Home / Browse projects / Vadodara, Gujarat / PARKREST

Valid until 30 Oct 2027 Residential/Group Housing project

PARKREST

By SHASHWAT INFRASPACE

RG-GJ-27559 · RERA PR/GJ/VADODARA/VADODARA/Others/RAA01575/080218 · Last updated on GujRERA portal: 21 Apr 2026

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Oct 2027Possession promisedno revision filed
32 of 63Construction stages doneacross 7 buildings; furthest along: Installation of lifts, 95%
73 of 360Units unsoldnot recorded sold or booked
Jump to the 44 documents Report an error

PARKREST is a Residential/Group Housing project by SHASHWAT INFRASPACE in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/RAA01575/080218 on 8 Feb 2018. Possession is promised by 30 Oct 2027. 287 of the 360 units on this registration are recorded sold or booked, and 32 of 63 construction stages are filed complete.

At a glance

Project

  • NamePARKREST
  • TypeResidential/Group Housing
  • Location
    • PARKREST
    • OPP. TAKSH AURA
    • ADJOINING L&T KNOWLEDGE CITY
    • NR. ANKHOL VILLAGE
    • WAGHODIA ROAD
    • Ankhol
    • Vadodara
    • 390019
  • Pincode390019
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/RAA01575/080218
  • ReraGenie IDRG-GJ-27559

Builder

  • NameSHASHWAT INFRASPACE
  • Entity typePARTNERSHIP FIRM
  • Other registrations2 more →

Key dates

this monthRegisteredFeb 2018PromisedOct 2027

Key facts

Registration and timeline

  • StatusValid until 30 Oct 2027
  • Registered on8 Feb 2018
  • Promised completion30 Oct 2027
  • Revised completionNone
  • Buildings7 building records
  • Documents filed44 files

Current status

80%287 of 360 units booked
88.8%Of the estimated cost spent so far

Figures as on 21 Apr 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
C---1200120
D---101
E---101
E1---101
F---202
A---1020102
B---1330133

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building7

As on 21 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

32 of 63 construction stages are filed complete across 7 buildings. The stage furthest along is Installation of lifts, at 95%.

C72%
ActivityProgress
Excavation90%
Podiums (if any)Not applicable
Plinth90%
Stilt Floor0%
Slabs of Super Structure88%
Internal walls, internal plaster, floorings, doors and windows within flats81%
Sanitary fittings within the flats60%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing85%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing70%
D97%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing80%
E97%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing85%
E199%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%
F99%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%
A89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor80%
Slabs of Super Structure88%
Internal walls, internal plaster, floorings, doors and windows within flats91%
Sanitary fittings within the flats90%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing85%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing80%
B63%
ActivityProgress
Excavation84%
Podiums (if any)Not applicable
Plinth80%
Stilt Floor0%
Slabs of Super Structure65%
Internal walls, internal plaster, floorings, doors and windows within flats65%
Sanitary fittings within the flats75%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing70%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing60%

Progress on shared amenities19

As on 21 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsYes25%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes0%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area50,989 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 64.50 cr
Cost incurredRs 57.25 cr
Spent of the estimate88.76%
BuildingWingEstimatedIncurred
BNARs 25.27 crRs 21.02 cr
CNARs 24.00 crRs 21.52 cr
ANARs 14.28 crRs 13.78 cr
FNARs 39.50 lakhRs 39.00 lakh
ENARs 18.75 lakhRs 18.00 lakh
E1NARs 18.75 lakhRs 18.50 lakh
DNARs 18.00 lakhRs 17.00 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKEKASHREE SUKESHKUMAR PATEL
EngineerNITIN SIDHPURA & ASSOCIATES

Documents filed44

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/RAA01575/080218 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)21 Apr 2026
Engineer's certificate (Form 2)21 Apr 2026
Engineer's certificate annexure21 Apr 2026
Accountant's certificate (Form 3)21 Apr 2026
Site photograph, C19 Apr 2026
Site photograph, D19 Apr 2026
Site photograph, E19 Apr 2026
Site photograph, E119 Apr 2026
Site photograph, F19 Apr 2026
Site photograph, A19 Apr 2026
Site photograph, B19 Apr 2026
RERA registration certificate8 Feb 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

80%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one has not

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep PARKREST on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Ankhol2,900+ in Vadodara

2 kmPARKRESTOther 152Dot size: filed unitsN

Filed coordinates, straight-line distance. 152 registered projects within 2 km.

Builder: SHASHWAT INFRASPACE

SHASHWAT INFRASPACE has 3 registrations on GujRERA, including PARKSHIRE and PARKREST. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if PARKREST is delayed beyond 30 Oct 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of PARKREST?

The registered promoter entity is SHASHWAT INFRASPACE, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in PARKREST?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at PARKREST?

The professionals named in the filing: Architect: KEKASHREE SUKESHKUMAR PATEL; Engineer: NITIN SIDHPURA & ASSOCIATES. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PARKREST?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PARKREST. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PARKREST to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.