ReraGenieLog inGet a buyer report

Home / Browse projects / Mehsana, Gujarat / Heritage Township

Valid until 31 Mar 2020 Residential/Group Housing project

Heritage Township

By HERITAGE INFRACON

RG-GJ-40885 · RERA PR/GJ/MEHSANA/VISNAGAR/Others/RAA02490/EX2/161219 · Last updated on GujRERA portal: 6 Feb 2020

Source: official GujRERA filing

Red flags

  • Completion date moved by 18 months
  • 2 extensions taken

Clear

  • Separate project account declared
Mar 2020Possession promisedmoved 18 months from the original
54 of 56Construction stages doneacross 17 buildings; furthest along: Stilt Floor, 0%
0 of 77Units unsoldnot recorded sold or booked
Jump to the 56 documents Report an error

Heritage Township is a Residential/Group Housing project by HERITAGE INFRACON in Mehsana, Gujarat, registered with GujRERA as PR/GJ/MEHSANA/VISNAGAR/Others/RAA02490/EX2/161219 on 25 Apr 2018. Possession is promised by 31 Mar 2020. The completion date has moved by 18 months from the original filing. 77 of the 77 units on this registration are recorded sold or booked, and 54 of 56 construction stages are filed complete.

At a glance

Project

  • NameHeritage Township
  • TypeResidential/Group Housing
  • Location
    • Heritage Township
    • Kada Char Rasta
    • Visnagar
    • Visnagar
    • Mehsana
    • 384315
  • Pincode384315
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/MEHSANA/VISNAGAR/Others/RAA02490/EX2/161219
  • ReraGenie IDRG-GJ-40885

Builder

  • NameHERITAGE INFRACON
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredApr 2018First promiseSep 2018Revised toMar 2020

Key facts

Registration and timeline

  • StatusValid until 31 Mar 2020
  • Registered on25 Apr 2018
  • Promised completion31 Mar 2020
  • Revised completionRevised to 31 Mar 2020 (originally 30 Sep 2018)
  • Buildings17 building records
  • Documents filed56 files

Current status

100%77 of 77 units booked
99.3%Of the estimated cost spent so far

Figures as on 6 Feb 2020, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
5TO8---404
13---101
14---101
19TO22---404
35TO48---14014
57TO65---909
68---101
69---101
74TO77---404
1TO4---404
9TO12---404
15TO18---404
23TO34---12012
49TO56---808
66---101
67---101
70TO73---404

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building17

As on 6 Feb 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

54 of 56 construction stages are filed complete across 17 buildings. The stage furthest along is Stilt Floor, at 0%.

5TO8Not stated
ActivityProgress
ExcavationNot applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flatsNot applicable
Sanitary fittings within the flatsNot applicable
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofingNot applicable
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
13Not stated
ActivityProgress
ExcavationNot applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flatsNot applicable
Sanitary fittings within the flatsNot applicable
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofingNot applicable
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
14Not stated
ActivityProgress
ExcavationNot applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flatsNot applicable
Sanitary fittings within the flatsNot applicable
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofingNot applicable
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
19TO22Not stated
ActivityProgress
ExcavationNot applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flatsNot applicable
Sanitary fittings within the flatsNot applicable
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofingNot applicable
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
35TO48Not stated
ActivityProgress
ExcavationNot applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flatsNot applicable
Sanitary fittings within the flatsNot applicable
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofingNot applicable
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
57TO65Not stated
ActivityProgress
ExcavationNot applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flatsNot applicable
Sanitary fittings within the flatsNot applicable
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofingNot applicable
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
68Not stated
ActivityProgress
ExcavationNot applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flatsNot applicable
Sanitary fittings within the flatsNot applicable
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofingNot applicable
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
69Not stated
ActivityProgress
ExcavationNot applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flatsNot applicable
Sanitary fittings within the flatsNot applicable
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofingNot applicable
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
74TO77Not stated
ActivityProgress
ExcavationNot applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flatsNot applicable
Sanitary fittings within the flatsNot applicable
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofingNot applicable
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
1TO4100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
9TO12100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
15TO18100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
23TO34100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
49TO5671%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
66100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
67100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
70TO73100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable

Progress on shared amenities19

As on 6 Feb 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area15,285 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 4.64 cr
Cost incurredRs 4.61 cr
Spent of the estimate99.27%
BuildingWingEstimatedIncurred
5TO8NARs 27.32 lakhRs 27.12 lakh
13NARs 27.32 lakhRs 27.12 lakh
14NARs 27.32 lakhRs 27.12 lakh
19TO22NARs 27.32 lakhRs 27.12 lakh
35TO48NARs 27.32 lakhRs 27.12 lakh
57TO65NARs 27.32 lakhRs 27.12 lakh
68NARs 27.32 lakhRs 27.12 lakh
69NARs 27.32 lakhRs 27.12 lakh
74TO77NARs 27.32 lakhRs 27.12 lakh
1TO4NARs 27.32 lakhRs 27.12 lakh
9TO12NARs 27.32 lakhRs 27.12 lakh
15TO18NARs 27.32 lakhRs 27.12 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKapil R Modi
EngineerMukesh P Patel

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/MEHSANA/VISNAGAR/Others/RAA02490/EX1/020119Applied Sep 2018; approved Jan 2019
PR/GJ/MEHSANA/VISNAGAR/Others/RAA02490/EX2/161219Applied Sep 2019; approved Dec 2019

Documents filed56

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/MEHSANA/VISNAGAR/Others/RAA02490/EX2/161219 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)6 Feb 2020
Architect's certificate (Form 1)3 Feb 2020
Engineer's certificate (Form 2)3 Feb 2020
Engineer's certificate annexure3 Feb 2020
Site photograph, 5TO83 Feb 2020
Site photograph, 133 Feb 2020
Site photograph, 143 Feb 2020
Site photograph, 19TO223 Feb 2020
Site photograph, 35TO483 Feb 2020
Site photograph, 57TO653 Feb 2020
Site photograph, 683 Feb 2020
Site photograph, 693 Feb 2020
Site photograph, 74TO773 Feb 2020
Site photograph, 1TO43 Feb 2020
Site photograph, 9TO123 Feb 2020
Site photograph, 15TO183 Feb 2020
Site photograph, 23TO343 Feb 2020
Site photograph, 23TO343 Feb 2020
Site photograph, 23TO343 Feb 2020
Site photograph, 49TO563 Feb 2020
Site photograph, 663 Feb 2020
Site photograph, 673 Feb 2020
Site photograph, 70TO733 Feb 2020
RERA registration certificate25 Apr 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Mehsana

100%of this project is bookeddistrict median 54%
11%of Mehsana projects moved their completion datethis one moved by 18 months

Computed across the 200+ Mehsana projects on ReraGenie, from their own filings.

Keep Heritage Township on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Visnagar200+ in Mehsana

2 kmHeritage TownshipOther 13Dot size: filed unitsN

Filed coordinates, straight-line distance. 13 registered projects within 2 km.

Builder: HERITAGE INFRACON

HERITAGE INFRACON has 1 registration on GujRERA, including Heritage Township. Read the full track record. See more projects on the Mehsana district page.

Frequently asked questions

What are my rights if Heritage Township is delayed beyond 31 Mar 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Heritage Township?

The registered promoter entity is HERITAGE INFRACON, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Heritage Township?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Heritage Township?

The professionals named in the filing: Architect: Kapil R Modi; Engineer: Mukesh P Patel. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Heritage Township?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Heritage Township. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Heritage Township to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.