MEADOWS BY ARANYA
RG-GJ-51829 · RERA PR/GJ/VADODARA/VADODARA/Vadodara Municipal Corporation/RAA13541/230524/231226 · Last updated on GujRERA portal: 22 Apr 2026
Source: official GujRERA filing
Red flags
- No red flags in this filing
Clear
- Completion date never moved
Saved.
MEADOWS BY ARANYA is a Residential/Group Housing project by VIHAL REALITY in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Vadodara Municipal Corporation/RAA13541/230524/231226 on 23 May 2024. Possession is promised by 23 Apr 2027. 17 of the 31 units on this registration are recorded sold or booked, and 17 of 54 construction stages are filed complete.
At a glance
Project
- NameMEADOWS BY ARANYA
- TypeResidential/Group Housing
- Location
- RS NO 157
- FP 112
- TP 46 (CHHANI)
- VILLAGE CHHANI
- TAL & DIST
- VADODARA - 391740
- CHHANI
- Vadodara
- 391740
- Pincode391740
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR/GJ/VADODARA/VADODARA/Vadodara Municipal Corporation/RAA13541/230524/231226
- ReraGenie IDRG-GJ-51829
Builder
- NameVIHAL REALITY
- Entity typePARTNERSHIP FIRM
Key dates
Key facts
Registration and timeline
- StatusValid until 23 Apr 2027
- Registered on23 May 2024
- Promised completion23 Apr 2027
- Revised completionNone
- Buildings6 building records
- Documents filed36 files
Current status
Figures as on 22 Apr 2026, this project's latest GujRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A1 | - | - | - | 0 | 0 | 2 |
| A | - | - | - | 0 | 0 | 2 |
| B1 | - | - | - | 0 | 0 | 11 |
| B | - | - | - | 0 | 0 | 11 |
| C1 | - | - | - | 0 | 0 | 3 |
| C | - | - | - | 0 | 0 | 2 |
The full filing
Everything below is from the project's own GujRERA filing, free to read.
Construction progress by building6
As on 22 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
17 of 54 construction stages are filed complete across 6 buildings. The stage furthest along is Slabs of Super Structure, at 94%.
A147%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 60% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 60% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
A56%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 70% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 70% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 60% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
B151%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 94% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 54% |
| Sanitary fittings within the flats | 9% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 52% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 45% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 3% |
B50%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 53% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 45% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 50% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
C146%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 40% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 35% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 35% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
C48%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 45% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 40% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 50% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
Progress on shared amenities19
As on 22 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal roads and footpaths | Yes | 0% |
| Water supply | Yes | 50% |
| Sewerage (chamber, lines, septic tank, STP) | Yes | 50% |
| Storm water drains | No | Not applicable |
| Landscaping and tree planting | Yes | 0% |
| Street lighting | Yes | 0% |
| Community buildings | No | Not applicable |
| Treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Water conservation, rain water harvesting | Yes | 0% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Fire fighting | No | Not applicable |
| Drinking water facilities | Yes | 0% |
| Emergency evacuation | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Security | Yes | 0% |
| Letter box | Yes | 0% |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| B | NA | Rs 5.76 cr | Rs 3.45 cr |
| B1 | NA | Rs 5.76 cr | Rs 3.47 cr |
| C1 | NA | Rs 1.68 cr | Rs 67.35 lakh |
| C | NA | Rs 1.12 cr | Rs 51.20 lakh |
| A | NA | Rs 1.08 cr | Rs 61.50 lakh |
| A1 | NA | Rs 1.08 cr | Rs 56.15 lakh |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Tejaswini Jayendrakumar Modhiya |
| Engineer | MEHUL AMARSINGH PRAJAPATI |
Documents filed36
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Vadodara Municipal Corporation/RAA13541/230524/231226 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect's certificate (Form 1) | 22 Apr 2026 |
| Engineer's certificate (Form 2) | 22 Apr 2026 |
| Engineer's certificate annexure | 22 Apr 2026 |
| Accountant's certificate (Form 3) | 22 Apr 2026 |
| Site photograph, A1 | 22 Apr 2026 |
| Site photograph, A | 22 Apr 2026 |
| Site photograph, B1 | 22 Apr 2026 |
| Site photograph, B | 22 Apr 2026 |
| Site photograph, C1 | 22 Apr 2026 |
| Site photograph, C | 22 Apr 2026 |
| RERA registration certificate | 23 May 2024 |
| Proforma agreement for sale | - |
| Auditor's report (3 of 3) | - |
| Income tax return (3 of 3) | - |
| Project specific document | - |
| Drainage affidavit | - |
| Directors' report (3 of 3) | - |
| Approved sanctioned plan | - |
| Approved layout plan | - |
| Land location | - |
| Encumbrance certificate | - |
| Area development document | - |
| Proforma allotment letter | - |
| Brochure | - |
| Declaration in Form B | - |
| Approved building or plotting plan | - |
| NOCs from authorities | - |
| Title clearance certificate | - |
| Title report | - |
| Property card | - |
| Statutory document | - |
| Project photograph | - |
| Proforma sale deed | - |
| Audited balance sheet (3 of 3) | - |
| Audited profit and loss statement (3 of 3) | - |
| Cash flow statement (3 of 3) | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Vadodara
Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.
Keep MEADOWS BY ARANYA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near CHHANI2,900+ in Vadodara
Filed coordinates, straight-line distance. 190 registered projects within 2 km.
NYSA SKYDALE
CHALLENGE INFRASTRUCTURE
MARUTI HEIGHTS
MARUTI INFRASTRUCTURE
Siddharth Annexe 3
SHARNAM REALTY
MARUTI INFINITY
DHRUV INFRA
RAMA RESIDENCY
GHANSHYAM INFRASTRUCTURE
SHREENATHJI AANGAN
SHREENATHIJI BUILDERS PRIVATE LIMITED
See every Vadodara project, with the district possession charts
Builder: VIHAL REALITY
VIHAL REALITY has 1 registration on GujRERA, including MEADOWS BY ARANYA. Read the full track record. See more projects on the Vadodara district page.
Frequently asked questions
What are my rights if MEADOWS BY ARANYA is delayed beyond 23 Apr 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.
How do I verify and contact the developer of MEADOWS BY ARANYA?
The registered promoter entity is VIHAL REALITY, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.
Is my payment protected in MEADOWS BY ARANYA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at MEADOWS BY ARANYA?
The professionals named in the filing: Architect: Tejaswini Jayendrakumar Modhiya; Engineer: MEHUL AMARSINGH PRAJAPATI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in MEADOWS BY ARANYA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.
Report an error Share feedback