Home / Browse projects / Ahmedabad, Gujarat / NORTH PARK (Phase-2 and 3)

Valid until 30 Jun 2027 Residential/Group Housing project

NORTH PARK (Phase-2 and 3)

By ADANI ESTATE MANAGEMENT PRIVATE LIMITED

RG-GJ-59078 · RERA PR/GJ/GANDHINAGAR/GANDHINAGAR/Ahmedabad Urban Development Authority/RAA01824/A1R/EX1/240726/300627 · Last updated on GujRERA portal: 6 Aug 2026

Source: official GujRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Nothing verified clear yet
Jun 2027Possession promisedmoved 12 months from the original
3 of 9Construction stages donefurthest along: Staircases, 99%
0 of 42Units unsoldnot recorded sold or booked
Jump to the 46 documents Report an error

NORTH PARK (Phase-2 and 3) is a Residential/Group Housing project by ADANI ESTATE MANAGEMENT PRIVATE LIMITED in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/GANDHINAGAR/Ahmedabad Urban Development Authority/RAA01824/A1R/EX1/240726/300627 on 1 Mar 2018. Possession is promised by 30 Jun 2027. The completion date has moved by 12 months from the original filing. 42 of the 42 units on this registration are recorded sold or booked, and 3 of 9 construction stages are filed complete.

At a glance

Project

  • NameNORTH PARK (Phase-2 and 3)
  • TypeResidential/Group Housing
  • Location
    • Shantigram
    • Nr.Vaishnodevi Circle
    • S.G.Highway
    • Dantali
    • Ahmedabad City
    • Ahmedabad
    • 382423
  • Pincode382423
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/GANDHINAGAR/Ahmedabad Urban Development Authority/RAA01824/A1R/EX1/240726/300627
  • ReraGenie IDRG-GJ-59078

Builder

  • NameADANI ESTATE MANAGEMENT PRIVATE LIMITED
  • Entity typeCOMPANY
  • Other registrations18 more →

Key dates

this monthRegisteredMar 2018First promiseJun 2026Revised toJun 2027

Key facts

Registration and timeline

  • StatusValid until 30 Jun 2027
  • Registered on1 Mar 2018
  • Promised completion30 Jun 2027
  • Revised completionRevised to 30 Jun 2027 (originally 30 Jun 2026)
  • Buildings1 building record
  • Documents filed46 files

Current status

100%42 of 42 units booked
98.7%Of the estimated cost spent so far

Figures as on 6 Aug 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
RESI(A-12,B-14,C-16)units---42042

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 6 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 9 construction stages are filed complete. The stage furthest along is Staircases, at 99%.

RESI(A-12,B-14,C-16)units: 88% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats98%
Sanitary fittings within the flats98%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks99%
External plumbing and external plaster, elevation, completion of terraces with waterproofing99%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing98%

Progress on shared amenities19

As on 6 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalYes100%
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesYes100%
Emergency evacuationNoNot applicable
Use of renewable energyYes95%
SecurityYes100%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area174,439 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 51.38 cr
Cost incurredRs 50.73 cr
Spent of the estimate98.74%
BuildingWingEstimatedIncurred
RESI(A-12,B-14,C-16)unitsNARs 51.38 crRs 50.73 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectUrvashi Lalitkumar Tuli
EngineerHARESH AMRUTLAL SHAH

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/GANDHINAGAR/GANDHINAGAR/Ahmedabad Urban Development Authority/RAA01824/A1R/EX1/240726/300627Applied May 2026; approved Jul 2026

Documents filed46

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/GANDHINAGAR/Ahmedabad Urban Development Authority/RAA01824/A1R/EX1/240726/300627 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)6 Aug 2026
Architect's certificate (Form 1)5 Aug 2026
Engineer's certificate (Form 2)5 Aug 2026
Engineer's certificate annexure5 Aug 2026
Site photograph, RESI(A-12,B-14,C-16)units22 Jun 2026
Site photograph, RESI(A-12,B-14,C-16)units22 Jun 2026
RERA registration certificate1 Mar 2018
Extension certificate-
Alteration certificate-
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Drainage affidavit-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Approved building or plotting plan-
Title clearance certificate-
Title report-
Property card-
Proforma sale deed-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

100%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one moved by 12 months

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep NORTH PARK (Phase-2 and 3) on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dantali5,400+ in Ahmedabad

2 kmNORTH PARK (Phase-2 and Other 29Dot size: filed unitsN

Filed coordinates, straight-line distance. 29 registered projects within 2 km.

Builder: ADANI ESTATE MANAGEMENT PRIVATE LIMITED

ADANI ESTATE MANAGEMENT PRIVATE LIMITED has 19 registrations on GujRERA, including NORTH PARK (Phase-2 and 3) and NORTH PARK (Phase-6). Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if NORTH PARK (Phase-2 and 3) is delayed beyond 30 Jun 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of NORTH PARK (Phase-2 and 3)?

The registered promoter entity is ADANI ESTATE MANAGEMENT PRIVATE LIMITED, a company as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in NORTH PARK (Phase-2 and 3)?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at NORTH PARK (Phase-2 and 3)?

The professionals named in the filing: Architect: Urvashi Lalitkumar Tuli; Engineer: HARESH AMRUTLAL SHAH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NORTH PARK (Phase-2 and 3)?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NORTH PARK (Phase-2 and 3). Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NORTH PARK (Phase-2 and 3) to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.