ReraGenieLog inGet a buyer report

Home / Browse projects / Ahmedabad, Gujarat / NISHAN SATVA

Valid until 18 Dec 2026 Mixed Development project

NISHAN SATVA

By NISHAN DEVELOPERS

RG-GJ-40786 · RERA PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Municipal Corporation/MAA13161/EX1/240326/181226 · Last updated on GujRERA portal: 11 Mar 2026

Source: official GujRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Nothing verified clear yet
Dec 2026Possession promisedmoved 12 months from the original
4 of 9Construction stages donefurthest along: Staircases, 90%
49 of 80Units unsoldnot recorded sold or booked
Jump to the 42 documents Report an error

NISHAN SATVA is a Mixed Development project by NISHAN DEVELOPERS in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Municipal Corporation/MAA13161/EX1/240326/181226 on 21 Mar 2024. Possession is promised by 18 Dec 2026. The completion date has moved by 12 months from the original filing. 31 of the 80 units on this registration are recorded sold or booked, and 4 of 9 construction stages are filed complete.

At a glance

Project

  • NameNISHAN SATVA
  • TypeMixed Development
  • Location
    • NISHAN SATVA
    • OPP. HARIVILLA APARTMENT
    • RAMJI MANDIR ROAD
    • RANIP
    • RANIP
    • Ahmedabad City
    • Ahmedabad
    • 382480
  • Pincode382480
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Municipal Corporation/MAA13161/EX1/240326/181226
  • ReraGenie IDRG-GJ-40786

Builder

  • NameNISHAN DEVELOPERS
  • Entity typePARTNERSHIP FIRM
  • Other registrations2 more →

Key dates

this monthRegisteredMar 2024First promiseDec 2025Revised toDec 2026

Key facts

Registration and timeline

  • StatusValid until 18 Dec 2026
  • Registered on21 Mar 2024
  • Promised completion18 Dec 2026
  • Revised completionRevised to 18 Dec 2026 (originally 21 Dec 2025)
  • Buildings1 building record
  • Documents filed42 files

Current status

39%31 of 80 units booked
87.9%Of the estimated cost spent so far

Figures as on 11 Mar 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A+B---701080

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 11 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 9 construction stages are filed complete. The stage furthest along is Staircases, at 90%.

A+B: 76% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats85%
Sanitary fittings within the flats10%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing80%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing20%

Progress on shared amenities19

As on 11 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes25%
Water supplyYes55%
Sewerage (chamber, lines, septic tank, STP)Yes45%
Storm water drainsYes45%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes0%
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes40%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes10%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes10%
Drinking water facilitiesYes0%
Emergency evacuationYes0%
Use of renewable energyYes0%
SecurityYes0%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,710 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 16.50 cr
Cost incurredRs 14.50 cr
Spent of the estimate87.88%
BuildingWingEstimatedIncurred
A+BNARs 16.50 crRs 14.50 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectUrvashi Lalitkumar Tuli
EngineerMEET RAJESHKUMAR PATEL

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Municipal Corporation/MAA13161/EX1/240326/181226Applied Dec 2025; approved Mar 2026

Documents filed42

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Municipal Corporation/MAA13161/EX1/240326/181226 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)11 Mar 2026
Engineer's certificate (Form 2)11 Mar 2026
Engineer's certificate annexure11 Mar 2026
Accountant's certificate (Form 3)11 Mar 2026
Site photograph, A+B10 Mar 2026
RERA registration certificate21 Mar 2024
Extension certificate-
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Proforma sale deed-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

39%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one moved by 12 months

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep NISHAN SATVA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near RANIP5,400+ in Ahmedabad

2 kmNISHAN SATVAOther 105Dot size: filed unitsN

Filed coordinates, straight-line distance. 105 registered projects within 2 km.

Builder: NISHAN DEVELOPERS

NISHAN DEVELOPERS has 3 registrations on GujRERA, including VISHWAS CITY 9 (BLOCK C) and NISHAN GRACE. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if NISHAN SATVA is delayed beyond 18 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of NISHAN SATVA?

The registered promoter entity is NISHAN DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in NISHAN SATVA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at NISHAN SATVA?

The professionals named in the filing: Architect: Urvashi Lalitkumar Tuli; Engineer: MEET RAJESHKUMAR PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NISHAN SATVA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NISHAN SATVA. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NISHAN SATVA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.