Home / Browse projects / Bharuch, Gujarat / Maharshi Villa
Maharshi Villa
RG-GJ-21124 · RERA PR/GJ/BHARUCH/BHARUCH/Others/RAA03125/090718 · Last updated on GujRERA portal: 18 Apr 2024
Source: official GujRERA filing
Red flags
- Completion date moved by 16 months
- 1 extension taken
Clear
- Nothing verified clear yet
Saved.
Maharshi Villa is a Residential/Group Housing project by DEVANI REALITY in Bharuch, Gujarat, registered with GujRERA as PR/GJ/BHARUCH/BHARUCH/Others/RAA03125/090718 on 9 Jul 2018. Possession is promised by 20 Oct 2025. The completion date has moved by 16 months from the original filing. 158 of the 176 units on this registration are recorded sold or booked, and 69 of 189 construction stages are filed complete.
At a glance
Project
- NameMaharshi Villa
- TypeResidential/Group Housing
- Location
- Serve no - 160/A
- HALDARVA
- Haldarwa
- Bharuch
- 392001
- Pincode392001
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR/GJ/BHARUCH/BHARUCH/Others/RAA03125/090718
- ReraGenie IDRG-GJ-21124
Builder
- NameDEVANI REALITY
- Entity typePARTNERSHIP FIRM
- Other registrations1 more →
Key dates
Key facts
Registration and timeline
- StatusValid until 20 Oct 2025
- Registered on9 Jul 2018
- Promised completion20 Oct 2025
- Revised completionRevised to 20 Oct 2025 (originally 30 Jun 2024)
- Buildings21 building records
- Documents filed58 files
Current status
Figures as on 18 Apr 2024, this project's latest GujRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| 1 to 10 | - | - | - | 10 | 0 | 10 |
| 11 to 19 | - | - | - | 9 | 0 | 9 |
| 20 to 28 | - | - | - | 9 | 0 | 9 |
| 29 to 45 | - | - | - | 17 | 0 | 17 |
| 46 to 60 | - | - | - | 15 | 0 | 15 |
| 61 to 72 | - | - | - | 12 | 0 | 12 |
| 73 to 78 | - | - | - | 6 | 0 | 6 |
| 79 to 80 | - | - | - | 2 | 0 | 2 |
| 81 to 88 | - | - | - | 8 | 0 | 8 |
| 89 to 96 | - | - | - | 8 | 0 | 8 |
| 97 to 100 | - | - | - | 4 | 0 | 4 |
| 101 to 115 | - | - | - | 15 | 0 | 15 |
| 116 to 129 | - | - | - | 14 | 0 | 14 |
| 130 to 134 | - | - | - | 5 | 0 | 5 |
| 135 to 138 | - | - | - | 4 | 0 | 4 |
| 139 to 144 | - | - | - | 6 | 0 | 6 |
| 145 to 151 | - | - | - | 7 | 0 | 7 |
| 152 to 157 | - | - | - | 6 | 0 | 6 |
| 158 to 162 | - | - | - | 5 | 0 | 5 |
| 163 to 168 | - | - | - | 6 | 0 | 6 |
| 169 to 176 | - | - | - | 8 | 0 | 8 |
The full filing
Everything below is from the project's own GujRERA filing, free to read.
Construction progress by building20
As on 18 Apr 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 21 buildings; the table lists the first 20.
69 of 189 construction stages are filed complete across 21 buildings. The stage furthest along is External plumbing and external plaster, at 97%.
