Valid until 31 Jul 2027 Mixed Development project

HR E III

By HR SPACECON LLP

RG-GJ-91981 · RERA PR/GJ/AHMEDABAD/DASKROI/Ahmedabad Municipal Corporation/MAA14092/040924/310327 · Last updated on GujRERA portal: 22 Sep 2026

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Jul 2027Possession promisedno revision filed
1 of 9Construction stages donefurthest along: Plinth, 90%
44 of 71Units unsoldnot recorded sold or booked
Jump to the 43 documents Report an error

HR E III is a Mixed Development project by HR SPACECON LLP in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/DASKROI/Ahmedabad Municipal Corporation/MAA14092/040924/310327 on 4 Sep 2024. Possession is promised by 31 Jul 2027. 27 of the 71 units on this registration are recorded sold or booked, and 1 of 9 construction stages are filed complete.

At a glance

Project

  • NameHR E III
  • TypeMixed Development
  • Location
    • HR EIII
    • B/S CONCEPT HYUNDAI
    • SARKHEJ - SHANTIPURA ROAD
    • NR. SHANTIPURA CIRCLE
    • SARKHEJ
    • Daskroi
    • Ahmedabad
    • 382210
  • Pincode382210
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/DASKROI/Ahmedabad Municipal Corporation/MAA14092/040924/310327
  • ReraGenie IDRG-GJ-91981

Builder

  • NameHR SPACECON LLP
  • Entity typeLIMITED LIABILITY PARTNERSHIP FIRM
  • Other registrations5 more →

Key dates

this monthRegisteredSep 2024PromisedJul 2027

Key facts

Registration and timeline

  • StatusValid until 31 Jul 2027
  • Registered on4 Sep 2024
  • Promised completion31 Jul 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed43 files

Current status

38%27 of 71 units booked
12.6%Of the estimated cost spent so far

Figures as on 22 Sep 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A+B---65671

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 22 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 9 construction stages are filed complete. The stage furthest along is Plinth, at 90%.

A+B: 39% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth90%
Stilt Floor50%
Slabs of Super Structure50%
Internal walls, internal plaster, floorings, doors and windows within flats10%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities19

As on 22 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsYes0%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesYes0%
Emergency evacuationYes0%
Use of renewable energyYes0%
SecurityYes0%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,182 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 35.00 cr
Cost incurredRs 4.43 cr
Spent of the estimate12.64%
BuildingWingEstimatedIncurred
A+BNARs 35.00 crRs 4.43 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHardik Durlabhbhai Ghelani
EngineerBHARGAV DINESHBHAI PATEL

Documents filed43

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/DASKROI/Ahmedabad Municipal Corporation/MAA14092/040924/310327 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)22 Sep 2026
Engineer's certificate annexure22 Sep 2026
Accountant's certificate (Form 3)22 Sep 2026
Architect's certificate (Form 1)19 Sep 2026
Site photograph, A+B17 Aug 2026
RERA registration certificate4 Sep 2024
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Statutory document-
Project photograph-
Proforma sale deed-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

38%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one has not

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep HR E III on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near SARKHEJ5,400+ in Ahmedabad

2 kmHR E IIIOther 41Dot size: filed unitsN

Filed coordinates, straight-line distance. 41 registered projects within 2 km.

Builder: HR SPACECON LLP

HR SPACECON LLP has 6 registrations on GujRERA, including HR ELANZA and HR EXETER. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if HR E III is delayed beyond 31 Jul 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of HR E III?

The registered promoter entity is HR SPACECON LLP, a limited liability partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in HR E III?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at HR E III?

The professionals named in the filing: Architect: Hardik Durlabhbhai Ghelani; Engineer: BHARGAV DINESHBHAI PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in HR E III?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About HR E III. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save HR E III to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.