ReraGenieLog inGet a buyer report

Home / Browse projects / Ahmedabad, Gujarat / Water Lily Ph-4 (Towers - C5,C6,C11,C12)

Valid until 30 Jun 2018 Residential/Group Housing project

Water Lily Ph-4 (Towers - C5,C6,C11,C12)

By Adani Township and Real Estate Company Private Limited

RG-GJ-62965 · RERA PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA01511/030218 · Last updated on GujRERA portal: 29 Jun 2018

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
  • Separate project account declared
Jun 2018Possession promisedno revision filed
34 of 36Construction stages doneacross 4 buildings; furthest along: Stilt Floor, 1%
Jump to the 39 documents Report an error

Water Lily Ph-4 (Towers - C5,C6,C11,C12) is a Residential/Group Housing project by Adani Township and Real Estate Company Private Limited in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA01511/030218 on 3 Feb 2018. Possession is promised by 30 Jun 2018.

At a glance

Project

  • NameWater Lily Ph-4 (Towers - C5,C6,C11,C12)
  • TypeResidential/Group Housing
  • Location
    • Shantigram
    • Nr.Vaishnodevi Circle
    • S.G.Highway
    • Khoraj-Khodiyar-Jaspur-Dantali
    • Ahmedabad City
    • Ahmedabad
    • 382423
  • Pincode382423
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA01511/030218
  • ReraGenie IDRG-GJ-62965

Builder

  • NameAdani Township and Real Estate Company Private Limited
  • Entity typeCOMPANY
  • Other registrations11 more →

Key dates

this monthRegisteredFeb 2018PromisedJun 2018

Key facts

Registration and timeline

  • StatusValid until 30 Jun 2018
  • Registered on3 Feb 2018
  • Promised completion30 Jun 2018
  • Revised completionNone
  • Buildings4 building records
  • Documents filed39 files

Current status

100.0%Of the estimated cost spent so far

Figures as on 29 Jun 2018, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
B5-----2
B6-----1
B3-----2
B4-----2

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building4

As on 29 Jun 2018, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

34 of 36 construction stages are filed complete across 4 buildings. The stage furthest along is Stilt Floor, at 1%.

B5100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B689%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor1%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B389%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor1%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B4100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 29 Jun 2018, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalYes100%
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingYes100%
Drinking water facilitiesYes100%
Emergency evacuationYes100%
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area21,473 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 115.85 cr
Cost incurredRs 115.85 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
B5NARs 28.96 crRs 28.96 cr
B6NARs 28.96 crRs 28.96 cr
B3NARs 28.96 crRs 28.96 cr
B4NARs 28.96 crRs 28.96 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMr Rupesh M Bhatt
EngineerJapan B Shah

Documents filed39

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA01511/030218 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)29 Jun 2018
Engineer's certificate (Form 2)29 Jun 2018
Site photograph, B529 Jun 2018
Site photograph, B629 Jun 2018
Site photograph, B329 Jun 2018
Site photograph, B429 Jun 2018
RERA registration certificate3 Feb 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

14%of Ahmedabad projects moved their completion datethis one has not

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep Water Lily Ph-4 (Towers - C5,C6,C11,C12) on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Khoraj-Khodiyar-Jaspur-Dantali,5,400+ in Ahmedabad

2 kmWater Lily Ph-4 (Towers Other 31Dot size: filed unitsN

Filed coordinates, straight-line distance. 31 registered projects within 2 km.

Builder: Adani Township and Real Estate Company Private Limited

Adani Township and Real Estate Company Private Limited has 12 registrations on GujRERA, including Elysium (Phase-I) and La-marina (Tower-B1, B7, B8). Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if Water Lily Ph-4 (Towers - C5,C6,C11,C12) is delayed beyond 30 Jun 2018?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Water Lily Ph-4 (Towers - C5,C6,C11,C12)?

The registered promoter entity is Adani Township and Real Estate Company Private Limited, a company as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Water Lily Ph-4 (Towers - C5,C6,C11,C12)?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Water Lily Ph-4 (Towers - C5,C6,C11,C12)?

The professionals named in the filing: Architect: Mr Rupesh M Bhatt; Engineer: Japan B Shah. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Water Lily Ph-4 (Towers - C5,C6,C11,C12)?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Water Lily Ph-4 (Towers - C5,C6,C11,C12). Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Water Lily Ph-4 (Towers - C5,C6,C11,C12) to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.