Valid until 30 Apr 2027 Residential/Group Housing project

PRAMUKH DARSHAN

By SHREENATHJI BUILTINFRA LLP

RG-GJ-18559 · RERA PR/GJ/ANAND/ANAND/Anand VallabhVidhyanagar Karmsad Urban Development Authority/RAA14787/060225/311226 · Last updated on GujRERA portal: 24 Jul 2026

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Apr 2027Possession promisedno revision filed
20 of 36Construction stages doneacross 4 buildings; furthest along: Internal walls, 75%
3 of 12Units unsoldnot recorded sold or booked
Jump to the 43 documents Report an error

PRAMUKH DARSHAN is a Residential/Group Housing project by SHREENATHJI BUILTINFRA LLP in Anand, Gujarat, registered with GujRERA as PR/GJ/ANAND/ANAND/Anand VallabhVidhyanagar Karmsad Urban Development Authority/RAA14787/060225/311226 on 6 Feb 2025. Possession is promised by 30 Apr 2027. 9 of the 12 units on this registration are recorded sold or booked, and 20 of 36 construction stages are filed complete.

At a glance

Project

  • NamePRAMUKH DARSHAN
  • TypeResidential/Group Housing
  • Location
    • F.P. NO.-103-1
    • T.P. NO.1
    • KARAMSAD TALAV TO V. V. NAGAR ROAD
    • TP-1 KARAMSAD
    • ANAND-388325
    • KARAMSAD
    • Anand
    • 388325
  • Pincode388325
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/ANAND/ANAND/Anand VallabhVidhyanagar Karmsad Urban Development Authority/RAA14787/060225/311226
  • ReraGenie IDRG-GJ-18559

Builder

  • NameSHREENATHJI BUILTINFRA LLP
  • Entity typeLIMITED LIABILITY PARTNERSHIP FIRM

Key dates

this monthRegisteredFeb 2025PromisedApr 2027

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2027
  • Registered on6 Feb 2025
  • Promised completion30 Apr 2027
  • Revised completionNone
  • Buildings4 building records
  • Documents filed43 files

Current status

75%9 of 12 units booked
80.3%Of the estimated cost spent so far

Figures as on 24 Jul 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
D---404
A---202
C---202
B---404

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building4

As on 24 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

20 of 36 construction stages are filed complete across 4 buildings. The stage furthest along is Internal walls, at 75%.

D94%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing50%
A81%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats75%
Sanitary fittings within the flats75%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing50%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing50%
C69%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats70%
Sanitary fittings within the flats60%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing40%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
B76%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats70%
Sanitary fittings within the flats60%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing50%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing50%

Progress on shared amenities19

As on 24 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes75%
Water supplyYes50%
Sewerage (chamber, lines, septic tank, STP)Yes50%
Storm water drainsYes50%
Landscaping and tree plantingYes50%
Street lightingYes75%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes50%
Fire fightingNoNot applicable
Drinking water facilitiesYes50%
Emergency evacuationNoNot applicable
Use of renewable energyYes0%
SecurityYes0%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,894 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 2.75 cr
Cost incurredRs 2.21 cr
Spent of the estimate80.3%
BuildingWingEstimatedIncurred
BNARs 95.22 lakhRs 69.51 lakh
DNARs 95.22 lakhRs 90.45 lakh
ANARs 42.28 lakhRs 32.76 lakh
CNARs 42.28 lakhRs 28.11 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPriyanka Bhadreshkumar Gajjar
EngineerAHMEDHUSEIN YUSUFBHAI CHHIPA

Documents filed43

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/ANAND/ANAND/Anand VallabhVidhyanagar Karmsad Urban Development Authority/RAA14787/060225/311226 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)24 Jul 2026
Engineer's certificate (Form 2)24 Jul 2026
Engineer's certificate annexure24 Jul 2026
Accountant's certificate (Form 3)24 Jul 2026
Site photograph, D23 Jul 2026
Site photograph, D23 Jul 2026
Site photograph, D23 Jul 2026
Site photograph, D23 Jul 2026
Site photograph, A23 Jul 2026
Site photograph, A23 Jul 2026
Site photograph, C23 Jul 2026
Site photograph, C23 Jul 2026
Site photograph, B23 Jul 2026
Site photograph, B23 Jul 2026
Site photograph, B23 Jul 2026
Site photograph, B23 Jul 2026
RERA registration certificate6 Feb 2025
Proforma agreement for sale-
Auditor's report (3 of 3)-
Income tax return (3 of 3)-
Project specific document-
Drainage affidavit-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Statutory document-
Other document-
Project photograph-
Proforma sale deed-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (3 of 3)-

How this compares with Anand

75%of this project is bookeddistrict median 57%
17%of Anand projects moved their completion datethis one has not

Computed across the 310+ Anand projects on ReraGenie, from their own filings.

Keep PRAMUKH DARSHAN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near KARAMSAD310+ in Anand

2 kmPRAMUKH DARSHANOther 137Dot size: filed unitsN

Filed coordinates, straight-line distance. 137 registered projects within 2 km.

Builder: SHREENATHJI BUILTINFRA LLP

SHREENATHJI BUILTINFRA LLP has 1 registration on GujRERA, including PRAMUKH DARSHAN. Read the full track record. See more projects on the Anand district page.

Frequently asked questions

What are my rights if PRAMUKH DARSHAN is delayed beyond 30 Apr 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of PRAMUKH DARSHAN?

The registered promoter entity is SHREENATHJI BUILTINFRA LLP, a limited liability partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in PRAMUKH DARSHAN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at PRAMUKH DARSHAN?

The professionals named in the filing: Architect: Priyanka Bhadreshkumar Gajjar; Engineer: AHMEDHUSEIN YUSUFBHAI CHHIPA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PRAMUKH DARSHAN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PRAMUKH DARSHAN. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PRAMUKH DARSHAN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.