1 to 1086%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 91% |
| Sanitary fittings within the flats | 91% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 97% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 92% |
11 to 1977%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 90% |
| Sanitary fittings within the flats | 58% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 77% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 72% |
20 to 2884%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 95% |
| Sanitary fittings within the flats | 86% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 92% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 82% |
29 to 4580%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 90% |
| Sanitary fittings within the flats | 66% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 92% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 86% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 82% |
46 to 6085%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 90% |
| Sanitary fittings within the flats | 87% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 96% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 96% |
61 to 7285%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 91% |
| Sanitary fittings within the flats | 87% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 92% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 92% |
73 to 7883%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 91% |
| Sanitary fittings within the flats | 82% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 96% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 92% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 82% |
79 to 8081%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 90% |
| Sanitary fittings within the flats | 75% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 91% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 87% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 82% |
81 to 8878%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 77% |
| Sanitary fittings within the flats | 77% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 91% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 86% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 72% |
89 to 9669%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 87% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 62% |
| Sanitary fittings within the flats | 62% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 85% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 76% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 52% |
97 to 10066%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 82% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 57% |
| Sanitary fittings within the flats | 42% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 76% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 82% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 52% |
101 to 11578%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 77% |
| Sanitary fittings within the flats | 82% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 82% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 81% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 77% |
116 to 12978%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 82% |
| Sanitary fittings within the flats | 77% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 87% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 86% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 72% |
130 to 13465%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 52% |
| Sanitary fittings within the flats | 33% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 72% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 72% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 52% |
135 to 13879%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 81% |
| Sanitary fittings within the flats | 86% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 82% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 86% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 72% |
139 to 14480%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 92% |
| Sanitary fittings within the flats | 82% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 86% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 92% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 72% |
145 to 15183%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 82% |
| Sanitary fittings within the flats | 87% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 92% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 87% |
152 to 15780%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 82% |
| Sanitary fittings within the flats | 72% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 92% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 77% |
158 to 16282%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 97% |
| Sanitary fittings within the flats | 82% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 87% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 72% |
163 to 16878%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 82% |
| Sanitary fittings within the flats | 72% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 82% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 92% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 77% |
Progress on shared amenities19
