Home / Browse projects / Dharwad, Karnataka / NIKETAN LUXURIA

Registration approved No litigation declared Residential/Group Housing project

NIKETAN LUXURIA

By NIKETAN BUILDERS PVT LTD

RG-KA-30295 · RERA PRM/KA/RERA/1259/479/PR/130924/007011 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Sep 2027Possession promisedno revision filed
17 of 17Construction stages doneevery applicable stage filed complete
1 of 16Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 139 documents Report an error

NIKETAN LUXURIA is a Residential/Group Housing project by NIKETAN BUILDERS PVT LTD in Dharwad, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1259/479/PR/130924/007011 on 13 Sep 2024. Possession is promised by 30 Sep 2027. 15 of the 16 units on this registration are recorded sold or booked, and 17 of 17 construction stages are filed complete.

At a glance

Project

  • NameNIKETAN LUXURIA
  • TypeResidential/Group Housing
  • Location
    • Hubballi
    • Dharwad
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1259/479/PR/130924/007011
  • ReraGenie IDRG-KA-30295

Builder

  • NameNIKETAN BUILDERS PVT LTD
  • Entity typeCompany
  • GSTIN29AAACN6740P1ZV
  • Authorized SignatoryVISHNU MEHARWADE
  • Managing DirectorVISHNU MEHARWADE
  • DirectorMEENAKASHI KOTHARI
  • Project HeadATUL KOTHARI

Key dates

this monthRegisteredSep 2024PromisedSep 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on13 Sep 2024
  • Promised completion30 Sep 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed139 files

Current status

94%15 of 16 units booked
12.4%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
NIKETAN LUXURIA---16016

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

17 of 17 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Painting100%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)100%
Wardrobe, Showcase, Kitchen cabinet, Puja work100%
Elevation work100%
Internal and External work including landscapes as per sanctioned drawingsNot applicable

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Sewage and Drainage SystemYes100%
Water conservation/rain water harvesting/recharge of ground waterYes100%
Energy managementYes100%
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes100%
Emergency Evacuation servicesYes100%
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes100%
Storm water drainsYes100%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingNoNot applicable
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes100%
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes100%
Piped GasNoNot applicable
Water and SanitationYes100%
Air ConditioningNoNot applicable
StaircasesYes100%
LiftsYes100%
Corridor/LobbiesYes100%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes100%
BasementYes100%
TerraceYes100%
Outer WallYes100%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership5

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners5
LandownerVillageDistrict
Mukesh Kumar Ails Mukesh Dhirajlal Shah--
Rajesh Shah--
Lalit Kumar Shah--
Girish Shah--
Deepak kumar Shah--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 4.18 cr
Cost incurredRs 51.66 lakh
Spent of the estimate12.36%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 3.92 crRs 51.66 lakh
Payment of taxesRs 26.01 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSanjaykumar L Biranur
EngineerMURALIDHAR MALLIDU
Chartered AccountantM R JOSHI

