Home / Browse projects / Valsad, Gujarat / Arham Industrial Park
Arham Industrial Park
RG-GJ-28740 · RERA PR/GJ/VALSAD/PARDI/Others/CAA05677/EX1/EX2/040925/200626 · Last updated on GujRERA portal: 17 Jul 2025
Source: official GujRERA filing
Red flags
- Completion date moved by 24 months
- 2 extensions taken
Clear
- Nothing verified clear yet
Saved.
Arham Industrial Park is a Commercial project by ARHAM DEVELOPERS in Valsad, Gujarat, registered with GujRERA as PR/GJ/VALSAD/PARDI/Others/CAA05677/EX1/EX2/040925/200626 on 9 Jul 2019. Possession is promised by 20 Jun 2026. The completion date has moved by 24 months from the original filing. 42 of the 344 units on this registration are recorded sold or booked, and 12 of 108 construction stages are filed complete.
At a glance
Project
- NameArham Industrial Park
- TypeCommercial
- Location
- Survey No.500/1
- Reliance Petrol Pump
- Opp.Tirumati Panchnath Mahadev Mandir On N.H -8
- Pardi
- Pardi
- Valsad
- 396125
- Pincode396125
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR/GJ/VALSAD/PARDI/Others/CAA05677/EX1/EX2/040925/200626
- ReraGenie IDRG-GJ-28740
Builder
- NameARHAM DEVELOPERS
- Entity typePARTNERSHIP FIRM
- Other registrations8 more →
Key dates
Key facts
Registration and timeline
- StatusValid until 20 Jun 2026
- Registered on9 Jul 2019
- Promised completion20 Jun 2026
- Revised completionRevised to 20 Jun 2026 (originally 30 Jun 2024)
- Buildings12 building records
- Documents filed55 files
Current status
Figures as on 17 Jul 2025, this project's latest GujRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| TOWER A | - | - | - | 0 | 96 | 96 |
| TOWER B | - | - | - | 0 | 0 | 18 |
| TOWER C | - | - | - | 0 | 0 | 18 |
| TOWER D | - | - | - | 0 | 0 | 20 |
| TOWER E | - | - | - | 0 | 0 | 18 |
| TOWER F | - | - | - | 0 | 0 | 18 |
| TOWER G | - | - | - | 0 | 0 | 18 |
| TOWER H | - | - | - | 0 | 0 | 28 |
| TOWER I | - | - | - | 0 | 0 | 26 |
| TOWER J | - | - | - | 0 | 0 | 24 |
| TOWER K | - | - | - | 0 | 0 | 24 |
| TOWER L | - | - | - | 0 | 0 | 36 |
The full filing
Everything below is from the project's own GujRERA filing, free to read.
Construction progress by building12
As on 17 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
12 of 108 construction stages are filed complete across 12 buildings. The stage furthest along is Installation of lifts, at 90%.
TOWER A78%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 10% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 90% |
TOWER B44%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 20% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
TOWER C0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 0% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
TOWER D0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 0% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
TOWER E0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 0% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
TOWER F0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 0% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
TOWER G0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 0% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
TOWER H0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 0% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
TOWER I0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 0% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
TOWER J0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 0% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
TOWER K0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 0% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
TOWER L61%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 66% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 50% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 50% |
Progress on shared amenities19
As on 17 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal roads and footpaths | Yes | 100% |
| Water supply | Yes | 50% |
| Sewerage (chamber, lines, septic tank, STP) | Yes | 100% |
| Storm water drains | Yes | 0% |
| Landscaping and tree planting | Yes | 0% |
| Street lighting | No | Not applicable |
| Community buildings | No | Not applicable |
| Treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Water conservation, rain water harvesting | Yes | 0% |
| Energy management | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 45% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Fire fighting | Yes | 45% |
