KANHA NIRMAL

By JIYA ASSOCIATES

RG-GJ-10941 · RERA PR/GJ/VADODARA/VADODARA/Others/MAA02344/EX1/290922 · Last updated on GujRERA portal: 6 May 2023

Source: official GujRERA filing

Red flags

  • Completion date moved by 40 months
  • 2 extensions taken

Clear

  • Nothing verified clear yet
Oct 2025Possession promisedmoved 40 months from the original
23 of 30Construction stages doneacross 4 buildings; furthest along: Stilt Floor, 95%
61 of 201Units unsoldnot recorded sold or booked
Jump to the 41 documents Report an error

KANHA NIRMAL is a Mixed Development project by JIYA ASSOCIATES in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/MAA02344/EX1/290922 on 12 Apr 2018. Possession is promised by 25 Oct 2025. The completion date has moved by 40 months from the original filing. 140 of the 201 units on this registration are recorded sold or booked, and 23 of 30 construction stages are filed complete.

At a glance

Project

  • NameKANHA NIRMAL
  • TypeMixed Development
  • Location
    • BESIDE DWARKESH HIGHVIEW
    • NEAR N. H. 08
    • TARSALI FLYOVER
    • TARSALII
    • Tarsali
    • Vadodara
    • 390010
  • Pincode390010
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/MAA02344/EX1/290922
  • ReraGenie IDRG-GJ-10941

Builder

  • NameJIYA ASSOCIATES
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredApr 2018First promiseJun 2022Revised toOct 2025

Key facts

Registration and timeline

  • StatusValid until 25 Oct 2025
  • Registered on12 Apr 2018
  • Promised completion25 Oct 2025
  • Revised completionRevised to 25 Oct 2025 (originally 30 Jun 2022)
  • Buildings4 building records
  • Documents filed41 files

Current status

70%140 of 201 units booked
91.8%Of the estimated cost spent so far

Figures as on 6 May 2023, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOWER B---306090
TOWER C---055
DUPLEX---35035
TOWER A---234871

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building4

As on 6 May 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

23 of 30 construction stages are filed complete across 4 buildings. The stage furthest along is Stilt Floor, at 95%.

TOWER B100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TOWER C90%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor95%
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats90%
Sanitary fittings within the flats85%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing90%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing85%
DUPLEX99%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor92%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TOWER A100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 6 May 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes80%
Water supplyYes45%
Sewerage (chamber, lines, septic tank, STP)Yes35%
Storm water drainsYes65%
Landscaping and tree plantingYes65%
Street lightingYes65%
Community buildingsYes50%
Treatment and disposal of sewage and sullage waterYes45%
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes65%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,277 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 8.97 cr
Cost incurredRs 8.24 cr
Spent of the estimate91.82%
BuildingWingEstimatedIncurred
TOWER ANARs 2.24 crRs 2.06 cr
TOWER BNARs 2.24 crRs 2.06 cr
TOWER CNARs 2.24 crRs 2.06 cr
DUPLEXNARs 2.24 crRs 2.06 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDinesh D. Dudhaiya
EngineerZARNA ASSOCIATES

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/VADODARA/VADODARA/Others/MAA02344/EX1/290922Applied Jul 2022; approved Sep 2022
ExtensionApplied Jun 2024; no approval date filed

Documents filed41

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/MAA02344/EX1/290922 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)6 May 2023
Architect's certificate (Form 1)5 May 2023
Engineer's certificate (Form 2)5 May 2023
Engineer's certificate annexure5 May 2023
Site photograph, TOWER B5 May 2023
Site photograph, TOWER C5 May 2023
Site photograph, DUPLEX5 May 2023
Site photograph, TOWER A5 May 2023
RERA registration certificate12 Apr 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

70%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one moved by 40 months

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep KANHA NIRMAL on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Tarsali2,900+ in Vadodara

2 kmKANHA NIRMALOther 138Dot size: filed unitsN

Filed coordinates, straight-line distance. 138 registered projects within 2 km.

Builder: JIYA ASSOCIATES

JIYA ASSOCIATES has 1 registration on GujRERA, including KANHA NIRMAL. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if KANHA NIRMAL is delayed beyond 25 Oct 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of KANHA NIRMAL?

The registered promoter entity is JIYA ASSOCIATES, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in KANHA NIRMAL?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at KANHA NIRMAL?

The professionals named in the filing: Architect: Dinesh D. Dudhaiya; Engineer: ZARNA ASSOCIATES. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KANHA NIRMAL?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KANHA NIRMAL. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KANHA NIRMAL to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.