Home / Browse projects / Ahmedabad, Gujarat / N K ANANTAYA

Valid until 31 Jul 2028 Mixed Development project

N K ANANTAYA

By AVISHKAR BUILDCON LLP

RG-GJ-98427 · RERA PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA08629/A1M/231122 · Last updated on GujRERA portal: 20 Jul 2026

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Jul 2028Possession promisedno revision filed
15 of 80Construction stages doneacross 8 buildings; furthest along: Stilt Floor, 95%
222 of 427Units unsoldnot recorded sold or booked
Jump to the 48 documents Report an error

N K ANANTAYA is a Mixed Development project by AVISHKAR BUILDCON LLP in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA08629/A1M/231122 on 16 Jun 2021. Possession is promised by 31 Jul 2028. 205 of the 427 units on this registration are recorded sold or booked, and 15 of 80 construction stages are filed complete.

At a glance

Project

  • NameN K ANANTAYA
  • TypeMixed Development
  • Location
    • T.P.S. No. 26 (Vasna)
    • F. P. No. 372
    • Survey No. 278/Paiki
    • VASNA
    • Ahmedabad City
    • Ahmedabad
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA08629/A1M/231122
  • ReraGenie IDRG-GJ-98427

Builder

  • NameAVISHKAR BUILDCON LLP
  • Entity typeLIMITED LIABILITY PARTNERSHIP FIRM

Key dates

this monthRegisteredJun 2021PromisedJul 2028

Key facts

Registration and timeline

  • StatusValid until 31 Jul 2028
  • Registered on16 Jun 2021
  • Promised completion31 Jul 2028
  • Revised completionNone
  • Buildings8 building records
  • Documents filed48 files

Current status

48%205 of 427 units booked
61.0%Of the estimated cost spent so far

Figures as on 20 Jul 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
E---54054
D---27027
G---54054
F---55055
I---54761
H---55661
C---54054
B---55661

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building8

As on 20 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

15 of 80 construction stages are filed complete across 8 buildings. The stage furthest along is Stilt Floor, at 95%.

E15%
ActivityProgress
Excavation100%
Podiums (if any)0%
Plinth50%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
D14%
ActivityProgress
Excavation100%
Podiums (if any)0%
Plinth40%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
G54%
ActivityProgress
Excavation100%
Podiums (if any)100%
Plinth100%
Stilt Floor95%
Slabs of Super Structure75%
Internal walls, internal plaster, floorings, doors and windows within flats35%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
F17%
ActivityProgress
Excavation100%
Podiums (if any)0%
Plinth70%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
I56%
ActivityProgress
Excavation100%
Podiums (if any)95%
Plinth100%
Stilt Floor95%
Slabs of Super Structure95%
Internal walls, internal plaster, floorings, doors and windows within flats45%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks30%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
H57%
ActivityProgress
Excavation100%
Podiums (if any)100%
Plinth100%
Stilt Floor95%
Slabs of Super Structure95%
Internal walls, internal plaster, floorings, doors and windows within flats40%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
C52%
ActivityProgress
Excavation100%
Podiums (if any)90%
Plinth100%
Stilt Floor95%
Slabs of Super Structure55%
Internal walls, internal plaster, floorings, doors and windows within flats45%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
B84%
ActivityProgress
Excavation100%
Podiums (if any)90%
Plinth100%
Stilt Floor95%
Slabs of Super Structure95%
Internal walls, internal plaster, floorings, doors and windows within flats90%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing85%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%

Progress on shared amenities19

As on 20 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes0%
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes0%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area12,378 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 113.75 cr
Cost incurredRs 69.44 cr
Spent of the estimate61.04%
BuildingWingEstimatedIncurred
BNARs 15.03 crRs 13.13 cr
CNARs 15.03 crRs 9.02 cr
DNARs 15.03 crRs 5.55 cr
ENARs 15.03 crRs 5.56 cr
FNARs 15.03 crRs 5.51 cr
HNARs 15.03 crRs 12.78 cr
INARs 15.03 crRs 12.78 cr
GNARs 8.54 crRs 5.13 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectATULCHANDRA S DAVE
EngineerNELSON N. MACWAN

Documents filed48

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA08629/A1M/231122 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)20 Jul 2026
Engineer's certificate (Form 2)20 Jul 2026
Engineer's certificate annexure20 Jul 2026
Accountant's certificate (Form 3)20 Jul 2026
Site photograph, E20 Jul 2026
Site photograph, D20 Jul 2026
Site photograph, G20 Jul 2026
Site photograph, F20 Jul 2026
Site photograph, I20 Jul 2026
Site photograph, H20 Jul 2026
Site photograph, C20 Jul 2026
Site photograph, B20 Jul 2026
RERA registration certificate16 Jun 2021
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

48%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one has not

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep N K ANANTAYA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Ahmedabad5,400+ in Ahmedabad

2 kmN K ANANTAYAOther 144Dot size: filed unitsN

Filed coordinates, straight-line distance. 144 registered projects within 2 km.

Builder: AVISHKAR BUILDCON LLP

AVISHKAR BUILDCON LLP has 1 registration on GujRERA, including N K ANANTAYA. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if N K ANANTAYA is delayed beyond 31 Jul 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of N K ANANTAYA?

The registered promoter entity is AVISHKAR BUILDCON LLP, a limited liability partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in N K ANANTAYA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at N K ANANTAYA?

The professionals named in the filing: Architect: ATULCHANDRA S DAVE; Engineer: NELSON N. MACWAN. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in N K ANANTAYA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About N K ANANTAYA. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save N K ANANTAYA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.