Home / Browse projects / Dharwad, Karnataka / NANDAVAN
NANDAVAN
RG-KA-06275 · RERA PRM/KA/RERA/1259/479/PR/211024/007157 · Last updated on RERA Karnataka portal: 14 Oct 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
NANDAVAN is a Residential/Group Housing project by M/s REDBRICKS in Dharwad, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1259/479/PR/211024/007157 on 21 Oct 2024. Possession is promised by 31 Dec 2028. 10 of the 18 units on this registration are recorded sold or booked, and 5 of 17 construction stages are filed complete.
At a glance
Project
- NameNANDAVAN
- TypeResidential/Group Housing
- Location
- Hubballi
- Dharwad
- PincodeNot stated
- RERA no.PRM/KA/RERA/1259/479/PR/211024/007157
- ReraGenie IDRG-KA-06275
Builder
- NameM/s REDBRICKS
- Entity typePartnership Firm
- GSTIN29ABFFR2964N1ZG
- Authorized SignatoryRikabchand Jain
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on21 Oct 2024
- Promised completion31 Dec 2028
- Revised completionNone
- Buildings1 building record
- Documents filed98 files
Current status
Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Nandavan | - | - | - | 18 | 0 | 18 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 14 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 17 construction stages are filed complete. The stage furthest along is Masonry Construction, at 80%.
Building: 40% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Upto Plinth Level | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 100% |
| Retaining wall (All types) | Not applicable |
| RCC or MS Framed structure | 100% |
| Masonry Construction | 80% |
| Plastering inside , outside & Ceiling | 70% |
| Joinery: Doors, Windows, Ventilators etc | 10% |
| Basic work of Water supply, Sanitary and Electrification | 10% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 0% |
| Railing and Grill fixing | 0% |
| Electrification, Water supply and Sanitary Finishing | 10% |
| Painting | 0% |
| Fire prevention and fire fighting fitting and fixture with network | 0% |
| Weather Proof work(tile,concrete) | 0% |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 0% |
| Internal and External work including landscapes as per sanctioned drawings | 0% |
Progress on shared amenities40
As on 14 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 50% |
| Sewage and Drainage System | Yes | 50% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 50% |
| Energy management | Yes | 50% |
| Fire protection and fire safety requirements | Yes | 50% |
| Solid waste management and disposal | Yes | 50% |
| Emergency Evacuation services | Yes | 50% |
| Internal Roads & Footpaths | Yes | 50% |
| Electricity supply transformer and substation | Yes | 50% |
| Storm water drains | Yes | 50% |
| Use of renewable energy | Yes | 50% |
| Sewage Treatment Plant (STP) | Yes | 50% |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Electricity | Yes | 50% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 50% |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | Yes | 50% |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | 50% |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 90% |
| Lifts | Yes | 70% |
| Corridor/Lobbies | Yes | 70% |
| Fire escapes | Yes | 60% |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | 50% |
| Basement | Yes | 90% |
| Terrace | Yes | 20% |
| Outer Wall | Yes | 20% |
| Open parking areas | Yes | 50% |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | 20% |
| Common storage spaces | No | Not applicable |
Land and ownership4
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Rikabchand Jain | - | - |
| Sheetal S Raibagi | - | - |
| Mr. Rikabchand Jain | - | - |
| Mrs. Sheetal S Raibagi | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 6.00 cr | Rs 4.86 cr |
| Principal sum and interest payable to financial institutions-Money Lenders on construction funding or money borrowed for construction | Rs 72.80 lakh | - |
| On-site expenditure-Salaries of workers | Rs 9.00 lakh | Rs 7.55 lakh |
| On-site expenditure-Consultants Fees | Rs 6.00 lakh | - |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Ar. Prasad Manvi |
| Engineer | Er. Deepak Kawad |
| Chartered Accountant | CA Anujkumar Laddha |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed98
As listed on the registration, under the names the promoter filed them with; the newest 80 of 98 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1259/479/PR/211024/007157 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Q2 2026-2027 Form 4 CA.pdf | 14 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Q2 2026-2027 From 5 Arch.pdf | 14 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Q2 2026-2027 Form 6 Eng.pdf | 14 Oct 2026 |
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Q12026-2027.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 Q120262027.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 Q1 2026-2027.pdf | 15 Jul 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Certificate.pdf | 14 Apr 2026 |
| Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Srchitect Certificate.pdf | 14 Apr 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate.pdf | 14 Apr 2026 |
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Certificate.pdf | 6 Feb 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect Certificate.pdf | 6 Feb 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate.pdf | 6 Feb 2026 |
