD
    • AMODAR
    • Vadodara
    • 390019
  • Pincode390019
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Vadodara Urban Development Authority/RAA17565/041126/310331
  • ReraGenie IDRG-GJ-68062

Builder

  • NamePRIME CREATORS
  • Entity typePARTNERSHIP FIRM
  • Other registrations1 more →

Key dates

this monthRegisteredNov 2026PromisedMar 2031

Key facts

Registration and timeline

  • StatusValid until 31 Mar 2031
  • Registered on4 Nov 2026
  • Promised completion31 Mar 2031
  • Revised completionNone
  • Buildings40 building records
  • Documents filed82 files

Current status

0%0 of 40 units booked
5.2%Of the estimated cost spent so far

Figures as on 4 Nov 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TYPE-B6-12---101
TYPE-A6-13---101
TYPE-B7-14---101
TYPE-A7-15---101
TYPE-B8-16---101
TYPE-A8-17---101
TYPE-B9-18---101
TYPE-A9-19---101
TYPE-B10-20---101
TYPE-A10-21---101
TYPE-D1-22---101
TYPE-C1-23---101
TYPE-B11-24---101
TYPE-A11-25---101
TYPE-B12-26---101
TYPE-A12-27---101
TYPE-B13-28---101
TYPE-A13-29---101
TYPE-D2-30---101
TYPE-C2-31---101
TYPE-B14-32---101
TYPE-A14-33---101
TYPE-B15-34---101
TYPE-A15-35---101
TYPE-B16-36---101
TYPE-A16-37---101
TYPE-D3-38---101
TYPE-B1-2---101
TYPE-B17-40---101
TYPE-A1-3---101
TYPE-A17-41---101
TYPE-B2-4---101
TYPE-B18-42---101
TYPE-A2-5---101
TYPE-B3-6---101
TYPE-A3-7---101
TYPE-B4-8---101
TYPE-A4-9---101
TYPE-B5-10---101
TYPE-A5-11---101

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building20

As on 4 Nov 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 40 buildings; the table lists the first 20.

40 of 360 construction stages are filed complete across 40 buildings. The stage furthest along is Plinth, at 50%.

TYPE-B6-1217%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth50%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TYPE-A6-1317%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth50%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TYPE-B7-1417%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth50%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TYPE-A7-1517%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth50%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TYPE-B8-1617%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth50%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TYPE-A8-1717%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth50%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TYPE-B9-1817%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth50%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TYPE-A9-1917%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth50%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TYPE-B10-2017%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth50%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TYPE-A10-2117%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth50%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TYPE-D1-2217%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth50%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TYPE-C1-2317%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth50%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TYPE-B11-2417%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth50%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TYPE-A11-2517%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth50%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TYPE-B12-2617%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth50%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TYPE-A12-2717%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth50%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TYPE-B13-2817%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth50%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TYPE-A13-2917%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth50%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TYPE-D2-3017%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth50%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TYPE-C2-3117%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth50%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities19

As on 4 Nov 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsYes0%
Treatment and disposal of sewage and sullage waterYes0%
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingNoNot applicable
Drinking water facilitiesYes0%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes0%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,937 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 6.00 cr
Cost incurredRs 31.34 lakh
Spent of the estimate5.22%
BuildingWingEstimatedIncurred
TYPE-D1-22NARs 22.11 lakhRs 1.15 lakh
TYPE-C1-23NARs 22.11 lakhRs 1.15 lakh
TYPE-D2-30NARs 22.11 lakhRs 1.15 lakh
TYPE-C2-31NARs 22.11 lakhRs 1.15 lakh
TYPE-D3-38NARs 22.11 lakhRs 1.15 lakh
TYPE-B18-42NARs 17.81 lakhRs 93,038
TYPE-B17-40NARs 17.40 lakhRs 90,878
TYPE-A17-41NARs 17.40 lakhRs 90,878
TYPE-A8-17NARs 15.42 lakhRs 80,530
TYPE-B9-18NARs 14.34 lakhRs 74,928
TYPE-B15-34NARs 13.84 lakhRs 72,289
TYPE-A15-35NARs 13.84 lakhRs 72,289

