Red flags
- No red flags in this filing
Clear
- Completion date never moved
- Separate project account declared
Saved.
meera 26 residency is a Residential/Group Housing project by SAMARTH SURESHBHAI PATEL Proprietorship of S P BUILDERS in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/PADRA/Others/RAA04551/010119 on 1 Jan 2019. Possession is promised by 31 Dec 2020.
At a glance
Project
- Namemeera 26 residency
- TypeResidential/Group Housing
- Location
- sr. no. 1244/p
- padra kasba
- b/h western ceramic
- padra
- Padra
- Vadodara
- 391440
- Pincode391440
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR/GJ/VADODARA/PADRA/Others/RAA04551/010119
- ReraGenie IDRG-GJ-42520
Builder
- NameSAMARTH SURESHBHAI PATEL Proprietorship of S P BUILDERS
- Entity typeIndividual/Propritorship
- Other registrations2 more →
Key dates
Key facts
Registration and timeline
- StatusValid until 31 Dec 2020
- Registered on1 Jan 2019
- Promised completion31 Dec 2020
- Revised completionNone
- Buildings4 building records
- Documents filed19 files
Current status
Figures as on 31 Mar 2019, this project's latest GujRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| type A | - | - | - | - | - | 2 |
| type B | - | - | - | - | - | 1 |
| type C | - | - | - | - | - | 1 |
| type D | - | - | - | - | - | 22 |
The full filing
Everything below is from the project's own GujRERA filing, free to read.
Construction progress by building4
As on 31 Mar 2019, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
32 of 36 construction stages are filed complete across 4 buildings. The stage furthest along is Stilt Floor, at 0%.
type A89%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
type B89%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
type C89%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
type D89%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Progress on shared amenities19
As on 31 Mar 2019, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal roads and footpaths | Yes | 100% |
| Water supply | Yes | 100% |
| Sewerage (chamber, lines, septic tank, STP) | Yes | 100% |
| Storm water drains | No | Not applicable |
| Landscaping and tree planting | Yes | 100% |
| Street lighting | No | Not applicable |
| Community buildings | No | Not applicable |
| Treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Water conservation, rain water harvesting | No | Not applicable |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Fire fighting | No | Not applicable |
| Drinking water facilities | No | Not applicable |
| Emergency evacuation | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Security | No | Not applicable |
| Letter box | No | Not applicable |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| type A | NA | Rs 13.16 lakh | Rs 18.75 lakh |
| type B | NA | Rs 13.16 lakh | Rs 18.75 lakh |
| type C | NA | Rs 13.16 lakh | Rs 18.75 lakh |
| type D | NA | Rs 13.16 lakh | Rs 18.75 lakh |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | rahul patel |
| Engineer | snehal patel |
Documents filed19
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/PADRA/Others/RAA04551/010119 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect's certificate (Form 1) | 31 Mar 2019 |
| Engineer's certificate (Form 2) | 31 Mar 2019 |
| Site photograph, type A | 31 Mar 2019 |
| Site photograph, type A | 31 Mar 2019 |
| Site photograph, type B | 31 Mar 2019 |
| Site photograph, type B | 31 Mar 2019 |
| Site photograph, type C | 31 Mar 2019 |
| Site photograph, type C | 31 Mar 2019 |
| Site photograph, type D | 31 Mar 2019 |
| Site photograph, type D | 31 Mar 2019 |
| RERA registration certificate | 1 Jan 2019 |
| Directors' report (2 of 3) | - |
| Directors' report (3 of 3) | - |
| Project photograph | - |
| Audited balance sheet (1 of 3) | - |
| Audited balance sheet (2 of 3) | - |
| Audited balance sheet (3 of 3) | - |
| Audited profit and loss statement (2 of 3) | - |
| Audited profit and loss statement (3 of 3) | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Vadodara
Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.
Keep meera 26 residency on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Padra2,900+ in Vadodara
Filed coordinates, straight-line distance. 32 registered projects within 2 km.
AKSHAR HEIGHTS
akshar heights
Vishranti Heights
BHARGAVI ENTERPRISE
HAJI PARK
Tawakkal Devlopers
VRAJ VIHAR
GAJANAN ENTERPRISE
BAG E FATIMA
MOINUDDIN
PARKWOOD LIFESTYLE
Shreeji Astha Enterprise
See every Vadodara project, with the district possession charts
Builder: SAMARTH SURESHBHAI PATEL Proprietorship of S P BUILDERS
SAMARTH SURESHBHAI PATEL Proprietorship of S P BUILDERS has 3 registrations on GujRERA, including meera 26 residency and Meera 48 residency. Read the full track record. See more projects on the Vadodara district page.
Frequently asked questions
What are my rights if meera 26 residency is delayed beyond 31 Dec 2020?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.
How do I verify and contact the developer of meera 26 residency?
The registered promoter entity is SAMARTH SURESHBHAI PATEL Proprietorship of S P BUILDERS, an individual/propritorship as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.
Is my payment protected in meera 26 residency?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at meera 26 residency?
The professionals named in the filing: Architect: rahul patel; Engineer: snehal patel. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in meera 26 residency?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.
Report an error Share feedback