Home / Browse projects / Ahmedabad, Gujarat / SCARLET SPRINGS

Valid until 30 Apr 2029 Mixed Development project

SCARLET SPRINGS

By JAYATI INFRA SPACE

RG-GJ-29436 · RERA PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Municipal Corporation/MAA12911/A1M/121026/311228 · Last updated on GujRERA portal: 29 Sep 2026

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Apr 2029Possession promisedno revision filed
8 of 18Construction stages doneacross 2 buildings; furthest along: Internal walls, 80%
149 of 257Units unsoldnot recorded sold or booked
Jump to the 29 documents Report an error

SCARLET SPRINGS is a Mixed Development project by JAYATI INFRA SPACE in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Municipal Corporation/MAA12911/A1M/121026/311228 on 12 Feb 2024. Possession is promised by 30 Apr 2029. 108 of the 257 units on this registration are recorded sold or booked, and 8 of 18 construction stages are filed complete.

At a glance

Project

  • NameSCARLET SPRINGS
  • TypeMixed Development
  • Location
    • SCARLET SPRINGS
    • NEAR KHODIAR MATA TEMPLE
    • NEW RANIP
    • AHMEDABAD
    • KALI
    • Ahmedabad City
    • Ahmedabad
    • 382480
  • Pincode382480
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Municipal Corporation/MAA12911/A1M/121026/311228
  • ReraGenie IDRG-GJ-29436

Builder

  • NameJAYATI INFRA SPACE
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredFeb 2024PromisedApr 2029

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2029
  • Registered on12 Feb 2024
  • Promised completion30 Apr 2029
  • Revised completionNone
  • Buildings2 building records
  • Documents filed29 files

Current status

42%108 of 257 units booked
78.8%Of the estimated cost spent so far

Figures as on 29 Sep 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A+B+C---16833201
D---56056

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building2

As on 29 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 18 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 80%.

A+B+C59%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats80%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing70%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
D63%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities19

As on 29 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes20%
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsYes50%
Treatment and disposal of sewage and sullage waterYes0%
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes50%
Fire fightingYes0%
Drinking water facilitiesYes50%
Emergency evacuationYes50%
Use of renewable energyYes0%
SecurityYes0%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,353 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 33.97 cr
Cost incurredRs 26.75 cr
Spent of the estimate78.75%
BuildingWingEstimatedIncurred
A+B+CNARs 25.48 crRs 19.11 cr
DNARs 8.49 crRs 7.64 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRISHI PRADYUMAN BARAIYA
EngineerNEEL RAMESHBHAI PATEL

Documents filed29

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Municipal Corporation/MAA12911/A1M/121026/311228 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)29 Sep 2026
Architect's certificate (Form 1)29 Jul 2026
Engineer's certificate (Form 2)29 Jul 2026
Engineer's certificate annexure29 Jul 2026
Site photograph, A+B+C29 Jul 2026
Site photograph, D29 Jul 2026
RERA registration certificate12 Feb 2024
Proforma agreement for sale-
Auditor's report (3 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Proforma sale deed-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

42%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one has not

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep SCARLET SPRINGS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near KALI5,400+ in Ahmedabad

2 kmSCARLET SPRINGSOther 126Dot size: filed unitsN

Filed coordinates, straight-line distance. 126 registered projects within 2 km.

Builder: JAYATI INFRA SPACE

JAYATI INFRA SPACE has 1 registration on GujRERA, including SCARLET SPRINGS. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if SCARLET SPRINGS is delayed beyond 30 Apr 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SCARLET SPRINGS?

The registered promoter entity is JAYATI INFRA SPACE, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SCARLET SPRINGS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SCARLET SPRINGS?

The professionals named in the filing: Architect: RISHI PRADYUMAN BARAIYA; Engineer: NEEL RAMESHBHAI PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SCARLET SPRINGS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SCARLET SPRINGS. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SCARLET SPRINGS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.