Valid until 30 Nov 2019 Mixed Development project

Palmera

By Shree Jala Enterprise

RG-GJ-00483 · RERA PR/GJ/VADODARA/VADODARA/Others/MAA04079/EX1/140219 · Last updated on GujRERA portal: 5 Nov 2019

Source: official GujRERA filing

Red flags

  • Completion date moved by 11 months
  • 1 extension taken

Clear

  • Separate project account declared
Nov 2019Possession promisedmoved 11 months from the original
34 of 34Construction stages doneacross 4 buildings; every applicable stage filed complete
26 of 222Units unsoldnot recorded sold or booked
Jump to the 41 documents Report an error

Palmera is a Mixed Development project by Shree Jala Enterprise in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/MAA04079/EX1/140219 on 20 Nov 2018. Possession is promised by 30 Nov 2019. The completion date has moved by 11 months from the original filing. 196 of the 222 units on this registration are recorded sold or booked, and 34 of 34 construction stages are filed complete.

At a glance

Project

  • NamePalmera
  • TypeMixed Development
  • Location
    • Nr. Royal Green
    • B/H
    • Bill bong high school
    • Vadsar
    • Vadodara
    • 390012
  • Pincode390012
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/MAA04079/EX1/140219
  • ReraGenie IDRG-GJ-00483

Builder

  • NameShree Jala Enterprise
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredNov 2018First promiseDec 2018Revised toNov 2019

Key facts

Registration and timeline

  • StatusValid until 30 Nov 2019
  • Registered on20 Nov 2018
  • Promised completion30 Nov 2019
  • Revised completionRevised to 30 Nov 2019 (originally 31 Dec 2018)
  • Buildings4 building records
  • Documents filed41 files

Current status

88%196 of 222 units booked
92.1%Of the estimated cost spent so far

Figures as on 5 Nov 2019, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---8836124
B---28028
C---37037
D---33033

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building4

As on 5 Nov 2019, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

34 of 34 construction stages are filed complete across 4 buildings.

A100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
C100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
D100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 5 Nov 2019, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingYes100%
Drinking water facilitiesYes100%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,891 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 21.32 cr
Cost incurredRs 19.64 cr
Spent of the estimate92.13%
BuildingWingEstimatedIncurred
ANARs 5.33 crRs 4.91 cr
BNARs 5.33 crRs 4.91 cr
CNARs 5.33 crRs 4.91 cr
DNARs 5.33 crRs 4.91 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRuchir Seth
EngineerAashutosh Desai

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/VADODARA/VADODARA/Others/MAA04079/EX1/140219Applied Dec 2018; approved Feb 2019

Documents filed41

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/MAA04079/EX1/140219 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)5 Nov 2019
Engineer's certificate (Form 2)5 Nov 2019
Engineer's certificate annexure5 Nov 2019
Accountant's certificate (Form 3)5 Nov 2019
Site photograph, A5 Nov 2019
Site photograph, B5 Nov 2019
Site photograph, C5 Nov 2019
Site photograph, D5 Nov 2019
RERA registration certificate20 Nov 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

88%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one moved by 11 months

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep Palmera on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Vadodara2,900+ in Vadodara

2 kmPalmeraOther 148Dot size: filed unitsN

Filed coordinates, straight-line distance. 148 registered projects within 2 km.

Builder: Shree Jala Enterprise

Shree Jala Enterprise has 1 registration on GujRERA, including Palmera. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if Palmera is delayed beyond 30 Nov 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Palmera?

The registered promoter entity is Shree Jala Enterprise, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Palmera?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Palmera?

The professionals named in the filing: Architect: Ruchir Seth; Engineer: Aashutosh Desai. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Palmera?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Palmera. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Palmera to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.