As on 18 Apr 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal roads and footpaths | Yes | 70% |
| Water supply | Yes | 70% |
| Sewerage (chamber, lines, septic tank, STP) | Yes | 70% |
| Storm water drains | Yes | 70% |
| Landscaping and tree planting | Yes | 50% |
| Street lighting | Yes | 70% |
| Community buildings | No | Not applicable |
| Treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Water conservation, rain water harvesting | Yes | 60% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 60% |
| Fire fighting | No | Not applicable |
| Drinking water facilities | Yes | 80% |
| Emergency evacuation | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Security | No | Not applicable |
| Letter box | No | Not applicable |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| 29 to 45 | NA | Rs 2.00 cr | Rs 1.70 cr |
| 46 to 60 | NA | Rs 1.64 cr | Rs 1.40 cr |
| 101 to 115 | NA | Rs 1.61 cr | Rs 1.10 cr |
| 1 to 10 | NA | Rs 1.54 cr | Rs 1.05 cr |
| 116 to 129 | NA | Rs 1.53 cr | Rs 90.00 lakh |
| 11 to 19 | NA | Rs 1.39 cr | Rs 1.20 cr |
| 61 to 72 | NA | Rs 1.31 cr | Rs 1.15 cr |
| 169 to 176 | NA | Rs 1.23 cr | Rs 1.00 cr |
| 20 to 28 | NA | Rs 1.13 cr | Rs 1.02 cr |
| 163 to 168 | NA | Rs 92.49 lakh | Rs 40.00 lakh |
| 145 to 151 | NA | Rs 87.63 lakh | Rs 70.00 lakh |
| 81 to 88 | NA | Rs 87.48 lakh | Rs 55.00 lakh |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | PANKAJ VISHWAKARMA |
| Engineer | ANIL MISTRY |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Documents filed58
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/BHARUCH/BHARUCH/Others/RAA03125/090718 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Accountant's certificate (Form 3) | 18 Apr 2024 |
| Engineer's certificate (Form 2) | 3 Apr 2024 |
| Engineer's certificate annexure | 3 Apr 2024 |
| Architect's certificate (Form 1) | 30 Mar 2024 |
| Site photograph, 1 to 10 | 22 Mar 2024 |
| Site photograph, 11 to 19 | 22 Mar 2024 |
| Site photograph, 20 to 28 | 22 Mar 2024 |
| Site photograph, 29 to 45 | 22 Mar 2024 |
| Site photograph, 46 to 60 | 22 Mar 2024 |
| Site photograph, 61 to 72 | 22 Mar 2024 |
| Site photograph, 73 to 78 | 22 Mar 2024 |
| Site photograph, 79 to 80 | 22 Mar 2024 |
| Site photograph, 81 to 88 | 22 Mar 2024 |
| Site photograph, 89 to 96 | 22 Mar 2024 |
| Site photograph, 97 to 100 | 22 Mar 2024 |
| Site photograph, 101 to 115 | 22 Mar 2024 |
| Site photograph, 116 to 129 | 22 Mar 2024 |
| Site photograph, 130 to 134 | 22 Mar 2024 |
| Site photograph, 135 to 138 | 22 Mar 2024 |
| Site photograph, 139 to 144 | 22 Mar 2024 |
| Site photograph, 145 to 151 | 22 Mar 2024 |
| Site photograph, 152 to 157 | 22 Mar 2024 |
| Site photograph, 158 to 162 | 22 Mar 2024 |
| Site photograph, 163 to 168 | 22 Mar 2024 |
| Site photograph, 169 to 176 | 22 Mar 2024 |
| RERA registration certificate | 9 Jul 2018 |
| Proforma agreement for sale | - |
| Auditor's report (1 of 3) | - |
| Auditor's report (2 of 3) | - |
| Auditor's report (3 of 3) | - |
| Income tax return (1 of 3) | - |
| Income tax return (2 of 3) | - |
| Income tax return (3 of 3) | - |
| Project specific document | - |
| Directors' report (1 of 3) | - |
| Directors' report (2 of 3) | - |
| Directors' report (3 of 3) | - |
| Commencement certificate | - |
| Approved sanctioned plan | - |
| Approved layout plan | - |
| Agreement | - |
| Land location | - |
| Encumbrance certificate | - |
| Area development document | - |
| Proforma allotment letter | - |
| Brochure | - |
| Project related document | - |
| Declaration in Form B | - |
| Project photograph | - |
| Audited balance sheet (1 of 3) | - |
| Audited balance sheet (2 of 3) | - |
| Audited balance sheet (3 of 3) | - |
| Audited profit and loss statement (1 of 3) | - |
| Audited profit and loss statement (2 of 3) | - |
| Audited profit and loss statement (3 of 3) | - |
| Cash flow statement (1 of 3) | - |
| Cash flow statement (2 of 3) | - |
| Cash flow statement (3 of 3) | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bharuch
Computed across the 200+ Bharuch projects on ReraGenie, from their own filings.
Keep Maharshi Villa on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Haldarwa200+ in Bharuch
Filed coordinates, straight-line distance. 22 registered projects within 2 km.
R K COUNTY
SHREE SAI KRUPA CREATION
SAHJANAND LUXURIA
SAHJANAND BUILD SQUARE LLP
CITY CENTER
DRA NARMADA BUSPORT PRIVATE LIMITED
WELL TRADE CENTER
WELLWORTH INFRASTRUCTURE AND DEVELOPMENT P
SHYAM RICHMOND
JALARAM DEVELOPERS
NARAYAN ARENA
NARAYAN LAND ESTATE
See every Bharuch project, with the district possession charts
Builder: DEVANI REALITY
DEVANI REALITY has 2 registrations on GujRERA, including Maharshi Villa and MAHERSHI VILLA PHASE-2. Read the full track record. See more projects on the Bharuch district page.
Frequently asked questions
What are my rights if Maharshi Villa is delayed beyond 20 Oct 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.
How do I verify and contact the developer of Maharshi Villa?
The registered promoter entity is DEVANI REALITY, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.
Is my payment protected in Maharshi Villa?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Maharshi Villa?
The professionals named in the filing: Architect: PANKAJ VISHWAKARMA; Engineer: ANIL MISTRY. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Maharshi Villa?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.