Home / Browse projects / Ahmedabad, Gujarat / OMKAR HERITAGE

Valid until 31 Mar 2027 Residential/Group Housing project

OMKAR HERITAGE

By MAHAVIR CORPORATION

RG-GJ-87852 · RERA PR/GJ/AHMEDABAD/DASKROI/AUDA/RAA09125/EX1/EX2/210926/310327 · Last updated on GujRERA portal: 31 Aug 2026

Source: official GujRERA filing

Red flags

  • Completion date moved by 34 months
  • 2 extensions taken

Clear

  • Nothing verified clear yet
Mar 2027Possession promisedmoved 34 months from the original
96 of 108Construction stages doneacross 12 buildings; furthest along: Plinth, 0%
0 of 22Units unsoldnot recorded sold or booked
Jump to the 40 documents Report an error

OMKAR HERITAGE is a Residential/Group Housing project by MAHAVIR CORPORATION in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/DASKROI/AUDA/RAA09125/EX1/EX2/210926/310327 on 1 Oct 2021. Possession is promised by 31 Mar 2027. The completion date has moved by 34 months from the original filing. 22 of the 22 units on this registration are recorded sold or booked, and 96 of 108 construction stages are filed complete.

At a glance

Project

  • NameOMKAR HERITAGE
  • TypeResidential/Group Housing
  • Location
    • Omkar Haritage
    • Near Omkar Residency
    • B/h
    • Panchvati Party Plot
    • Bareja
    • Daskroi
    • Ahmedabad
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/DASKROI/AUDA/RAA09125/EX1/EX2/210926/310327
  • ReraGenie IDRG-GJ-87852

Builder

  • NameMAHAVIR CORPORATION
  • Entity typePARTNERSHIP FIRM
  • Other registrations4 more →

Key dates

this monthRegisteredOct 2021First promiseMay 2024Revised toMar 2027

Key facts

Registration and timeline

  • StatusValid until 31 Mar 2027
  • Registered on1 Oct 2021
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 1 May 2024)
  • Buildings12 building records
  • Documents filed40 files

Current status

100%22 of 22 units booked
100.0%Of the estimated cost spent so far

Figures as on 31 Aug 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
1 TENA---101
2 TENA---303
3 TENA---202
7 TENA---101
8 TENA---101
9 TENA---303
10 TENA---202
14 TENA---101
15 TENA---101
16 TENA---303
17 TENA---303
22 TENA---101

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building12

As on 31 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

96 of 108 construction stages are filed complete across 12 buildings. The stage furthest along is Plinth, at 0%.

1 TENA89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
2 TENA89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
3 TENA89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
7 TENA89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
8 TENA89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
9 TENA89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
10 TENA89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
14 TENA89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
15 TENA89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
16 TENA89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
17 TENA89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
22 TENA89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 31 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesYes100%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,667 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 3.00 cr
Cost incurredRs 3.00 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
9 TENANARs 42.33 lakhRs 42.33 lakh
16 TENANARs 40.86 lakhRs 40.86 lakh
17 TENANARs 40.86 lakhRs 40.86 lakh
2 TENANARs 39.47 lakhRs 39.47 lakh
10 TENANARs 28.22 lakhRs 28.22 lakh
3 TENANARs 26.30 lakhRs 26.30 lakh
8 TENANARs 14.18 lakhRs 14.18 lakh
14 TENANARs 14.11 lakhRs 14.11 lakh
15 TENANARs 13.67 lakhRs 13.67 lakh
22 TENANARs 13.65 lakhRs 13.65 lakh
7 TENANARs 13.19 lakhRs 13.19 lakh
1 TENANARs 13.16 lakhRs 13.16 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVIRAL BHAYCHANDBHAI PATEL
EngineerVIRAN D PARIKH

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/AHMEDABAD/DASKROI/AUDA/RAA09125/EX1/060724/300425Applied Apr 2024; approved Jul 2024
PR/GJ/AHMEDABAD/DASKROI/AUDA/RAA09125/EX1/EX2/210926/310327Applied Apr 2025; approved Sep 2026

Documents filed40

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/DASKROI/AUDA/RAA09125/EX1/EX2/210926/310327 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)31 Aug 2026
Engineer's certificate (Form 2)31 Aug 2026
Engineer's certificate annexure31 Aug 2026
Accountant's certificate (Form 3)31 Aug 2026
RERA registration certificate1 Oct 2021
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

100%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one moved by 34 months

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep OMKAR HERITAGE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Ahmedabad5,400+ in Ahmedabad

2 kmOMKAR HERITAGEOther 22Dot size: filed unitsN

Filed coordinates, straight-line distance. 22 registered projects within 2 km.

Builder: MAHAVIR CORPORATION

MAHAVIR CORPORATION has 5 registrations on GujRERA, including CORNER POINT and OMKAR RESIDENCY. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if OMKAR HERITAGE is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of OMKAR HERITAGE?

The registered promoter entity is MAHAVIR CORPORATION, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in OMKAR HERITAGE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at OMKAR HERITAGE?

The professionals named in the filing: Architect: VIRAL BHAYCHANDBHAI PATEL; Engineer: VIRAN D PARIKH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in OMKAR HERITAGE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About OMKAR HERITAGE. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save OMKAR HERITAGE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.