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDhavalbhai Ashokbhai Rao
EngineerVINUBHAI RATILAL PATEL

Documents filed82

As listed on the registration, under the names the promoter filed them with; the newest 80 of 82 are shown. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Vadodara Urban Development Authority/RAA17565/041126/310331 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
RERA registration certificate4 Nov 2026
Architect's certificate (Form 1)24 Sep 2026
Engineer's certificate (Form 2)24 Sep 2026
Engineer's certificate annexure24 Sep 2026
Accountant's certificate (Form 3)24 Sep 2026
Site photograph, TYPE-B6-1223 Sep 2026
Site photograph, TYPE-A6-1323 Sep 2026
Site photograph, TYPE-B7-1423 Sep 2026
Site photograph, TYPE-A7-1523 Sep 2026
Site photograph, TYPE-B8-1623 Sep 2026
Site photograph, TYPE-A8-1723 Sep 2026
Site photograph, TYPE-B9-1823 Sep 2026
Site photograph, TYPE-A9-1923 Sep 2026
Site photograph, TYPE-B10-2023 Sep 2026
Site photograph, TYPE-A10-2123 Sep 2026
Site photograph, TYPE-D1-2223 Sep 2026
Site photograph, TYPE-C1-2323 Sep 2026
Site photograph, TYPE-B11-2423 Sep 2026
Site photograph, TYPE-A11-2523 Sep 2026
Site photograph, TYPE-B12-2623 Sep 2026
Site photograph, TYPE-A12-2723 Sep 2026
Site photograph, TYPE-B13-2823 Sep 2026
Site photograph, TYPE-A13-2923 Sep 2026
Site photograph, TYPE-D2-3023 Sep 2026
Site photograph, TYPE-C2-3123 Sep 2026
Site photograph, TYPE-B14-3223 Sep 2026
Site photograph, TYPE-A14-3323 Sep 2026
Site photograph, TYPE-B15-3423 Sep 2026
Site photograph, TYPE-A15-3523 Sep 2026
Site photograph, TYPE-B16-3623 Sep 2026
Site photograph, TYPE-A16-3723 Sep 2026
Site photograph, TYPE-D3-3823 Sep 2026
Site photograph, TYPE-B1-223 Sep 2026
Site photograph, TYPE-B17-4023 Sep 2026
Site photograph, TYPE-A1-323 Sep 2026
Site photograph, TYPE-A17-4123 Sep 2026
Site photograph, TYPE-B2-423 Sep 2026
Site photograph, TYPE-B18-4223 Sep 2026
Site photograph, TYPE-A2-523 Sep 2026
Site photograph, TYPE-B3-623 Sep 2026
Site photograph, TYPE-A3-723 Sep 2026
Site photograph, TYPE-B4-823 Sep 2026
Site photograph, TYPE-A4-923 Sep 2026
Site photograph, TYPE-B5-1023 Sep 2026
Site photograph, TYPE-A5-1123 Sep 2026
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Drainage affidavit-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Statutory document-
Project photograph-
Proforma sale deed-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-

How this compares with Vadodara

0%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one has not

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep PRIME PEARL on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near AMODAR2,900+ in Vadodara

2 kmPRIME PEARLOther 54Dot size: filed unitsN

Filed coordinates, straight-line distance. 54 registered projects within 2 km.

Builder: PRIME CREATORS

PRIME CREATORS has 2 registrations on GujRERA, including PRIME KUTIR and PRIME PEARL. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if PRIME PEARL is delayed beyond 31 Mar 2031?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of PRIME PEARL?

The registered promoter entity is PRIME CREATORS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in PRIME PEARL?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at PRIME PEARL?

The professionals named in the filing: Architect: Dhavalbhai Ashokbhai Rao; Engineer: VINUBHAI RATILAL PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PRIME PEARL?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PRIME PEARL. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PRIME PEARL to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.