RG-KA-42486 · RERA PRM/KA/RERA/1259/479/PR/191125/008260 · Last updated on RERA Karnataka portal: 14 Oct 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
JEWEL PARADISE is a Mixed Development project by Redbricks in Dharwad, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1259/479/PR/191125/008260 on 19 Nov 2025. Possession is promised by 31 Mar 2030. 0 of the 37 units on this registration are recorded sold or booked, and 0 of 16 construction stages are filed complete.
At a glance
Project
- NameJEWEL PARADISE
- TypeMixed Development
- Location
- Hubballi
- Dharwad
- 580023
- Pincode580023
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1259/479/PR/191125/008260
- ReraGenie IDRG-KA-42486
Builder
- NameRedbricks
- Entity typePartnership Firm
- GSTIN29ABFFR2964N1ZG
- Authorized SignatoryRikabchand Jain
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on19 Nov 2025
- Promised completion31 Mar 2030
- Revised completionNone
- Buildings1 building record
- Documents filed101 files
Current status
Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| JEWEL PARADISE | - | - | - | - | - | 37 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 14 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 16 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 0%.
Building: 0% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 0% |
| Foundation footing work | 0% |
| Upto Plinth Level | 0% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 0% |
| Retaining wall (All types) | Not applicable |
| RCC or MS Framed structure | 0% |
| Masonry Construction | 0% |
| Plastering inside , outside & Ceiling | 0% |
| Joinery: Doors, Windows, Ventilators etc | 0% |
| Basic work of Water supply, Sanitary and Electrification | 0% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 0% |
| Railing and Grill fixing | 0% |
| Electrification, Water supply and Sanitary Finishing | 0% |
| Painting | 0% |
| Fire prevention and fire fighting fitting and fixture with network | 0% |
| Weather Proof work(tile,concrete) | Not applicable |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 0% |
| Internal and External work including landscapes as per sanctioned drawings | 0% |
Progress on shared amenities32
As on 14 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 0% |
| Sewage and Drainage System | Yes | 0% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 0% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Solid waste management and disposal | No | Not applicable |
| Emergency Evacuation services | No | Not applicable |
| Internal Roads & Footpaths | Yes | 0% |
| Electricity supply transformer and substation | Yes | 0% |
| Storm water drains | Yes | 0% |
| Use of renewable energy | Yes | 0% |
| Sewage Treatment Plant (STP) | Yes | 0% |
| Parks & Tree planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Electricity | Yes | 0% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | No | Not applicable |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | Yes | 0% |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | 0% |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 0% |
| Lifts | Yes | 0% |
| Corridor/Lobbies | Yes | 0% |
| Fire escapes | No | Not applicable |
Land and ownership2
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Rikabchand Jain | - | - |
| Smt Sheetal W/o Satyanarayan Raibagi | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 12.96 cr | - |
| On-site expenditure-Consultants Fees | Rs 11.00 lakh | - |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Shrivatsa S Hegde |
| Engineer | Deepak Kawad |
| Chartered Accountant | Anujkumar Jainarayan Laddha |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed101
As listed on the registration, under the names the promoter filed them with; the newest 80 of 101 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1259/479/PR/191125/008260 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Q2 2026-2027 Form 4 CA.pdf | 14 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Q2 2026-2027 Form 5 Arch.pdf | 14 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Q2 2026-2027 Form 6 Eng.pdf | 14 Oct 2026 |
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 2026-27.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 Jewel Paradise.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 2026-27.pdf | 15 Jul 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Certificate.pdf | 14 Apr 2026 |
| Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect Certificate.pdf | 14 Apr 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate.pdf | 14 Apr 2026 |
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Certificate.pdf | 18 Feb 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect Certificate.pdf | 18 Feb 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate.pdf | 18 Feb 2026 |
| Registered Genaral Power of AttorneyFile: Registered Genaral Power of Attorney.pdf | 6 Nov 2025 |
| JDAFile: JDA.pdf | 6 Nov 2025 |
| JDA clarification AffidavitFile: JDA clarification Affidavit.pdf | 6 Nov 2025 |
| HESCOM NOC AFFIDAVIT JP 9454File: HESCOM NOC AFFIDAVIT JP 9454.pdf | 6 Nov 2025 |
