Home / Browse projects / Uttara Kannada, Karnataka / JUKAKU LEGACY

Registration approved No litigation declared Residential/Group Housing project

JUKAKU LEGACY

By HASMAI BUILDERS & DEVELOPERS

RG-KA-80116 · RERA PRM/KA/RERA/1274/353/PR/210826/008884 · Last updated on RERA Karnataka portal: 9 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2031Possession promisedno revision filed
0 of 16Construction stages donefurthest along: Earth work and other leveling..., 75%
18 of 18Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 64 documents Report an error

JUKAKU LEGACY is a Residential/Group Housing project by HASMAI BUILDERS & DEVELOPERS in Uttara Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1274/353/PR/210826/008884 on 21 Aug 2026. Possession is promised by 31 Dec 2031. 0 of the 18 units on this registration are recorded sold or booked, and 0 of 16 construction stages are filed complete.

At a glance

Project

  • NameJUKAKU LEGACY
  • TypeResidential/Group Housing
  • Location
    • Bhatkala
    • Uttara Kannada
    • 581320
  • Pincode581320
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1274/353/PR/210826/008884
  • ReraGenie IDRG-KA-80116

Builder

  • NameHASMAI BUILDERS & DEVELOPERS
  • Entity typePartnership Firm
  • GSTIN29AASFH9586Q1ZT
  • Authorized SignatoryABDUL VAHEED KUDROLI
  • Other registrations1 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2026PromisedDec 2031

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on21 Aug 2026
  • Promised completion31 Dec 2031
  • Revised completionNone
  • Buildings1 building record
  • Documents filed64 files

Current status

0%0 of 18 units booked
5.8%Of the estimated cost spent so far

Figures as on 9 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
JUKAKU LEGACY---18018

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 9 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 16 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 75%.

Building: 21% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work75%
Foundation footing work75%
Upto Plinth Level75%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)25%
Retaining wall (All types)75%
RCC or MS Framed structure10%
Masonry Construction0%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 9 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes0%
Emergency Evacuation servicesYes0%
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingNoNot applicable
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes0%
Community HallYes0%
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityYes0%
Swimming PoolNoNot applicable
GymYes0%
ParksNoNot applicable
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes0%
LiftsYes0%
Corridor/LobbiesYes0%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementYes0%
TerraceYes0%
Outer WallYes0%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes0%
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,011 sq m
Named landowners1
LandownerVillageDistrict
MOHAMMED SALAUDDIN SARFARAZ--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 3.87 cr
Cost incurredRs 22.62 lakh
Spent of the estimate5.85%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 3.28 crRs 19.62 lakh
Payment of taxesRs 35.00 lakh-
On-site expenditure-Site OverheadRs 15.00 lakh-
On-site expenditure-Consultants FeesRs 9.00 lakhRs 3.00 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectM SADANANDA BHAT
EngineerSUBRAMANYA
Chartered AccountantSATHISH SHETTY

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed64

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1274/353/PR/210826/008884 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: CA CERTIFICATE-JL-Q2 (26-27).pdf9 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: ARCH CERTIFICATE - JL -Q2 (26-27).pdf9 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: ENG CERTIFICATE - JL - Q2 (26-27).pdf9 Oct 2026
Q2 2026-27 Water supply and sewage board9 Oct 2026
Q2 2026-27 KPTCL- BESCOM9 Oct 2026
RTC, survey 9999 NAWAYATH-
Mutation, survey 9999 NAWAYATH-
Encumbrance Certificate, survey 9999 NAWAYATH-
Conversion/Alienation Order, survey 9999 NAWAYATH-
Sale/Title/Gift Deed, survey 9999 NAWAYATH-
JDA, survey 9999 NAWAYATH-
Khatha, survey 9999 NAWAYATH-
Registration CertificateFile: firm regsitartion.pdf-
GST CertificateFile: GST.pdf-
Partnership DeedFile: Partnership Deed.pdf-
Partner Details-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: Form 1 Jukaku Legacy.pdf-
Certificate issued by Architect Form 2File: FORM 2.pdf-
Certificate issued by Engineer Form 3File: Engineer Certificate Form 3.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: litigation affidavit.pdf-
Balance Sheet 2024 - 2025File: BS AY 2026-27.pdf-
Audited Profit and Loss Statement 2024 - 2025File: PL AY 2026-27.pdf-
BUILDING LICENSE - JL_compressed-
Jukaku Legacy Approved Plan-
approved plan final-
stability certificate with licence and declaration-
Specification-
BROCHURE - JL-
proforma AOS-
proforma allottment letter-
form b-
affidavit 3(1)-
JDA affidavit-
search report-
MESCOM NOC - JL-
water noc-
UGD noc-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Estimation-
Village map-
STP DRAWING - JL-
MESCOM FEE RECEIPT - JL-
FORM 5-
Engineer From-6-
location map with boundary point-
ADLR Sketch-plot-
Title deed-
Carpet Area Statement-
Land Cost Calculation-
Borewell water Availability-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 under way, not due yet
ProjectLocationStatusPromisedDelivered
NAWAYATH RESIDENCYPLAN SHOING RESIDENTIAL BUILDING (APARTMENT) IN , S.N.9999 PLOT NO.207 E-SWATTU (9-1-101-12) WARD NO.9 BHATKALOngoingJul 2030Not due yet

How this compares with Uttara Kannada

0%of this project is bookeddistrict median 27%
22%of Uttara Kannada projects moved their completion datethis one has not
0%of Uttara Kannada registrations are shown as withdrawn or revokedthis one is not

Computed across the 100+ Uttara Kannada projects on ReraGenie, from their own filings.

Keep JUKAKU LEGACY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Uttara Kannada100+ in Uttara Kannada

Builder: HASMAI BUILDERS & DEVELOPERS

HASMAI BUILDERS & DEVELOPERS has 2 registrations on RERA Karnataka, including NAWAYATH RESIDENCY and JUKAKU LEGACY. Its filings declare 1 earlier project, none of them declared completed. Read the full track record. See more projects on the Uttara Kannada district page.

Frequently asked questions

What are my rights if JUKAKU LEGACY is delayed beyond 31 Dec 2031?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of JUKAKU LEGACY?

The registered promoter entity is HASMAI BUILDERS & DEVELOPERS, a partnership firm as per the filing. Its GSTIN 29AASFH9586Q1ZT can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in JUKAKU LEGACY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at JUKAKU LEGACY?

The professionals named in the filing: Architect: M SADANANDA BHAT; Engineer: SUBRAMANYA; Chartered Accountant: SATHISH SHETTY. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in JUKAKU LEGACY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About JUKAKU LEGACY. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save JUKAKU LEGACY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.