Home / Browse projects / Surat, Gujarat / KPM TERRA PRIME

Valid until 30 Jun 2020 Residential/Group Housing project

KPM TERRA PRIME

By PARTH DEVELOPERS

RG-GJ-20346 · RERA PR/GJ/SURAT/SURAT CITY/SUDA/RAA01147/EX1/120619 · Last updated on GujRERA portal: 7 Jan 2020

Source: official GujRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Separate project account declared
Jun 2020Possession promisedmoved 12 months from the original
36 of 54Construction stages doneacross 6 buildings; furthest along: Internal walls, 95%
86 of 163Units unsoldnot recorded sold or booked
Jump to the 37 documents Report an error

KPM TERRA PRIME is a Residential/Group Housing project by PARTH DEVELOPERS in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/SURAT CITY/SUDA/RAA01147/EX1/120619 on 29 Dec 2017. Possession is promised by 30 Jun 2020. The completion date has moved by 12 months from the original filing. 77 of the 163 units on this registration are recorded sold or booked, and 36 of 54 construction stages are filed complete.

At a glance

Project

  • NameKPM TERRA PRIME
  • TypeResidential/Group Housing
  • Location
    • KPM TERRA PRIME
    • opp bharti maiya school
    • Big Bazar Lane
    • Vesu-Rundh
    • Rundh
    • Surat City
    • Surat
    • 395007
  • Pincode395007
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/SURAT/SURAT CITY/SUDA/RAA01147/EX1/120619
  • ReraGenie IDRG-GJ-20346

Builder

  • NamePARTH DEVELOPERS
  • Entity typePARTNERSHIP FIRM
  • Other registrations11 more →

Key dates

this monthRegisteredDec 2017First promiseJun 2019Revised toJun 2020

Key facts

Registration and timeline

  • StatusValid until 30 Jun 2020
  • Registered on29 Dec 2017
  • Promised completion30 Jun 2020
  • Revised completionRevised to 30 Jun 2020 (originally 30 Jun 2019)
  • Buildings6 building records
  • Documents filed37 files

Current status

47%77 of 163 units booked
95.0%Of the estimated cost spent so far

Figures as on 7 Jan 2020, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---11011
B---42042
C---22022
D---22022
E---22022
F---44044

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building6

As on 7 Jan 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

36 of 54 construction stages are filed complete across 6 buildings. The stage furthest along is Internal walls, at 95%.

A76%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats76%
Sanitary fittings within the flats10%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing2%
B79%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats95%
Sanitary fittings within the flats10%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing10%
C80%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats95%
Sanitary fittings within the flats10%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing15%
D80%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats95%
Sanitary fittings within the flats10%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing15%
E80%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats95%
Sanitary fittings within the flats10%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing15%
F80%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats95%
Sanitary fittings within the flats7%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing15%

Progress on shared amenities19

As on 7 Jan 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes65%
Water supplyYes25%
Sewerage (chamber, lines, septic tank, STP)Yes95%
Storm water drainsYes70%
Landscaping and tree plantingYes30%
Street lightingYes15%
Community buildingsYes0%
Treatment and disposal of sewage and sullage waterYes90%
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes37%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes10%
Electrical meter room, sub-station, receiving stationYes75%
Fire fightingNoNot applicable
Drinking water facilitiesYes0%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes0%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area19,243 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 67.91 cr
Cost incurredRs 64.52 cr
Spent of the estimate95.01%
BuildingWingEstimatedIncurred
ANARs 11.32 crRs 10.75 cr
BNARs 11.32 crRs 10.75 cr
CNARs 11.32 crRs 10.75 cr
DNARs 11.32 crRs 10.75 cr
ENARs 11.32 crRs 10.75 cr
FNARs 11.32 crRs 10.75 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSANJAY PATEL
EngineerJALIL A SHEIKH

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/SURAT/SURAT CITY/SUDA/RAA01147/EX1/120619Applied Jun 2019; approved Jun 2019

Documents filed37

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/SURAT CITY/SUDA/RAA01147/EX1/120619 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)7 Jan 2020
Architect's certificate (Form 1)6 Jan 2020
Engineer's certificate (Form 2)6 Jan 2020
Engineer's certificate annexure6 Jan 2020
RERA registration certificate29 Dec 2017
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Surat

47%of this project is bookeddistrict median 39%
15%of Surat projects moved their completion datethis one moved by 12 months

Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.

Keep KPM TERRA PRIME on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Rundh2,600+ in Surat

2 kmKPM TERRA PRIMEOther 146Dot size: filed unitsN

Filed coordinates, straight-line distance. 146 registered projects within 2 km.

Builder: PARTH DEVELOPERS

PARTH DEVELOPERS has 12 registrations on GujRERA, including KPM TERRA PRIME and ARJUN VILLA. Read the full track record. See more projects on the Surat district page.

Frequently asked questions

What are my rights if KPM TERRA PRIME is delayed beyond 30 Jun 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of KPM TERRA PRIME?

The registered promoter entity is PARTH DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in KPM TERRA PRIME?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at KPM TERRA PRIME?

The professionals named in the filing: Architect: SANJAY PATEL; Engineer: JALIL A SHEIKH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KPM TERRA PRIME?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KPM TERRA PRIME. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KPM TERRA PRIME to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.