| Drinking water facilities | No | Not applicable |
| Emergency evacuation | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Security | Yes | 0% |
| Letter box | No | Not applicable |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| TOWER A | NA | Rs 3.00 cr | Rs 2.85 cr |
| TOWER L | NA | Rs 2.34 cr | Rs 1.92 cr |
| TOWER K | NA | Rs 1.60 cr | - |
| TOWER H | NA | Rs 1.53 cr | - |
| TOWER I | NA | Rs 1.40 cr | - |
| TOWER B | NA | Rs 1.34 cr | Rs 94.13 lakh |
| TOWER C | NA | Rs 1.34 cr | - |
| TOWER J | NA | Rs 1.28 cr | - |
| TOWER D | NA | Rs 1.20 cr | - |
| TOWER E | NA | Rs 1.08 cr | - |
| TOWER F | NA | Rs 1.08 cr | - |
| TOWER G | NA | Rs 1.08 cr | - |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Prashant R Chokhawala |
| Engineer | Chetan H Sapariya |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Documents filed55
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VALSAD/PARDI/Others/CAA05677/EX1/EX2/040925/200626 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Accountant's certificate (Form 3) | 17 Jul 2025 |
| Architect's certificate (Form 1) | 2 Jul 2025 |
| Engineer's certificate (Form 2) | 2 Jul 2025 |
| Engineer's certificate annexure | 2 Jul 2025 |
| Site photograph, TOWER A | 1 Jul 2025 |
| Site photograph, TOWER A | 1 Jul 2025 |
| Site photograph, TOWER A | 1 Jul 2025 |
| Site photograph, TOWER B | 1 Jul 2025 |
| Site photograph, TOWER C | 1 Jul 2025 |
| Site photograph, TOWER D | 1 Jul 2025 |
| Site photograph, TOWER E | 1 Jul 2025 |
| Site photograph, TOWER F | 1 Jul 2025 |
| Site photograph, TOWER G | 1 Jul 2025 |
| Site photograph, TOWER H | 1 Jul 2025 |
| Site photograph, TOWER I | 1 Jul 2025 |
| Site photograph, TOWER J | 1 Jul 2025 |
| Site photograph, TOWER K | 1 Jul 2025 |
| Site photograph, TOWER L | 1 Jul 2025 |
| RERA registration certificate | 9 Jul 2019 |
| Extension certificate | - |
| Proforma agreement for sale | - |
| Auditor's report (1 of 3) | - |
| Auditor's report (2 of 3) | - |
| Auditor's report (3 of 3) | - |
| Income tax return (1 of 3) | - |
| Income tax return (2 of 3) | - |
| Income tax return (3 of 3) | - |
| Project specific document | - |
| Directors' report (1 of 3) | - |
| Directors' report (2 of 3) | - |
| Directors' report (3 of 3) | - |
| Commencement certificate | - |
| Approved sanctioned plan | - |
| Approved layout plan | - |
| Agreement | - |
| Land location | - |
| Encumbrance certificate | - |
| Area development document | - |
| Proforma allotment letter | - |
| Brochure | - |
| Project related document | - |
| Declaration in Form B | - |
| Title clearance certificate | - |
| Title report | - |
| Property card | - |
| Project photograph | - |
| Audited balance sheet (1 of 3) | - |
| Audited balance sheet (2 of 3) | - |
| Audited balance sheet (3 of 3) | - |
| Audited profit and loss statement (1 of 3) | - |
| Audited profit and loss statement (2 of 3) | - |
| Audited profit and loss statement (3 of 3) | - |
| Cash flow statement (1 of 3) | - |
| Cash flow statement (2 of 3) | - |
| Cash flow statement (3 of 3) | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Valsad
Computed across the 390+ Valsad projects on ReraGenie, from their own filings.
Keep Arham Industrial Park on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Pardi390+ in Valsad
Filed coordinates, straight-line distance. 14 registered projects within 2 km.
Ellora Park
VRAJ ENTERPRISE
Karmabhumi Dream City
Aakruts Commotrade Private Limited
LAKE CITY
KINAR ENTERPRISE
SAI UNIVERSAL PARK
SAI UNIVERSAL DEVELOPERS
Capital Hub
MAHARSHI ENTERPRISE
Rudra Arcade
Rudra Arcade
See every Valsad project, with the district possession charts
Builder: ARHAM DEVELOPERS
ARHAM DEVELOPERS has 9 registrations on GujRERA, including SHYAM PLAZA and The Elegance. Read the full track record. See more projects on the Valsad district page.
Frequently asked questions
What are my rights if Arham Industrial Park is delayed beyond 20 Jun 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.
How do I verify and contact the developer of Arham Industrial Park?
The registered promoter entity is ARHAM DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.
Is my payment protected in Arham Industrial Park?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Arham Industrial Park?
The professionals named in the filing: Architect: Prashant R Chokhawala; Engineer: Chetan H Sapariya. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Arham Industrial Park?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.