| WATER BOARD NOC AFFIDAVIT JP 9454File: WATER BOARD NOC AFFIDAVIT JP 9454.pdf | 6 Nov 2025 |
| Detailed Estimated Cost of constructionFile: Detailed Estimated Cost of construction.pdf | 6 Nov 2025 |
| JDAFile: JDA.pdf | 7 Oct 2025 |
| JDA AffidavitFile: Affidavit JDA clarification.pdf | 7 Oct 2025 |
| Form 3 Engineer CertificateFile: Form 3 Engineer Certificate.pdf | 7 Oct 2025 |
| Allotment LetterFile: Allotment Letter.pdf | 7 Oct 2025 |
| Estimated Cost of ConstructionFile: Estimated Cost of Construction for Jewel Paradise.pdf | 7 Oct 2025 |
| Engineer Licence LatestFile: Engineer License Letest.pdf | 7 Oct 2025 |
| ITR ACK 2023-24File: ITR ACK 2023-24 Redbricks.pdf | 16 Sep 2025 |
| ITR ACK 2024-25File: ITR ACK 2024-25 Redbricks.pdf | 16 Sep 2025 |
| Profit And Loss AccountFile: Profit & Loss Account and Balance sheet.pdf | 16 Sep 2025 |
| Profit And Loss AccoutFile: Profit & Loss Account and Balance sheet.pdf | 16 Sep 2025 |
| Land Cost Value CalculationFile: Land cast calculation.pdf | 16 Sep 2025 |
| Sheetal Baig ITRFile: Sheetal Raibagi ITR ACK.pdf | 16 Sep 2025 |
| Sheetal Baig Balance sheet 2024-25File: Sheetal Raibhag Balacesheet 2024-25.pdf | 16 Sep 2025 |
| Approval DrawingFile: Approval Drawing.pdf | 16 Sep 2025 |
| Appraval LetterFile: Approval Letter.pdf | 16 Sep 2025 |
| KJP SheetFile: KJP.pdf | 16 Sep 2025 |
| ADRL MapFile: ADLR Map.pdf | 16 Sep 2025 |
| Form 3 Engineer CertificateFile: Form 3 Engineer Certificate.pdf | 16 Sep 2025 |
| Work OrderFile: Work order 2518.pdf | 16 Sep 2025 |
| TAX Paid ReceiptFile: Tax paid Receipt.pdf | 16 Sep 2025 |
| Affidavit Section 3File: Affidavit Section 3.pdf | 16 Sep 2025 |
| Engineer Certificate RenewedFile: Engineer License Letest.pdf | 16 Sep 2025 |
| Sale DeedFile: sale Deed.pdf | 16 Sep 2025 |
| ECFile: EC.pdf | 16 Sep 2025 |
| Letest ECFile: ECC.pdf | 16 Sep 2025 |
| RTC, survey 40/10 | - |
| Mutation, survey 40/10 | - |
| Encumbrance Certificate, survey 40/10 | - |
| Conversion/Alienation Order, survey 40/10 | - |
| Sale/Title/Gift Deed, survey 40/10 | - |
| Khatha, survey 40/10 | - |
| Registration CertificateFile: Firm Registration Certificate.pdf | - |
| GST CertificateFile: GST CERTIFICATE.pdf | - |
| Partnership DeedFile: Partnership Deed.pdf | - |
| Partner Details | - |
| Partner Details | - |
| Certificate issued by CA Form 1File: Reg1 CA Certificate.pdf | - |
| Certificate issued by Architect Form 2File: From 2 Arichitect Certificate.pdf | - |
| Certificate issued by Engineer Form 3File: Form 3 Engineer Certificate.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: Affidavit Non Litigation.pdf | - |
| Balance Sheet 2023 - 2024File: Profit & Loss Account and Balance sheet.pdf | - |
| Balance Sheet 2022 - 2023File: Profit & Loss Account and Balance sheet.pdf | - |
| Balance Sheet 2021 - 2022File: Profit & Loss Account and Balance sheet.pdf | - |
| Audited Profit and Loss Statement 2023 - 2024File: Profit & Loss Account and Balance sheet.pdf | - |
| Audited Profit and Loss Statement 2022 - 2023File: Profit & Loss Account and Balance sheet.pdf | - |
| Audited Profit and Loss Statement 2021 - 2022File: Profit & Loss Account and Balance sheet.pdf | - |
| Income Tax Return Acknowledgement 2023 - 2024File: ITR ACK 2023-24 Redbricks.pdf | - |
| Income Tax Return Acknowledgement 2022 - 2023File: ITR Acknowledgement 2022-23.pdf | - |
| Income Tax Return Acknowledgement 2021 - 2022File: ITR Acknowledgement 2022-23.pdf | - |
| Approval Letter | - |
| Approval Drawing | - |
| Approval Drawing | - |
| Structural Stability Certificate | - |
| Project Specification | - |
| Bank Account 100% | - |
| sale Deed | - |
| Agreement of Sale Proforma JP | - |
| Allotment letter JP | - |
| Affidavit Form B | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Dharwad
Computed across the 250+ Dharwad projects on ReraGenie, from their own filings.
Keep JEWEL PARADISE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Dharwad250+ in Dharwad
Filed coordinates, straight-line distance. 13 registered projects within 2 km.
Shriya Symphony Heights
Shriya BDP Properties
NIKETAN EMERALD
NIKETAN EMERALD
Infinity Urban Suites
INFINITY PROJECTS
BANADEVI PURAM
LAXMI SAI INVESTMENTS
SHRI GURUJI GREEN PARK
CG Parivar Constructions
YESH PRESTIGE
YESH DEVELOPERS AND PROMOTERS
See every Dharwad project, with the district possession charts
Builder: Redbricks
Redbricks has 1 registration on RERA Karnataka, including JEWEL PARADISE. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Dharwad district page.
Frequently asked questions
What are my rights if JEWEL PARADISE is delayed beyond 31 Mar 2030?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of JEWEL PARADISE?
The registered promoter entity is Redbricks, a partnership firm as per the filing. Its GSTIN 29ABFFR2964N1ZG can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in JEWEL PARADISE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at JEWEL PARADISE?
The professionals named in the filing: Architect: Shrivatsa S Hegde; Engineer: Deepak Kawad; Chartered Accountant: Anujkumar Jainarayan Laddha. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in JEWEL PARADISE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback