Kailash Shikhar
RG-GJ-77104 · RERA PR/GJ/VADODARA/VADODARA/Others/RAA04877/EX2/170222 · Last updated on GujRERA portal: 27 Jun 2022
Source: official GujRERA filing
Red flags
- Completion date moved by 30 months
- 2 extensions taken
Clear
- Nothing verified clear yet
Saved.
Kailash Shikhar is a Residential/Group Housing project by KAILASH INFRATECH in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/RAA04877/EX2/170222 on 19 Feb 2019. Possession is promised by 29 Jun 2022. The completion date has moved by 30 months from the original filing. 207 of the 224 units on this registration are recorded sold or booked, and 40 of 47 construction stages are filed complete.
At a glance
Project
- NameKailash Shikhar
- TypeResidential/Group Housing
- Location
- Kailash Shikhar nr Pratham Upvan
- Sun Pharma Road Atladara
- Atladara
- Vadodara
- 390012
- Pincode390012
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR/GJ/VADODARA/VADODARA/Others/RAA04877/EX2/170222
- ReraGenie IDRG-GJ-77104
Builder
- NameKAILASH INFRATECH
- Entity typePARTNERSHIP FIRM
- Other registrations1 more →
Key dates
Key facts
Registration and timeline
- StatusValid until 29 Jun 2022
- Registered on19 Feb 2019
- Promised completion29 Jun 2022
- Revised completionRevised to 29 Jun 2022 (originally 31 Dec 2019)
- Buildings7 building records
- Documents filed44 files
Current status
Figures as on 27 Jun 2022, this project's latest GujRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| E | - | - | - | 32 | 0 | 32 |
| J | - | - | - | 32 | 0 | 32 |
| K | - | - | - | 32 | 0 | 32 |
| A | - | - | - | 32 | 0 | 32 |
| B | - | - | - | 32 | 0 | 32 |
| C | - | - | - | 32 | 0 | 32 |
| D | - | - | - | 32 | 0 | 32 |
The full filing
Everything below is from the project's own GujRERA filing, free to read.
Construction progress by building7
As on 27 Jun 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
40 of 47 construction stages are filed complete across 7 buildings. The stage furthest along is Installation of lifts, at 98%.
E99%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | 100% |
| Slabs of Super Structure | Not applicable |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 96% |
J98%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | 100% |
| Slabs of Super Structure | Not applicable |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | Not applicable |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 90% |
K99%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | 100% |
| Slabs of Super Structure | Not applicable |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 95% |
A100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 98% |
B99%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | 100% |
| Slabs of Super Structure | Not applicable |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 96% |
C99%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | 100% |
| Slabs of Super Structure | Not applicable |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 96% |
D99%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | 100% |
| Slabs of Super Structure | Not applicable |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 96% |
Progress on shared amenities19
As on 27 Jun 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal roads and footpaths | Yes | 100% |
| Water supply | Yes | 100% |
| Sewerage (chamber, lines, septic tank, STP) | Yes | 100% |
| Storm water drains | Yes | 100% |
| Landscaping and tree planting | Yes | 100% |
| Street lighting | Yes | 80% |
| Community buildings | Yes | 53% |
| Treatment and disposal of sewage and sullage water | Yes | 100% |
| Solid waste management and disposal | Yes | 100% |
| Water conservation, rain water harvesting | Yes | 50% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 94% |
| Electrical meter room, sub-station, receiving station | Yes | 65% |
| Fire fighting | No | Not applicable |
| Drinking water facilities | Yes | 75% |
| Emergency evacuation | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Security | Yes | 60% |
| Letter box | No | Not applicable |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| A | NA | Rs 4.67 cr | Rs 4.61 cr |
| B | NA | Rs 4.67 cr | Rs 4.61 cr |
| C | NA | Rs 4.67 cr | Rs 4.61 cr |
| D | NA | Rs 4.67 cr | Rs 4.61 cr |
| E | NA | Rs 4.67 cr | Rs 4.61 cr |
| J | NA | Rs 4.67 cr | Rs 4.61 cr |
| K | NA | Rs 4.67 cr | Rs 4.61 cr |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Design Studio Associates Ar. Ruchir Sheth |
| Engineer | Zarna Associates |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Documents filed44
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/RAA04877/EX2/170222 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect's certificate (Form 1) | 27 Jun 2022 |
| Engineer's certificate (Form 2) | 27 Jun 2022 |
| Engineer's certificate annexure | 27 Jun 2022 |
| Accountant's certificate (Form 3) | 27 Jun 2022 |
| Site photograph, E | 27 Jun 2022 |
| Site photograph, J | 27 Jun 2022 |
| Site photograph, K | 27 Jun 2022 |
| Site photograph, A | 27 Jun 2022 |
| Site photograph, B | 27 Jun 2022 |
| Site photograph, C | 27 Jun 2022 |
| Site photograph, D | 27 Jun 2022 |
| RERA registration certificate | 19 Feb 2019 |
| Proforma agreement for sale | - |
| Auditor's report (1 of 3) | - |
| Auditor's report (2 of 3) | - |
| Auditor's report (3 of 3) | - |
| Income tax return (1 of 3) | - |
| Income tax return (2 of 3) | - |
| Income tax return (3 of 3) | - |
| Project specific document | - |
| Directors' report (1 of 3) | - |
| Directors' report (2 of 3) | - |
| Directors' report (3 of 3) | - |
| Commencement certificate | - |
| Approved sanctioned plan | - |
| Approved layout plan | - |
| Agreement | - |
| Land location | - |
| Encumbrance certificate | - |
| Area development document | - |
| Proforma allotment letter | - |
| Brochure | - |
| Project related document | - |
| Declaration in Form B | - |
| Project photograph | - |
| Audited balance sheet (1 of 3) | - |
| Audited balance sheet (2 of 3) | - |
| Audited balance sheet (3 of 3) | - |
| Audited profit and loss statement (1 of 3) | - |
| Audited profit and loss statement (2 of 3) | - |
| Audited profit and loss statement (3 of 3) | - |
| Cash flow statement (1 of 3) | - |
| Cash flow statement (2 of 3) | - |
| Cash flow statement (3 of 3) | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Vadodara
Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.
Keep Kailash Shikhar on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Atladara2,900+ in Vadodara
Filed coordinates, straight-line distance. 352 registered projects within 2 km.
SHYAMAL PARK
SHREE GANESH INFRA HOMES
AARYA EMPIRE
SHIVAM INFRA
Star City I
SAMANVAY SPARSH
AAMRAPALI RESI-COM
GAYATRI DEVELOPERS
SHREE BALAJI SKYRISE
MANAV INFRASTRUCTURE PRIVATE LIMITED
SAFAL IRIS
SAHAJANAND INFRA
See every Vadodara project, with the district possession charts
Builder: KAILASH INFRATECH
KAILASH INFRATECH has 2 registrations on GujRERA, including Kailash Shikhar and Kailash Shikhar Phase-2. Read the full track record. See more projects on the Vadodara district page.
Frequently asked questions
What are my rights if Kailash Shikhar is delayed beyond 29 Jun 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.
How do I verify and contact the developer of Kailash Shikhar?
The registered promoter entity is KAILASH INFRATECH, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.
Is my payment protected in Kailash Shikhar?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Kailash Shikhar?
The professionals named in the filing: Architect: Design Studio Associates Ar. Ruchir Sheth; Engineer: Zarna Associates. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Kailash Shikhar?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.