Home / Browse projects / Vadodara, Gujarat / LOTUS LIFESTYLE

Valid until 31 Jul 2028 Residential/Group Housing project

LOTUS LIFESTYLE

By LOTUS BUILDCON

RG-GJ-76040 · RERA PR/GJ/VADODARA/VADODARA/Vadodara Municipal Corporation/RAA13039/260224/310328 · Last updated on GujRERA portal: 26 Mar 2026

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Jul 2028Possession promisedno revision filed
6 of 54Construction stages doneacross 6 buildings; furthest along: Staircases, 80%
21 of 43Units unsoldnot recorded sold or booked
Jump to the 42 documents Report an error

LOTUS LIFESTYLE is a Residential/Group Housing project by LOTUS BUILDCON in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Vadodara Municipal Corporation/RAA13039/260224/310328 on 26 Feb 2024. Possession is promised by 31 Jul 2028. 22 of the 43 units on this registration are recorded sold or booked, and 6 of 54 construction stages are filed complete.

At a glance

Project

  • NameLOTUS LIFESTYLE
  • TypeResidential/Group Housing
  • Location
    • BLOCK NO 46/48 SAMA SAVLI ROAD
    • NEAR IOCL PETROL PUMP
    • VEMALI
    • VEMALI
    • Vadodara
    • 390008
  • Pincode390008
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Vadodara Municipal Corporation/RAA13039/260224/310328
  • ReraGenie IDRG-GJ-76040

Builder

  • NameLOTUS BUILDCON
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredFeb 2024PromisedJul 2028

Key facts

Registration and timeline

  • StatusValid until 31 Jul 2028
  • Registered on26 Feb 2024
  • Promised completion31 Jul 2028
  • Revised completionNone
  • Buildings6 building records
  • Documents filed42 files

Current status

51%22 of 43 units booked
23.7%Of the estimated cost spent so far

Figures as on 26 Mar 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A1---34034
A3---101
A2---303
A5---303
A4---101
A---101

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building6

As on 26 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 54 construction stages are filed complete across 6 buildings. The stage furthest along is Staircases, at 80%.

A136%
ActivityProgress
Excavation57%
Podiums (if any)Not applicable
Plinth57%
Stilt Floor51%
Slabs of Super Structure51%
Internal walls, internal plaster, floorings, doors and windows within flats25%
Sanitary fittings within the flats7%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks51%
External plumbing and external plaster, elevation, completion of terraces with waterproofing18%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing7%
A30%
ActivityProgress
Excavation0%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
A220%
ActivityProgress
Excavation33%
Podiums (if any)Not applicable
Plinth33%
Stilt Floor0%
Slabs of Super Structure35%
Internal walls, internal plaster, floorings, doors and windows within flats35%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks35%
External plumbing and external plaster, elevation, completion of terraces with waterproofing7%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
A554%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats75%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing33%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
A442%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats50%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing30%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
A0%
ActivityProgress
Excavation0%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities19

As on 26 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes35%
Water supplyYes50%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsYes0%
Landscaping and tree plantingYes80%
Street lightingYes0%
Community buildingsYes92%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingNoNot applicable
Drinking water facilitiesYes0%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes0%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area9,470 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 26.66 cr
Cost incurredRs 6.32 cr
Spent of the estimate23.72%
BuildingWingEstimatedIncurred
A1NARs 21.27 crRs 4.61 cr
A2NARs 1.81 crRs 32.82 lakh
A5NARs 1.79 crRs 1.05 cr
A3NARs 60.28 lakh-
A4NARs 59.65 lakhRs 33.65 lakh
ANARs 59.08 lakh-

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectShivani Pranay Gohil
EngineerRANJIT HARILAL SOJITRA

Documents filed42

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Vadodara Municipal Corporation/RAA13039/260224/310328 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)26 Mar 2026
Engineer's certificate (Form 2)21 Mar 2026
Engineer's certificate annexure21 Mar 2026
Architect's certificate (Form 1)20 Mar 2026
Site photograph, A118 Mar 2026
Site photograph, A318 Mar 2026
Site photograph, A218 Mar 2026
Site photograph, A518 Mar 2026
Site photograph, A418 Mar 2026
Site photograph, A18 Mar 2026
RERA registration certificate26 Feb 2024
Proforma agreement for sale-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Drainage affidavit-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Statutory document-
Project photograph-
Proforma sale deed-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

51%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one has not

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep LOTUS LIFESTYLE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near VEMALI2,900+ in Vadodara

2 kmLOTUS LIFESTYLEOther 189Dot size: filed unitsN

Filed coordinates, straight-line distance. 189 registered projects within 2 km.

Builder: LOTUS BUILDCON

LOTUS BUILDCON has 1 registration on GujRERA, including LOTUS LIFESTYLE. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if LOTUS LIFESTYLE is delayed beyond 31 Jul 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of LOTUS LIFESTYLE?

The registered promoter entity is LOTUS BUILDCON, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in LOTUS LIFESTYLE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at LOTUS LIFESTYLE?

The professionals named in the filing: Architect: Shivani Pranay Gohil; Engineer: RANJIT HARILAL SOJITRA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in LOTUS LIFESTYLE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About LOTUS LIFESTYLE. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save LOTUS LIFESTYLE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.