Home / Browse projects / Ahmedabad, Gujarat / PRAANGAN

Valid until 1 Jun 2027 Mixed Development project

PRAANGAN

By PRIME DEVELOPERS

RG-GJ-43010 · RERA PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA10774/141022 · Last updated on GujRERA portal: 29 Sep 2025

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Jun 2027Possession promisedno revision filed
14 of 27Construction stages doneacross 3 buildings; furthest along: External plumbing and external plaster, 95%
68 of 215Units unsoldnot recorded sold or booked
Jump to the 43 documents Report an error

PRAANGAN is a Mixed Development project by PRIME DEVELOPERS in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA10774/141022 on 14 Oct 2022. Possession is promised by 1 Jun 2027. 147 of the 215 units on this registration are recorded sold or booked, and 14 of 27 construction stages are filed complete.

At a glance

Project

  • NamePRAANGAN
  • TypeMixed Development
  • Location
    • FP NO-121/2
    • NR. APPLE GREEN BUNGLOWS
    • CHHARODI
    • TA-GHATLODIA
    • Ahmedabad City
    • Ahmedabad
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA10774/141022
  • ReraGenie IDRG-GJ-43010

Builder

  • NamePRIME DEVELOPERS
  • Entity typePARTNERSHIP FIRM
  • Other registrations4 more →

Key dates

this monthRegisteredOct 2022PromisedJun 2027

Key facts

Registration and timeline

  • StatusValid until 1 Jun 2027
  • Registered on14 Oct 2022
  • Promised completion1 Jun 2027
  • Revised completionNone
  • Buildings3 building records
  • Documents filed43 files

Current status

68%147 of 215 units booked
65.8%Of the estimated cost spent so far

Figures as on 29 Sep 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A+B---9623119
C---48048
D---48048

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building3

As on 29 Sep 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

14 of 27 construction stages are filed complete across 3 buildings. The stage furthest along is External plumbing and external plaster, at 95%.

A+B86%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats85%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing95%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%
C86%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats95%
Sanitary fittings within the flats85%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing95%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%
D94%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats75%
Sanitary fittings within the flats85%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing95%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%

Progress on shared amenities19

As on 29 Sep 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes80%
Water supplyYes80%
Sewerage (chamber, lines, septic tank, STP)Yes95%
Storm water drainsYes95%
Landscaping and tree plantingYes70%
Street lightingYes60%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes85%
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes75%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes40%
Fire fightingYes100%
Drinking water facilitiesNoNot applicable
Emergency evacuationYes0%
Use of renewable energyYes85%
SecurityYes40%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,948 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 47.90 cr
Cost incurredRs 31.50 cr
Spent of the estimate65.76%
BuildingWingEstimatedIncurred
A+BNARs 24.30 crRs 15.92 cr
CNARs 11.80 crRs 7.88 cr
DNARs 11.80 crRs 7.71 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRONAK M PATEL
EngineerJAYESH D DESAI

Documents filed43

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA10774/141022 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)29 Sep 2025
Architect's certificate (Form 1)23 Sep 2025
Site photograph, A+B23 Sep 2025
Site photograph, C23 Sep 2025
Site photograph, D23 Sep 2025
Engineer's certificate (Form 2)6 Oct 2024
Engineer's certificate annexure6 Oct 2024
RERA registration certificate14 Oct 2022
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

68%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one has not

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep PRAANGAN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Ahmedabad5,400+ in Ahmedabad

2 kmPRAANGANOther 122Dot size: filed unitsN

Filed coordinates, straight-line distance. 122 registered projects within 2 km.

Builder: PRIME DEVELOPERS

PRIME DEVELOPERS has 5 registrations on GujRERA, including PRIME PLAZA and PRIME NINE. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if PRAANGAN is delayed beyond 1 Jun 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of PRAANGAN?

The registered promoter entity is PRIME DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in PRAANGAN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at PRAANGAN?

The professionals named in the filing: Architect: RONAK M PATEL; Engineer: JAYESH D DESAI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PRAANGAN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PRAANGAN. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PRAANGAN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.