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed139

As listed on the registration, under the names the promoter filed them with; the newest 80 of 139 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1259/479/PR/130924/007011 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: form_4 niketan luxuria CA.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: A C Niketan Luxuria FORM 5.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: form _6 niketan luxuria EC.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: form - 4 n l c a.pdf14 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: form 5 archite engg Niketan Luxuria.pdf14 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate Niketan Luxuria 30062026.pdf14 Jul 2026
Q1 2026-27 Water supply and sewage board14 Jul 2026
Q1 2026-27 KPTCL- BESCOM14 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: form 4 chartered accountant NL.pdf9 Jul 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: form 5 archite engg Niketan Luxuria.pdf9 Jul 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate Niketan Luxuria.pdf9 Jul 2026
Q4 2025-26 Water supply and sewage board9 Jul 2026
Q4 2025-26 KPTCL- BESCOM9 Jul 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: FROM CA 1.pdf15 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: from 05 NIKETAN LUXURIA 31 12 2025.pdf15 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: FORM-6 NIKETAN LUXURIA-31-12-2025.pdf15 Jan 2026
Q3 2025-26 Water supply and sewage board15 Jan 2026
Q3 2025-26 KPTCL- BESCOM15 Jan 2026
Affidavit for Section-3 NonViolationFile: Affidavit for Section-3 NonViolation.pdf1 Aug 2024
Declaration For Section 3 non-violationFile: Declaration For Section 3 non-violation.pdf1 Aug 2024
Form 6 Engineers CertificateFile: Form 6 Engineers Certificate.pdf1 Aug 2024
HESCOM NOCFile: HESCOM NOC.pdf1 Aug 2024
SINGLE PLOT LAYOUT ORDERFile: SINGLE PLOT LAYOUT ORDER.pdf1 Aug 2024
Water NocFile: WATER NOC.jpg1 Aug 2024
CDP MapFile: CDP with Demarcation.png1 Aug 2024
Bank StatementsFile: Bank Statements.pdf1 Aug 2024
Bank StatementsFile: bank statements.pdf1 Aug 2024
Clarification reply to the queries received.File: Notice reply 23-07-2024.pdf1 Aug 2024
Single plot Layout orderFile: SINGLE PLOT LAYOUT ORDER.pdf25 Apr 2024
CDP MapFile: CDP HUBBALLI FOR NIKETAN_compressed.pdf25 Apr 2024
Building permissionFile: Building Permission.pdf25 Apr 2024
Form -6 Engineer CertificateFile: Form 6 Engineers Certificate.pdf25 Apr 2024
Hescom fee receiptFile: Electricity Bill.jpg25 Apr 2024
Borewell receiptFile: Borewell Receipt.jpg25 Apr 2024
STP ExplanationFile: STP Explanation.pdf25 Apr 2024
BorewellFile: Borewell .jpg25 Apr 2024
Area Calculation Certificate by ArchitectFile: Area Calculation Certificate.jpg25 Apr 2024
Upload memorandum of association and article of associationFile: MOA AND AOA.pdf5 Mar 2024
Upload memorandum of association and article of associationFile: All Sources of Fund.pdf5 Mar 2024
Promoter need to upload title deed in favour of mukesh kumar instead of othersFile: Sale Deed.pdf5 Mar 2024
Upload Single plot layoutFile: PT SHEET.pdf5 Mar 2024
Upload Single plot layout OrderFile: SINGLE PLOT LAYOUT ORDER.pdf5 Mar 2024
Upload certified Carpet area calculationFile: Carpet Area Details.pdf5 Mar 2024
Upload CDP map showing the proposed siteFile: CDP map.pdf5 Mar 2024
Upload commencement certificateFile: COMMENCEMENT CERTIFICATE.pdf5 Mar 2024
Upload all sanctioned drawings Floor plans, sectional drawings and elevationsFile: SANCTION DRAWINGS.pdf5 Mar 2024
Please update the Type of Inventory and No. of Inventory with the brief BHK-wFile: BHK wise.pdf5 Mar 2024
Please update the Amenities and Common area details properly on the projectFile: AMENITIES AND COMMON AREA DETAILS.pdf5 Mar 2024
brief estimated cost of construction certified by the registered Civil EngineerFile: ESTIMATION COPY.pdf5 Mar 2024
please update the area details properly on the project detail page as per the approved drawingFile: SANCTION DRAWINGS.pdf5 Mar 2024
Please update the Project bank account in Mode payment clause and Time line completion date in the pFile: agrement of sale.pdf5 Mar 2024
Please upload the self-attested copy of the correctly scanned HESCOM NOC and Water supply NOC alongFile: Hescom.pdf5 Mar 2024
Please upload the STP design drawing certified by the Engineer as per the guidelines of KSPCBFile: STP NORMS.pdf5 Mar 2024
Please upload the Land cost calculation sheet as per the guidance value(Self-attested copy)File: LAND COST OF THE PROJECT.pdf5 Mar 2024
the source of water supply mentioned as bore well, please upload the permission letter issued byFile: SOURCE OF WATER FOR THE PROJECT.pdf5 Mar 2024
Please mention the project name and project address and upload the project section 3(1) notarized afFile: notarized affidavit.pdf5 Mar 2024
memorandum of association and article of associationFile: MOA6.pdf3 Feb 2024
directors details with KYCFile: KYC DIRECTORS.pdf3 Feb 2024
mention 100% and 30 % account details in CA certificate , upload chartered accountant certificate inFile: Form - 1 CA Certificate.pdf3 Feb 2024
profit and loss account and balance sheet, 2020-21, 2021-22 & 2022-23 with CA UDIN along with scheduFile: P & L Balance Sheet THREE YEARS.pdf3 Feb 2024
sources of funds to completeFile: All Sources of Fund.pdf3 Feb 2024
visible MR extractFile: MR Extract.pdf3 Feb 2024
title deed in favour of land ownerFile: Sale Deed.pdf3 Feb 2024
conversion order issued by the deputy commissionerFile: n a order letter and n a order copy.pdf3 Feb 2024
latest katha extract obtained from local bodyFile: katha and e swatha.pdf3 Feb 2024
non-litigation affidavit need to be notarizedFile: Non Litigation Affidavit.pdf3 Feb 2024
advocate search reportFile: advocate search report.pdf3 Feb 2024
form-B need to be notarizedFile: Form - B.pdf3 Feb 2024
JD AFFIDAVIT CUM DECLARATIONFile: Affidavit Cum Declaration jd.pdf3 Feb 2024
Break up of types of Units (BHKwise)File: Break up of types of Units (BHKwise).pdf3 Feb 2024
FAR As per the sanction PlanFile: FAR.pdf3 Feb 2024
Height of the building mentioned in the development details pageFile: Height of the building mentioned in the development.pdf3 Feb 2024
Upload Single plot layoutFile: PT SHEET.pdf3 Feb 2024
Upload Single plot layout OrderFile: PT SHEET.pdf3 Feb 2024
Upload certified Carpet area calculationFile: Carpet Area Details.pdf3 Feb 2024
Upload CDP map showing the proposed siteFile: CDP map.pdf3 Feb 2024
KSPCB CFEFile: Karnataka State Pollution Control Board Letter Niketan Luxuria.pdf3 Feb 2024
commencement certificateFile: Building Permission.pdf3 Feb 2024

How this compares with Dharwad

94%of this project is bookeddistrict median 38%
29%of Dharwad projects moved their completion datethis one has not
0%of Dharwad registrations are shown as withdrawn or revokedthis one is not

Computed across the 250+ Dharwad projects on ReraGenie, from their own filings.

Keep NIKETAN LUXURIA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dharwad250+ in Dharwad

Builder: NIKETAN BUILDERS PVT LTD

NIKETAN BUILDERS PVT LTD has 1 registration on RERA Karnataka, including NIKETAN LUXURIA. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Dharwad district page.

Frequently asked questions

What are my rights if NIKETAN LUXURIA is delayed beyond 30 Sep 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of NIKETAN LUXURIA?

The registered promoter entity is NIKETAN BUILDERS PVT LTD, a company as per the filing. Its GSTIN 29AAACN6740P1ZV can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in NIKETAN LUXURIA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at NIKETAN LUXURIA?

The professionals named in the filing: Architect: Sanjaykumar L Biranur; Engineer: MURALIDHAR MALLIDU; Chartered Accountant: M R JOSHI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NIKETAN LUXURIA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NIKETAN LUXURIA. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NIKETAN LUXURIA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.