ReraGenieLog inGet a buyer report

Home / Browse projects / Valsad, Gujarat / Mithali Residency

Valid until 31 Dec 2019 Residential/Group Housing project

Mithali Residency

By Mithali Enterprise

RG-GJ-39659 · RERA PR/GJ/VALSAD/PARDI/Others/RAA05804/290719 · Last updated on GujRERA portal: 31 Dec 2019

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
  • Separate project account declared
Dec 2019Possession promisedno revision filed
12 of 12Construction stages doneacross 2 buildings; every applicable stage filed complete
32 of 32Units unsoldnot recorded sold or booked
Jump to the 42 documents Report an error

Mithali Residency is a Residential/Group Housing project by Mithali Enterprise in Valsad, Gujarat, registered with GujRERA as PR/GJ/VALSAD/PARDI/Others/RAA05804/290719 on 29 Jul 2019. Possession is promised by 31 Dec 2019. 0 of the 32 units on this registration are recorded sold or booked, and 12 of 12 construction stages are filed complete.

At a glance

Project

  • NameMithali Residency
  • TypeResidential/Group Housing
  • Location
    • Survey No. 3124
    • Khodiyar Nagar
    • Near Sulabh Nagar
    • Behind Brahma Kumaris Ashram
    • N. H. No. 8
    • Killa Pardi
    • Pardi
    • Valsad
    • 396125
  • Pincode396125
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VALSAD/PARDI/Others/RAA05804/290719
  • ReraGenie IDRG-GJ-39659

Builder

  • NameMithali Enterprise
  • Entity typeOther

Key dates

this monthRegisteredJul 2019PromisedDec 2019

Key facts

Registration and timeline

  • StatusValid until 31 Dec 2019
  • Registered on29 Jul 2019
  • Promised completion31 Dec 2019
  • Revised completionNone
  • Buildings2 building records
  • Documents filed42 files

Current status

0%0 of 32 units booked
100.0%Of the estimated cost spent so far

Figures as on 31 Dec 2019, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A Building---16016
B Building---16016

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building2

As on 31 Dec 2019, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

12 of 12 construction stages are filed complete across 2 buildings.

A Building100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B Building100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 31 Dec 2019, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyNoNot applicable
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,315 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 2.09 cr
Cost incurredRs 2.09 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
A BuildingNARs 1.05 crRs 1.05 cr
B BuildingNARs 1.05 crRs 1.05 cr

Documents filed42

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VALSAD/PARDI/Others/RAA05804/290719 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)31 Dec 2019
Site photograph, A Building31 Dec 2019
Site photograph, B Building31 Dec 2019
Accountant's certificate (Form 3)7 Nov 2019
RERA registration certificate29 Jul 2019
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-
Engineer's certificate (Form 2)-
Engineer's certificate annexure-

How this compares with Valsad

0%of this project is bookeddistrict median 45%
23%of Valsad projects moved their completion datethis one has not

Computed across the 390+ Valsad projects on ReraGenie, from their own filings.

Keep Mithali Residency on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Pardi390+ in Valsad

2 kmMithali ResidencyOther 25Dot size: filed unitsN

Filed coordinates, straight-line distance. 25 registered projects within 2 km.

Builder: Mithali Enterprise

Mithali Enterprise has 1 registration on GujRERA, including Mithali Residency. Read the full track record. See more projects on the Valsad district page.

Frequently asked questions

What are my rights if Mithali Residency is delayed beyond 31 Dec 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Mithali Residency?

The registered promoter entity is Mithali Enterprise. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Mithali Residency?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in Mithali Residency?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Mithali Residency. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Mithali Residency to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.