Home / Browse projects / Vadodara, Gujarat / ORCHID LUXURIA
ORCHID LUXURIA
By UNITY INFRA
RG-GJ-15482 · RERA PR/GJ/VADODARA/VADODARA/Vadodara Municipal Corporation/RN59AA09959/EX1/070326/311226 · Last updated on GujRERA portal: 25 Feb 2026
Source: official GujRERA filing
Red flags
- Completion date moved by 12 months
- 1 extension taken
Clear
- Nothing verified clear yet
Saved.
ORCHID LUXURIA is a Residential/Group Housing project by UNITY INFRA in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Vadodara Municipal Corporation/RN59AA09959/EX1/070326/311226 on 6 Jun 2022. Possession is promised by 31 Dec 2026. The completion date has moved by 12 months from the original filing. 62 of the 98 units on this registration are recorded sold or booked, and 14 of 18 construction stages are filed complete.
At a glance
Project
- NameORCHID LUXURIA
- TypeResidential/Group Housing
- Location
- NEAR RAAMA SKYZ
- BEHIND PLAZZO RESTAURANT
- SAMA-SAVLI ROAD
- VEMALI
- Vadodara
- 390024
- Pincode390024
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR/GJ/VADODARA/VADODARA/Vadodara Municipal Corporation/RN59AA09959/EX1/070326/311226
- ReraGenie IDRG-GJ-15482
Builder
- NameUNITY INFRA
- Entity typePARTNERSHIP FIRM
- Other registrations5 more →
Key dates
Key facts
Registration and timeline
- StatusValid until 31 Dec 2026
- Registered on6 Jun 2022
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2025)
- Buildings2 building records
- Documents filed26 files
Current status
Figures as on 25 Feb 2026, this project's latest GujRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| TOWER-A | - | - | - | 42 | 0 | 42 |
| TOWER-B | - | - | - | 56 | 0 | 56 |
The full filing
Everything below is from the project's own GujRERA filing, free to read.
Construction progress by building2
As on 25 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
14 of 18 construction stages are filed complete across 2 buildings. The stage furthest along is Sanitary fittings within the flats, at 70%.
TOWER-A82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 20% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 20% |
TOWER-B90%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 70% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 40% |
Progress on shared amenities19
As on 25 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal roads and footpaths | Yes | 40% |
| Water supply | Yes | 50% |
| Sewerage (chamber, lines, septic tank, STP) | No | Not applicable |
| Storm water drains | No | Not applicable |
| Landscaping and tree planting | Yes | 0% |
| Street lighting | Yes | 0% |
| Community buildings | Yes | 0% |
| Treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Water conservation, rain water harvesting | Yes | 0% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Fire fighting | Yes | 50% |
| Drinking water facilities | No | Not applicable |
| Emergency evacuation | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Security | Yes | 0% |
| Letter box | Yes | 0% |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| TOWER-B | NA | Rs 18.90 cr | Rs 12.33 cr |
| TOWER-A | NA | Rs 14.18 cr | Rs 8.22 cr |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Kirankumar Rasikbhai Ramjiyani |
| Engineer | AASHUTOSH ANILCHANDRA DESAI |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Documents filed26
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Vadodara Municipal Corporation/RN59AA09959/EX1/070326/311226 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Accountant's certificate (Form 3) | 25 Feb 2026 |
| Architect's certificate (Form 1) | 11 Feb 2026 |
| Engineer's certificate (Form 2) | 11 Feb 2026 |
| Engineer's certificate annexure | 11 Feb 2026 |
| Site photograph, TOWER-A | 11 Feb 2026 |
| Site photograph, TOWER-B | 11 Feb 2026 |
| RERA registration certificate | 6 Jun 2022 |
| Extension certificate | - |
| Proforma agreement for sale | - |
| Project specific document | - |
| Approved sanctioned plan | - |
| Approved layout plan | - |
| Land location | - |
| Encumbrance certificate | - |
| Area development document | - |
| Proforma allotment letter | - |
| Brochure | - |
| Declaration in Form B | - |
| Approved building or plotting plan | - |
| NOCs from authorities | - |
| Title clearance certificate | - |
| Title report | - |
| Property card 2 | - |
| Property card | - |
| Project photograph | - |
| Proforma sale deed | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Vadodara
Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.
Keep ORCHID LUXURIA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near VEMALI2,900+ in Vadodara
Filed coordinates, straight-line distance. 162 registered projects within 2 km.
JV TRANSLIFE
KATIRA CONSTRUCTION LIMITED
VEDA II
ALEMBIC LIMITED
FORTUNE GATEWAY
FORTUNE INFRA
AASHRAY RESIDENCY
SHIV BUILDCON
KRISHNA PRIME
SATYAM OPULENT
SIDDHARTH CREST
Shree B R Patel Developers
See every Vadodara project, with the district possession charts
Builder: UNITY INFRA
UNITY INFRA has 6 registrations on GujRERA, including SHANTAM SKYLINE and ORCHID LUXURIA. Read the full track record. See more projects on the Vadodara district page.
Frequently asked questions
What are my rights if ORCHID LUXURIA is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.
How do I verify and contact the developer of ORCHID LUXURIA?
The registered promoter entity is UNITY INFRA, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.
Is my payment protected in ORCHID LUXURIA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at ORCHID LUXURIA?
The professionals named in the filing: Architect: Kirankumar Rasikbhai Ramjiyani; Engineer: AASHUTOSH ANILCHANDRA DESAI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ORCHID LUXURIA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.
Report an error Share feedback