| REDBRICKS Financial StatementsFile: REDBRICKS Financial Statements.pdf | 3 Aug 2024 |
| CA Certificate Form REG-1File: CA Certificate Form REG-1.pdf | 3 Aug 2024 |
| Clarification on CTSFile: Clarification on CTS.pdf | 3 Aug 2024 |
| Certified carpet area statementFile: Certified carpet area statement.pdf | 3 Aug 2024 |
| CDP MapFile: HUBBALLI CDP.pdf | 3 Aug 2024 |
| Demarked site on CDPFile: CDP with Demarcation.png | 3 Aug 2024 |
| Sanctioned DrawingFile: Sanctioned Drawing.pdf | 3 Aug 2024 |
| ElevationsFile: Elevation of the Building.pdf | 3 Aug 2024 |
| Sectional DrawingsFile: Sectional Plan.pdf | 3 Aug 2024 |
| Floor PlansFile: Floor Plans.pdf | 3 Aug 2024 |
| Clarification on Unsecured LoansFile: Clarification on unsecured loans.pdf | 11 Jul 2024 |
| No Financial StatementsFile: No Financial Statements.pdf | 11 Jul 2024 |
| Latest ECFile: Latest EC.pdf | 11 Jul 2024 |
| CA From REG-1File: CA Certificate Form REG-1.pdf | 11 Jul 2024 |
| Clarification on CTSFile: Clarification on CTS.pdf | 11 Jul 2024 |
| HUBBALLI CDPFile: HUBBALLI CDP.pdf | 11 Jul 2024 |
| STP ExplanationFile: STP Explanation.pdf | 11 Jul 2024 |
| Sectionl DrawingsFile: Approval Drawing.pdf | 11 Jul 2024 |
| No Financial StatementsFile: No Financial Statements.pdf | 14 Jun 2024 |
| CA Form REG-1File: CA Certificate Form REG-1.pdf | 14 Jun 2024 |
| List of lenders with their pan numberFile: List of lenders with their pan number.jpg | 14 Jun 2024 |
| Bank AffidavitFile: Bank Affidavit.pdf | 14 Jun 2024 |
| ECFile: EC.pdf | 14 Jun 2024 |
| CTSFile: CTS.pdf | 14 Jun 2024 |
| KHATAFile: RTC Copy.pdf | 14 Jun 2024 |
| CDPFile: HUBBALLI.pdf | 14 Jun 2024 |
| Villag MapFile: Kusugal Village Map.pdf | 14 Jun 2024 |
| Commencemant CertificateFile: Approval Letter (1).pdf | 14 Jun 2024 |
| KSPCBFile: STP Explanation.pdf | 14 Jun 2024 |
| STPFile: STP Explanation.pdf | 14 Jun 2024 |
| HESCOM NOCFile: NOC-HESCOM.pdf | 14 Jun 2024 |
| Fire NOCFile: NOC-Fire Services.pdf | 14 Jun 2024 |
| Registration CertificateFile: Firm Reg & Pan.pdf | - |
| Partnership DeedFile: Partnership Deed.pdf | - |
| Partner Details | - |
| Partner Details | - |
| Certificate issued by CA Form 1File: CA Certificate Form REG-1.pdf | - |
| Certificate issued by Architect Form 2File: Architect Certificate Form 2.pdf | - |
| Certificate issued by Engineer Form 3File: Engineer Certificate Form 3.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: No Litigation Affidavit.pdf | - |
| Certificate from Chartered AccountFile: CA Certificate Form REG-1.pdf | - |
| Balance Sheet 2022 - 2023File: No Financial Statements.pdf | - |
| Balance Sheet 2021 - 2022File: No Financial Statements.pdf | - |
| Balance Sheet 2020 - 2021File: No Financial Statements.pdf | - |
| Audited Profit and Loss Statement 2022 - 2023File: No Financial Statements.pdf | - |
| Audited Profit and Loss Statement 2021 - 2022File: No Financial Statements.pdf | - |
| Audited Profit and Loss Statement 2020 - 2021File: No Financial Statements.pdf | - |
| Director's Report 2022 - 2023File: No Director's Report.pdf | - |
| Director's Report 2021 - 2022File: No Director's Report.pdf | - |
| Director's Report 2020 - 2021File: No Director's Report.pdf | - |
| Cash Flow Statement 2022 - 2023File: No Cash Flow Statement.pdf | - |
| Cash Flow Statement 2021 - 2022File: No Cash Flow Statement.pdf | - |
| Auditor's Report 2022 - 2023File: No Financial Statements.pdf | - |
| Auditor's Report 2021 - 2022File: No Financial Statements.pdf | - |
| Auditor's Report 2020 - 2021File: No Financial Statements.pdf | - |
| Income Tax Return Acknowledgement 2022 - 2023File: ITR Acknowledgement 2022-23.pdf | - |
| Income Tax Return Acknowledgement 2021 - 2022File: No Financial Statements.pdf | - |
| Income Tax Return Acknowledgement 2020 - 2021File: No Financial Statements.pdf | - |
| Approval Letter (1) | - |
| NOC-HESCOM | - |
| Approval Letter (1) | - |
| Approval Drawing | - |
| Approval Drawing | - |
| City Servey Map | - |
| Approval Drawing | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Dharwad
Computed across the 250+ Dharwad projects on ReraGenie, from their own filings.
Keep NANDAVAN on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Dharwad250+ in Dharwad
construction of 1248 houses at Hubli
Commissioner
Akshay Town Tarihal Sector A
Suresh Enterprises Pvt.Ltd
ONE HUBLI PHASE-1
SHETTY-PATIL DEVELOPERS LLP
construction of 784 houses at Hubli
Commissioner
M/s. PRIDE IKON
M/s. PRIDE GROUP
Pourakarmikas Gruha Bhagya Yojane
Hubli Dharwad Municipal Corporation
See every Dharwad project, with the district possession charts
Builder: M/s REDBRICKS
M/s REDBRICKS has 1 registration on RERA Karnataka, including NANDAVAN. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Dharwad district page.
Frequently asked questions
What are my rights if NANDAVAN is delayed beyond 31 Dec 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of NANDAVAN?
The registered promoter entity is M/s REDBRICKS, a partnership firm as per the filing. Its GSTIN 29ABFFR2964N1ZG can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in NANDAVAN?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at NANDAVAN?
The professionals named in the filing: Architect: Ar. Prasad Manvi; Engineer: Er. Deepak Kawad; Chartered Accountant: CA Anujkumar Laddha. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in NANDAVAN?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback