Home / Browse projects / Vadodara, Gujarat / PARK WOODS

Valid until 30 Apr 2026 Residential/Group Housing project

PARK WOODS

By SHREE SAI DEVELOPERS

RG-GJ-96630 · RERA PR/GJ/VADODARA/VADODARA/Others/RAA02748/EX2/160922 · Last updated on GujRERA portal: 7 Jun 2023

Source: official GujRERA filing

Red flags

  • Completion date moved by 58 months
  • 3 extensions taken

Clear

  • Nothing verified clear yet
Apr 2026Possession promisedmoved 58 months from the original
57 of 72Construction stages doneacross 9 buildings; furthest along: Internal walls, 60%
78 of 216Units unsoldnot recorded sold or booked
Jump to the 45 documents Report an error

PARK WOODS is a Residential/Group Housing project by SHREE SAI DEVELOPERS in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/RAA02748/EX2/160922 on 30 May 2018. Possession is promised by 30 Apr 2026. The completion date has moved by 58 months from the original filing. 138 of the 216 units on this registration are recorded sold or booked, and 57 of 72 construction stages are filed complete.

At a glance

Project

  • NamePARK WOODS
  • TypeResidential/Group Housing
  • Location
    • F1 JALANAND TOWNSHIP
    • GORWA REFINERY ROAD
    • Gorwa
    • Vadodara
    • 391310
  • Pincode391310
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/RAA02748/EX2/160922
  • ReraGenie IDRG-GJ-96630

Builder

  • NameSHREE SAI DEVELOPERS
  • Entity typePARTNERSHIP FIRM
  • Other registrations9 more →

Key dates

this monthRegisteredMay 2018First promiseJun 2021Revised toApr 2026

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2026
  • Registered on30 May 2018
  • Promised completion30 Apr 2026
  • Revised completionRevised to 30 Apr 2026 (originally 30 Jun 2021)
  • Buildings9 building records
  • Documents filed45 files

Current status

64%138 of 216 units booked
90.3%Of the estimated cost spent so far

Figures as on 7 Jun 2023, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower J---20020
Tower K---20020
Tower L---40040
Tower A---36036
Tower E---20020
Tower F---20020
Tower G---20020
Tower H---20020
Tower I---20020

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building9

As on 7 Jun 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

57 of 72 construction stages are filed complete across 9 buildings. The stage furthest along is Internal walls, at 60%.

Tower J45%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats60%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
Tower K42%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats40%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
Tower L100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Tower A100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Tower E100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Tower F100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Tower G100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Tower H100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Tower I45%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats60%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities19

As on 7 Jun 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes75%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes90%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area14,468 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 16.82 cr
Cost incurredRs 15.18 cr
Spent of the estimate90.27%
BuildingWingEstimatedIncurred
Tower ANARs 1.87 crRs 1.69 cr
Tower ENARs 1.87 crRs 1.69 cr
Tower FNARs 1.87 crRs 1.69 cr
Tower GNARs 1.87 crRs 1.69 cr
Tower HNARs 1.87 crRs 1.69 cr
Tower INARs 1.87 crRs 1.69 cr
Tower JNARs 1.87 crRs 1.69 cr
Tower KNARs 1.87 crRs 1.69 cr
Tower LNARs 1.87 crRs 1.69 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectCHIRAG PATEL
EngineerP M PATEL AND CO

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/VADODARA/VADODARA/Others/RAA02748/EX1/021121Applied Jul 2021; approved Nov 2021
PR/GJ/VADODARA/VADODARA/Others/RAA02748/EX2/160922Applied Sep 2022; approved Sep 2022
ExtensionApplied May 2023; no approval date filed

Documents filed45

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/RAA02748/EX2/160922 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)7 Jun 2023
Engineer's certificate (Form 2)7 Jun 2023
Engineer's certificate annexure7 Jun 2023
Accountant's certificate (Form 3)7 Jun 2023
Site photograph, Tower J7 Jun 2023
Site photograph, Tower K7 Jun 2023
Site photograph, Tower L7 Jun 2023
Site photograph, Tower A7 Jun 2023
Site photograph, Tower E7 Jun 2023
Site photograph, Tower F7 Jun 2023
Site photograph, Tower G7 Jun 2023
Site photograph, Tower H7 Jun 2023
Site photograph, Tower I7 Jun 2023
RERA registration certificate30 May 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

64%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one moved by 58 months

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep PARK WOODS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Gorwa2,900+ in Vadodara

2 kmPARK WOODSOther 122Dot size: filed unitsN

Filed coordinates, straight-line distance. 122 registered projects within 2 km.

Builder: SHREE SAI DEVELOPERS

SHREE SAI DEVELOPERS has 10 registrations on GujRERA, including PARK WOODS and VASTU 20. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if PARK WOODS is delayed beyond 30 Apr 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of PARK WOODS?

The registered promoter entity is SHREE SAI DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in PARK WOODS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at PARK WOODS?

The professionals named in the filing: Architect: CHIRAG PATEL; Engineer: P M PATEL AND CO. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PARK WOODS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PARK WOODS. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PARK WOODS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.